Analisis Kinerja Biaya dan Waktu dengan Metoda Earned Value serta Percepatan Sisa Pekerjaan Proyek Jembatan dengan Metoda Crashing Irfan Achmad Taufik; Anton Soekiman; Chandra Afriade Siregar
Jurnal Konstruksi Vol 23 No 2 (2025): Jurnal Konstruksi
Publisher : Institut Teknologi Garut

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.33364/konstruksi/v.23-2.2904

Abstract

This study analyzes the cost and time performance of the Sequoia Hills Bridge project in Bogor City using the Earned Value and Crashing methods. The EVM analysis results in week 8 show that time performance is slightly behind schedule (SV -1.17%) but cost performance is more economical (CV 0.17%). Overall, the project shows efficiency with an SPI of 1.30 and a CPI of 1.02, projecting completion 35 days ahead of schedule (EAS 175 days) and cost savings of IDR 40.5 million from the RAB. To meet the project owner's request for acceleration, a Crashing simulation was conducted on the remaining work with various overtime scenarios. The best scenario is adding 4 hours of overtime to critical work, resulting in an optimal duration of 165 days, which is faster than the initial remaining duration of 171 days. This study provides a reference for contractors in monitoring project performance and determining efficient and economical acceleration strategies.
Faktor-faktor Kunci Penerapan Bangunan RISHA pada Proyek Penanganan Pasca Bencana Gempa di Cianjur Kamal Komaludin; Anton Soekiman; Chandra Afriade Siregar
Jurnal Talenta Sipil Vol 9, No 1 (2026): Februari
Publisher : Universitas Batanghari Jambi

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.33087/talentasipil.v9i1.1151

Abstract

The implementation of Simple Healthy Instant Houses (RISHA) as a temporary or permanent housing solution after an earthquake has become a strategic choice for the Indonesian government. RISHA is designed to be built quickly, affordably, and earthquake-resistant. However, in its implementation, there are various challenges that hinder the effectiveness and efficiency of the implementation of this system. The purpose of this study is to identify and evaluate the main obstacles in the implementation of RISHA buildings in post-earthquake rehabilitation projects, including technical, social, and institutional aspects. This study uses a qualitative method with a case study approach focused on the earthquake-affected area in Cianjur Regency. The results of the study indicate that the main challenges include limited understanding of the local community and workforce regarding the RISHA modular system, the availability of materials and structural components at the disaster site, limited training time, and lack of coordination between stakeholders. In addition, the cultural and architectural preferences of the local community also affect the level of acceptance of the RISHA building model. Thus, a more comprehensive and participatory approach is needed in the implementation of RISHA in order to increase its effectiveness as a sustainable post-disaster solution.
Pengaruh Usia, Perawatan Dan Penggunaan Gedung Terhadap Tingkat Kerusakan Bangunan Dan Biaya Rehabilitasi Musa Rannu; Anton Soekiman; Chandra Afriade Siregar
Impression : Jurnal Teknologi dan Informasi Vol. 4 No. 3 (2025): November 2025
Publisher : Lembaga Riset Ilmiah

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.59086/jti.v4i3.1153

Abstract

ermasalahan kerusakan bangunan sekolah memberikan dampak luas, tidak hanya pada aspek fisik dan kenyamanan proses belajar mengajar, tetapi juga pada kebutuhan biaya rehabilitasi yang cukup besar. Penelitian ini bertujuan menganalisis pengaruh usia bangunan, perawatan gedung, dan penggunaan ruang kelas terhadap tingkat kerusakan bangunan, serta mengidentifikasi hubungan antara tingkat kerusakan dan biaya rehabilitasi pada 12 SMK Negeri dan Swasta di Kota Cirebon. Metode penelitian menggunakan pendekatan kuantitatif dengan analisis verifikatif berbantuan SPSS dan melibatkan 60 responden. Hasil penelitian menunjukkan bahwa usia bangunan dan perawatan gedung berpengaruh positif dan signifikan terhadap tingkat kerusakan ruang kelas, sedangkan penggunaan ruang kelas tidak memberikan pengaruh signifikan. Perawatan gedung menjadi variabel yang memiliki kontribusi pengaruh terbesar (35,7%), diikuti usia bangunan (34%), dan penggunaan ruang kelas (27,1%). Secara simultan, ketiga variabel tersebut terbukti berpengaruh signifikan terhadap tingkat kerusakan. Rata-rata tingkat kerusakan ruang kelas sebesar 36,55%, dengan rentang kerusakan 13,30% hingga 50,21%, dan rata-rata kebutuhan biaya rehabilitasi mencapai Rp107.385.050,22. Analisis korelasi menunjukkan hubungan sangat kuat antara tingkat kerusakan bangunan dan biaya rehabilitasi (r = 0,981), yang mengindikasikan bahwa semakin tinggi tingkat kerusakan, semakin besar biaya rehabilitasi yang diperlukan.   The problem of school building damage has a broad impact, not only on the physical aspects and comfort of the teaching and learning process, but also on the need for significant rehabilitation costs. This study aims to analyze the influence of building age, building maintenance, and classroom use on the level of building damage, as well as identify the relationship between the level of damage and rehabilitation costs in 12 public and private vocational schools in Cirebon City. The research method uses a quantitative approach with verification analysis assisted by SPSS and involving 60 respondents. The results show that building age and building maintenance have a positive and significant effect on the level of classroom damage, while classroom use does not have a significant effect. Building maintenance is the variable with the largest contribution (35.7%), followed by building age (34%), and classroom use (27.1%). Simultaneously, these three variables are proven to have a significant effect on the level of damage. The average level of classroom damage is 36.55%, with a range of damage from 13.30% to 50.21%, and the average rehabilitation cost reaches Rp107,385,050.22. Correlation analysis shows a very strong relationship between the level of building damage and rehabilitation costs (r = 0.981), which indicates that the higher the level of damage, the greater the rehabilitation costs required.  
Analisis Dampak Pemadatan Tanah Terhadap Kestabilan Struktur Yang Berdekatan Menggunakan Aplikasi Plaxis 2d (Studi Kasus PT. Teruna Perkasa Optimal New Factory Project, Tanggerang-Banten) Risman Dala; Agus Sulaeman; Chandra Afriade Siregar
Impression : Jurnal Teknologi dan Informasi Vol. 4 No. 3 (2025): November 2025
Publisher : Lembaga Riset Ilmiah

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.59086/jti.v4i3.1154

Abstract

Penelitian ini bertujuan untuk menganalisis dampak pemadatan tanah menggunakan vibro roller terhadap potensi keretakan struktur bangunan yang berada di sekitar area kerja. Studi ini menggunakan pendekatan kuantitatif melalui simulasi numerik berbasis finite element menggunakan perangkat lunak Plaxis 2D untuk memodelkan penurunan dan distribusi tekanan tanah akibat getaran. Hasil simulasi menunjukkan bahwa pada jarak 0,5 meter dari bangunan terjadi penurunan sebesar 2,2 cm dengan tekanan tanah 153,2 kN/m²; pada jarak 5 meter penurunan 0,97 cm (140,6 kN/m²); jarak 10 meter 0,32 cm (137,0 kN/m²); dan jarak 15 meter 0,29 cm (135,5 kN/m²). Secara teknis, nilai penurunan pada jarak 0,5 meter masih berada di bawah batas toleransi SNI 8460:2017 sebesar 2,5 cm, namun peningkatan tekanan tanah menunjukkan potensi risiko terhadap struktur tertentu dengan kondisi fondasi sensitif. Penelitian ini berkontribusi dalam memberikan batas aman operasional pemadatan getaran di area konstruksi padat, dengan rekomendasi jarak minimal 5 meter untuk mengurangi dampak deformasi dan menjaga keselamatan struktur di sekitarnya   This study aims to analyze the impact of soil compaction using a vibro roller on the potential for cracking in building structures around the work area. This study uses a quantitative approach through finite element-based numerical simulations using Plaxis 2D software to model the settlement and distribution of soil pressure due to vibration. The simulation results show that at a distance of 0.5 meters from the building, there is a settlement of 2.2 cm with a soil pressure of 153.2 kN/m²; at a distance of 5 meters, a settlement of 0.97 cm (140.6 kN/m²); a distance of 10 meters, 0.32 cm (137.0 kN/m²); and a distance of 15 meters, 0.29 cm (135.5 kN/m²). Technically, the settlement value at a distance of 0.5 meters is still below the tolerance limit of SNI 8460:2017 of 2.5 cm, but the increase in soil pressure indicates a potential risk to certain structures with sensitive foundation conditions. This research contributes to providing a safe operational limit for vibration compaction in dense construction areas, with a recommended minimum distance of 5 meters to reduce the impact of deformation and maintain the safety of surrounding structures.