ANALISIS PENGENDALIAN WAKTU DAN BIAYA MENGGUNAKAN METODE NILAI HASIL (EARNED VALUE METHOD) PADA PROYEK PERUMAHAN GRAHA CITRA KEMBANGAN DI PT SONTO PROPERTI GRESIK

Akhmad Andi Saputra (Program Studi Teknik Sipil,Fakultas Teknik, Universitas Gresik)
Bowo Leksono (Program Studi Teknik Sipil,Fakultas Teknik, Universitas Gresik)
Mu'arofah (Program Studi Teknik Sipil,Fakultas Teknik, Universitas Gresik)



Article Info

Publish Date
01 Dec 2021

Abstract

Planning and controlling time and costs are part of the overall construction project management. The existence of significant cost and time deviations indicates poor project management. Cost management and time management activities can be carried out using a method known as the Earned Value Method. The Earned Value Method is used to estimate the end time project completion and project performance. The results of the analysis using the Earned Value Method on the Graha Citra Kembangan housing development project are the project completion time ini accordance with the project qwal plan and the costs incurred are less than the budgeted cost (BAC). The difference between the contract costs (BAC) and the actual costs incurred (ACWP) reached Rp. 36.170.100. There are delays in the completion of work in several weeks of the project cycle. However, at the end of the project completion (week 40), the work was carried out in time according to schedule (estimate project plan time).

Copyrights © 2021






Journal Info

Abbrev

WahanaTeknik

Publisher

Subject

Civil Engineering, Building, Construction & Architecture Engineering Mechanical Engineering

Description

Wahana Teknik merupakan wadah publikasi ilmiah yang menyajikan hasil-hasil penelitian berupa makalah terkait bidang Teknik Mesin dan Teknik Sipil. Jurnal Wahana Teknik diterbitkan oleh Fakultas Teknik Universitas Gresik. Pada tahun 2017 jurnal Wahana Teknik terbit berkala dua kali per tahun. Makalah ...