PRODUKTIVITAS TENAGA KERJA PADA PROYEK PEMBANGUNAN REVITALISASI DAN PENGEMBANGAN ASRAMA HAJI WAIHERU AMBON Tomabuji Talaohu; Tonny Sahusilawane; Maslan Abdin
Journal Agregate Vol. 2 No. 2 (2023): September
Publisher : Jurusan Teknik Sipil

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.31959/ja.v2i2.1679

Abstract

The revitalization and construction of the Waiheru Ambon hajj dormitory building, the method used in this research is the validation test, reliability test, f test and t test using the SPSS V16 tool where in this method the questionnaire data will be obtained which will then be analyzed with the SPSS V16 tool. The research results were obtained based on the results of data analysis that has been carried out to solve the problem in this research where when conducting research on project implementation such as column casting work, it is often found that the workforce is not effective and efficient when pressing the vibrator so that when dismantling the formwork you can see many columns. which is corroded, then obtained: 1) The positive influence between competence on labor productivity can be seen from the t-count of  5.149 > t-table 1.724 and sig value = 0.000 < 0.05 which means that competence is very influential in influencing labor productivity. 2) The positive effect between skills on labor productivity can be seen from the t-count of 3.732 > t table 1.724 and sig value = 0.001 < 0.05 which means that skills is very influential in influencing labor productivity. 3) The positive effect of work discipline on labor productivity can be seen from the t-count of 11.992 > t-table 1.724 and sig value = 0.000 < 0.05 which means that work discipline is very influential in influencing labor productivity. 4) The positive influence between the level of income on labor productivity can be seen from the t-count 3.968 > t-table 1.724 and sig value = 0.001 < 0.05 which means that the level of income is very influential in influencing labor productivity. 
EVALUASI KERUSAKAN DAN BIAYA PELAKSANAAN PERBAIKAN GEDUNG AUDITORIUM IAIN KOTA AMBON Yuni Kartika Akhmad; Tonny Sahusilawane; Maslan Abdin
Journal Agregate Vol. 3 No. 1 (2024): Maret
Publisher : Jurusan Teknik Sipil

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.31959/ja.v3i1.1863

Abstract

This study aims to determine the level of damage that occurred in the repair of the Ambon City IAIN Auditorium Building and also to find out how much it costs to repair the Ambon City IAIN Auditorium Building. so that buildings can operate properly and users feel comfortable, which will further assist in improving building management. In carrying out the maintenance and maintenance of buildings, many things must be done so that the building has a high investment value, in general, the research specifically aims to be able to see the extent to which the implementation and management of building maintenance and maintenance. Damage to buildings occurs due to several factors including, human factors such as negligence in the implementation and use of materials, the quality of concrete factors of natural disasters such as earthquakes, floods, and the influence of weather and climate. For this reason, it is necessary to handle building maintenance where building maintenance is an activity to maintain the reliability, strength, and durability of buildings both in terms of infrastructure and facilities so that buildings are always fit to function as they should. The method used is observation and documentation. This technique is used to determine maintenance and care managers for buildings. From the results of the analysis carried out on the evaluation of repairs and implementation costs of the Ambon City IAIN Auditorium building, the level of damage that occurred to the building was 91% while the repair costs were IDR 49,327,557.66
Perhitungan RAB dan Waktu Pekerjaan Struktur Bangunan Gedung B Sekolah Rajawali Bangsa Negeri Lama Kota Ambon : RAB Calculation and Work Time Building Structure of Building B Rajawali Bangsa School the Old Country of Ambon City Muchlis Salamun; Pieter Lourens Frans; Maslan Abdin
LITERA: Jurnal Ilmiah Mutidisiplin Vol. 1 No. 2 (2024): LITERA: Jurnal Ilmiah Multidisiplin
Publisher : Litera Academica Publishing

Show Abstract | Download Original | Original Source | Check in Google Scholar

Abstract

Calculation of the cost and time budget for construction work aims to find out how much the budget costs and how long it will take to carry out construction work on the construction of Building B of the Rajawali Bangsa Negeri Lama School, Ambon City. Based on data obtained from the authorities working on the Rajawali Bangsa School Building B Construction Project, only working drawing data was obtained. This research aims to calculate the cost of structural work and plan the time for carrying out structural work on the construction of Building B of the Rajawali Bangsa Negeri Lama School, Ambon City. This research uses a field survey method. The results of the research show that based on unit prices for the Ambon City area in 2023, work time planning uses the S Curve method, so as to know the planned time for the duration of each work item being carried out. Based on the results of the calculations, the budget plan for the cost required for the Rajawali Bangsa School Building B Structure work is Rp. 3,450,354,000.00 and the planned duration of the Rajawali Bangsa School Building B Structure work duration is 16 weeks with 112 calendar days. So it can be suggested to calculate the budget plan for the costs and time of work that has not been achieved in the form of a budget for non-structural work costs and non-structural work time.
EVALUASI KERUSAKAN DAN BIAYA PELAKSANAAN PERBAIKAN GEDUNG AUDITORIUM IAIN KOTA AMBON Yuni Kartika Akhmad; Tonny Sahusilawane; Maslan Abdin
Journal Agregate Vol. 3 No. 1 (2024): Maret
Publisher : Jurusan Teknik Sipil

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.31959/ja.v3i1.1863

Abstract

This study aims to determine the level of damage that occurred in the repair of the Ambon City IAIN Auditorium Building and also to find out how much it costs to repair the Ambon City IAIN Auditorium Building. so that buildings can operate properly and users feel comfortable, which will further assist in improving building management. In carrying out the maintenance and maintenance of buildings, many things must be done so that the building has a high investment value, in general, the research specifically aims to be able to see the extent to which the implementation and management of building maintenance and maintenance. Damage to buildings occurs due to several factors including, human factors such as negligence in the implementation and use of materials, the quality of concrete factors of natural disasters such as earthquakes, floods, and the influence of weather and climate. For this reason, it is necessary to handle building maintenance where building maintenance is an activity to maintain the reliability, strength, and durability of buildings both in terms of infrastructure and facilities so that buildings are always fit to function as they should. The method used is observation and documentation. This technique is used to determine maintenance and care managers for buildings. From the results of the analysis carried out on the evaluation of repairs and implementation costs of the Ambon City IAIN Auditorium building, the level of damage that occurred to the building was 91% while the repair costs were IDR 49,327,557.66