Interpretasi Waktu Pelaksanaan Ketika Terjadi Perubahan Keadaan: Studi Kasus Penyesuaian Harga dalam Kontrak Pembangunan Saluran Udara Tegangan Ekstra Tinggi Lampung Wisnuaji, Haryo; Sami’an, S.; Hardjomuljadi, Sarwono
SIGn Jurnal Hukum Vol 6 No 2: Oktober 2024 - Maret 2025
Publisher : CV. Social Politic Genius (SIGn)

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.37276/sjh.v6i2.400

Abstract

This normative legal research analyzes disparities in interpreting work execution timelines in implementing the price adjustment clause in the Lampung EHV Overhead Line Construction Contract, which were complicated by significant changes in circumstances. The change in the transmission line route caused delays, triggering differences in viewpoints between PLN and the contractor regarding the cut-off for price adjustment calculations. The contractor argues for using factual indicators of work completion, referring to the doctrine of rebus sic stantibus. Meanwhile, PLN adheres to indicators related to the initial commitment based on the principles of pacta sunt servanda and nemo auditur. This research uses statute, conceptual, and case approaches to examine the Lampung EHV Overhead Line Construction Contract. The research findings show that neither approach, if applied rigidly, produces a fair cut-off. Therefore, this research formulates normative parameters that link the cut-off to the most relevant indicator, plus an adjusted duration that considers the impact of changes in circumstances and internal contractor factors. These parameters aim to achieve contractual justice, legal certainty, and objective, transparent, and accountable implementation of price adjustment based on the principle of good faith.
Legal Implications of Extension of Time in Power Plant Construction Projects: A Comparative Study of FIDIC and Indonesian Law Indahwati, Amaliyah Noor; Baroroh, Eric; Wisnuaji, Haryo; Sumantri, Mahfiar Fajar Akbar; Hardjomuljadi, Sarwono; Sami’an, S.
SIGn Journal of Social Science Vol 6 No 2: Desember 2025 - Mei 2026
Publisher : CV. Social Politic Genius (SIGn)

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.37276/sjss.v6i2.565

Abstract

Disputes related to EoT in electricity EPC projects frequently escalate due to normative conflicts. This conflict arises between the time-bar clause in the FIDIC international contract standards, characterized by strict liability, and the principle of equity in Indonesian civil law. This research aims to analyze the validity of the time-bar clause in light of the principle of good faith, qualify the characteristics of excusable delay in concurrent delay situations, and reconstruct effective dispute-resolution mechanisms. The research method employed is a normative juridical approach, with comparative and empirical case study methods, applied to power plant projects. The results indicate that the application of claim rights forfeiture sanctions due to administrative notification delays possesses conditionally binding force. Such provisions can be set aside if the Service User is proven to have violated the prevention principle. Furthermore, in concurrent delay situations, national law mandates the proportional application of the apportionment principle. This research also finds that the Standing Dispute Board, as provided for in PUPR Ministerial Regulation Number 11 of 2021, is a more effective preventive instrument than arbitration for maintaining project cash flow liquidity. It is concluded that legal harmonization through teleological contract interpretation and the strengthening of Dispute Board executive regulations is imperative. The implications of these findings demand that stakeholders revise the Particular Conditions of contract to accommodate equitable administrative flexibility, ensuring legal certainty and the sustainability of national strategic infrastructure.