Estimated Time and Cost of Realizing the Construction Work of the Education Quality Assurance Institute (LPMP) Phase II South Sulawesi. The purpose of this study is to find out all the estimated time and cost of realizing the construction work of the Education Quality Assurance Institution (LPMP) building phase II, South Sulawesi, where this research uses the S curve method with the aim of obtaining credible and valid data from the time schedule. The data collection method is carried out using the RAB method in construction, observation, and documentation projects and the results obtained are processed based on the time schedule made with the estimated time and cost realization design. The results obtained by using the estimated time schedule and realization costs, there is a 6 day time difference between planning and realization time, while the cost difference is Rp.1,506.414.776.12. from the planning budget Rp.42,492,268,405.01