PENERAPAN METODE LINE OF BALANCE (LOB) DALAM OPTIMALISASI JADWAL PEMBANGUNAN PERUMAHAN GRAHA ALAM SUTRA Matoha, Anwar; Mohamad Januar Fuad; Ari Putra Rachman
RADIAL : Jurnal Peradaban Sains, Rekayasa dan Teknologi Vol. 13 No. 1 (2025): RADIAL: JuRnal PerADaban SaIns RekAyasan dan TeknoLogi
Publisher : Universitas Bina Taruna Gorontalo

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.37971/radial.v13i1.512

Abstract

This study aims to apply and analyze the Line of Balance (LoB) method for scheduling the construction of 20 type 36/108 houses in the Graha Alam Sutra Housing Complex, Hutuo Village, Limboto District, Gorontalo Regency. The research questions include the technical application of the LoB method and the evaluation of project scheduling results after implementing the method. Research data includes the S-curve, Cost Estimate Plan (CEP), network planning, and field data. The LoB method is applied through the development of a Work Breakdown Structure (WBS), activity logic diagram, and LoB graph for one house unit, which is then scaled up to 20 units simultaneously and linearly. Adjustments were made to the RAB, S-curve, and work sequence to prevent conflicts (crosses) between activities. The research results show that the LoB method successfully identified the project's critical path, minimized time deviations, and improved work rotation efficiency and field supervision. The project was completed in 110 calendar days with balanced work distribution across weeks. In conclusion, the LoB method proved effective for large-scale housing construction projects, producing a more structured, efficient, and easily monitored schedule compared to conventional methods.
PENILAIAN KINERJA SISTEM IRIGASI DAERAH IRIGASI HULUDUPITANGO LIMBOTO DENGAN APLIKASI e-PAKSI Djakaria, Mohamad Zulkarnain; Mohamad Januar Fuad; Nona Fitriana Madjowa
RADIAL : Jurnal Peradaban Sains, Rekayasa dan Teknologi Vol. 13 No. 1 (2025): RADIAL: JuRnal PerADaban SaIns RekAyasan dan TeknoLogi
Publisher : Universitas Bina Taruna Gorontalo

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.37971/radial.v13i1.511

Abstract

This study aims to identify and evaluate the performance of the irrigation system in the Huludupitango Irrigation Area located in Limboto District, Gorontalo Regency. This area serves 1,054 hectares of agricultural land and plays an important role in supporting local agricultural productivity. However, with the increasing intensity of utilization, the performance of the irrigation system has declined due to insufficient attention to the maintenance of infrastructure and facilities. This study employs the e-PAKSI method (electronic–Asset Management and Irrigation System Performance), an internet-based system for comprehensively evaluating and managing irrigation assets. Based on the evaluation results, the performance score for physical infrastructure such as main structures reached only 9.41%, while the score for distribution channels was 11.19%, with an overall total score of 20.6%. These figures indicate that the irrigation system is in poor condition and requires attention and a comprehensive maintenance program from the government.
PENILAIAN KINERJA SISTEM IRIGASI DAERAH IRIGASI HULUDUPITANGO LIMBOTO DENGAN APLIKASI e-PAKSI Djakaria, Mohamad Zulkarnain; Mohamad Januar Fuad; Nona Fitriana Madjowa
RADIAL : Jurnal Peradaban Sains, Rekayasa dan Teknologi Vol. 13 No. 1 (2025): RADIAL: JuRnal PerADaban SaIns RekAyasan dan TeknoLogi
Publisher : Universitas Bina Taruna Gorontalo

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.37971/radial.v13i1.511

Abstract

This study aims to identify and evaluate the performance of the irrigation system in the Huludupitango Irrigation Area located in Limboto District, Gorontalo Regency. This area serves 1,054 hectares of agricultural land and plays an important role in supporting local agricultural productivity. However, with the increasing intensity of utilization, the performance of the irrigation system has declined due to insufficient attention to the maintenance of infrastructure and facilities. This study employs the e-PAKSI method (electronic–Asset Management and Irrigation System Performance), an internet-based system for comprehensively evaluating and managing irrigation assets. Based on the evaluation results, the performance score for physical infrastructure such as main structures reached only 9.41%, while the score for distribution channels was 11.19%, with an overall total score of 20.6%. These figures indicate that the irrigation system is in poor condition and requires attention and a comprehensive maintenance program from the government.
PENERAPAN METODE LINE OF BALANCE (LOB) DALAM OPTIMALISASI JADWAL PEMBANGUNAN PERUMAHAN GRAHA ALAM SUTRA Matoha, Anwar; Mohamad Januar Fuad; Ari Putra Rachman
RADIAL : Jurnal Peradaban Sains, Rekayasa dan Teknologi Vol. 13 No. 1 (2025): RADIAL: JuRnal PerADaban SaIns RekAyasan dan TeknoLogi
Publisher : Universitas Bina Taruna Gorontalo

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.37971/radial.v13i1.512

Abstract

This study aims to apply and analyze the Line of Balance (LoB) method for scheduling the construction of 20 type 36/108 houses in the Graha Alam Sutra Housing Complex, Hutuo Village, Limboto District, Gorontalo Regency. The research questions include the technical application of the LoB method and the evaluation of project scheduling results after implementing the method. Research data includes the S-curve, Cost Estimate Plan (CEP), network planning, and field data. The LoB method is applied through the development of a Work Breakdown Structure (WBS), activity logic diagram, and LoB graph for one house unit, which is then scaled up to 20 units simultaneously and linearly. Adjustments were made to the RAB, S-curve, and work sequence to prevent conflicts (crosses) between activities. The research results show that the LoB method successfully identified the project's critical path, minimized time deviations, and improved work rotation efficiency and field supervision. The project was completed in 110 calendar days with balanced work distribution across weeks. In conclusion, the LoB method proved effective for large-scale housing construction projects, producing a more structured, efficient, and easily monitored schedule compared to conventional methods.