Aplikasi Critical Path Method (CPM) dengan Crashing Program untuk Mengoptimalkan Waktu dan Biaya Proyek

Try Hardini Rahayu Mukti (Laboratorium Statistika Ekonomi dan Bisnis FMIPA Universitas Mulawarman)
Ika Purnamasari (Laboratorium Statistika Ekonomi dan Bisnis FMIPA Universitas Mulawarman)
Wasono Wasono (Laboratorium Matematika Komputasi FMIPA Universitas Mulawarman)



Article Info

Publish Date
28 Jun 2019

Abstract

The management of small and large-scale projects requires good planning, scheduling and coordination. Critical Path Method (CPM) is one of the method that has been developed to overcome the problem of managing a project. Time and cost greatly affect the success and failure of a project. A desired project is completed within a predetermined time, it can accelerate the duration of the activity with the consequence of an increase in cost. Acceleration of project duration at the lowest possible cost is called crashing program. The purpose of this study is to determine the optimal time and cost in completing the project. The data used is the type of work and time of completion of project work and wage costs of workers wages in the project development of SMP Negeri 24 Jalan Pangeran Suryanata Samarinda. Based on the analysis using the time efficient CPM method for completion of the project is 185 days. Acceleration of project completion time by using crashing program, project can be done for 157 days with increase of worker wage equal to Rp 473,802,785.32.

Copyrights © 2019






Journal Info

Abbrev

exponensial

Publisher

Subject

Computer Science & IT Decision Sciences, Operations Research & Management Economics, Econometrics & Finance Mathematics Other

Description

Jurnal Eksponensial is a scientific journal that publishes articles of statistics and its application. This journal This journal is intended for researchers and readers who are interested of statistics and its ...