Estimasi Durasi Serta Pekerjaan Kritis Pada Pembangunan Block 1 Kapal ASD Tug 35 M Oktaviani Kendri; Naufal Abdurrahman Prasetyo; Hendra Saputra; Mega Gemala; Mufti Fathonah Muvariz
ABEC Indonesia Vol. 10 (2022): 10th Applied Business and Engineering Conference
Publisher : Politeknik Caltex Riau

Show Abstract | Download Original | Original Source | Check in Google Scholar

Abstract

A schedule is crucial to the success of a project so that it is completed within the specifiedtimeframe. Construction of a block on a tugboat is one of the projects used as a case study. The aim of timeestimation is to determine the length of time required to complete a block with the stages of work involved. Inorder to ensure the work process runs on a schedule, a time estimation is done before the work is performed.This data is processed via a computer program. Microsoft Project is a familiar application used in projectmanagement or to assist in the processing of a project. The purpose of this study is to estimate the constructiontime of Block 1 and the work in the critical path on the 35-meter ASD tug ship. In this study, researchersobserve and participate in the construction of a ship block using the observation method. The results obtainedfrom this study are the estimated construction time of one ship block which is built in stages from marking,cutting, fitting, quality assurance, welding and grinding, to the final inspection by the Quality Controldepartment.