Analysis of Time Overrun and Alternative Solutions using The DMAIC Framework in The 8Th-Floor Electrical Installation Project at Mall X Siti Nurul Afina; Syamsir Abduh; Hakimul Batih
Journal of Social Research Vol. 5 No. 9 (2026): Journal of Social Research
Publisher : International Journal Labs (AHU-0028405-AH.01.14 Tahun 2022)

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.55324/josr.v5i9.3381

Abstract

Time overrun is one of the most critical challenges affecting schedule performance in construction projects. This study aimed to identify the factors contributing to time overruns, evaluate schedule deviations using Earned Value Management (EVM), and propose improvement strategies through the Critical Path Method (CPM) within the DMAIC (Define, Measure, Analyze, Improve, Control) framework for the electrical installation project on the 8th floor of Mall X. A mixed-methods approach was employed by combining primary data obtained from interviews with the Project Manager, Site Engineer, Supervisor, and Quality Control personnel with secondary data from project schedules, S-curves, and progress reports. The analysis was conducted using Schedule Variance (SV), Fishbone Diagram analysis, CPM simulation, and the development of a Standard Operating Procedure (SOP). The results showed that time overrun factors included Design, Material, Management, Method, and Man, with Design, Material, and Management identified as the dominant factors (100% occurrence frequency), followed by Method (75%) and Man (50%). EVM analysis indicated that schedule deviation began in week 11, with an SV of ?12.44% at the planned completion in week 17, indicating that actual progress reached only 87.56% of the planned progress and resulted in completion delays until week 20. The CPM simulation identified the critical path A–B–D–H–K–N–O with a total duration of 103 working days (approximately 15 weeks), compared with the existing 17-week schedule based on practical experience without structured scheduling methods, indicating a potential reduction of two weeks. This study proposed CPM implementation and an SOP for Project Schedule Performance Control to minimize time overruns in similar construction projects.
Optimasi Pelepasan Beban Menggunakan Skema Pertahanan Adaptif Saat Terjadi Kondisi Gangguan Beban Lebih Pada Subsistem Mandirancan Khrisna Ismayadi S.K; Dhami Johar Damiri; Hakimul Batih
Jurnal Teknologi dan Manajemen Industri Terapan Vol. 5 No. 3 (2026): Jurnal Teknologi dan Manajemen Industri Terapan
Publisher : Yayasan Inovasi Kemajuan Intelektual

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.55826/jtmit.v5i3.2157

Abstract

Meningkatnya pertumbuhan beban pada Subsistem Mandirancan berpotensi meningkatkan kerawanan sistem tenaga listrik di wilayah tersebut. Hal tersebut dapat terjadi apabila terjadi kontingensi yang menyebabkan pembebanan lebih (overload). Sistem skema pertahanan (Defense Scheme) yang terimplementasi pada sistem kelistrikan Subsistem Mandirancan membutuhkan sebuah pengembangan disain sebagai langkah mitigasi dalam menghadapi kondisi gangguan sistem tenaga listrik beban lebih. Penelitian ini mengusulkan desain skema pertahanan adaptif yang mengintegrasikan peralatan SCADA, telekomunikasi, dan sistem proteksi dengan memanfaatkan infrastruktur Gardu Induk yang ada dan disain logika pelepasan beban yang adaptif berdasarkan kondisi real-time. Metode pengujian dilakukan menggunakan perangkat server controller, gateway, data concentrator unit, master trip defense scheme dan simulator remote station yang diintegrasikan menjadi suatu sistem skema pertahanan adaptif. Pada studi kasus kontingensi N-1 IBT 1&2 500/150kV Mandirancan dengan set point sebesar 400MW, memberikan hasil akurasi pelepasan beban tanpa deviasi dan efektivitas pelepasan target 18 Trafo 100% dengan durasi waktu aksi selama 24 ms, akurasi pelepasan beban sangat penting untuk mengurangi kelebihan jumlah pemadaman tanpa mengesampingkan kestabilan sistem tenaga listrik.