PENERAPAN METODE CPM DAN CCPM UNTUK PERENCANAAN SUMBER DAYA DAN WAKTU PENYELESAIAN MULTI PROYEK

Rahayu, Sri (Unknown)
Yuliana, Pram Eliyah (Unknown)
Kelvin, Kelvin (Unknown)



Article Info

Publish Date
29 Dec 2022

Abstract

ABSTRAK Penelitian ini dilakukan pada perusahaan yang bergerak di bidang supplies dan engineering dan berlokasi di Surabaya. Perusahaan mempunyai beberapa proyek dalam waktu yang dekat maupun bersamaan. Salah satunya adalah proyek alat pengupas bawang dan proyek exhaust silencer yang harus diselesaikan sesuai dengan waktu yang ditetapkan dengan sumber daya yang terbatas. Untuk menyelesaikan hal tersebut maka pentingnya untuk dilakukan perencanaan terhadap jadwal dengan menggunakan metode critical path method dan juga critical chain project management. Pada critical path method bertujuan untuk melihat kegiatan mana saja yang harus menjadi perhatian perusahaan dalam pelaksanaannya agar tidak menyebabkan keterlambatan penyelesaian. Lalu dengan mmetode critical chain project management bertujuan untuk mengatur penjadwalan terhadap tenaga kerja yang melakukan pekerjaan terhadap beberapa proyek. Setelah melakukan analisa, dari hasil penelitian didapatkan untuk proyek alat pengupas bawang pada metode critical path method adalah 56 hari dari waktu normal 59 hari, sedangkan untuk proyek exhaust silencer 46 hari dari waktu normal 47. Lalu untuk metode critical chain project management, kegiatan multiproyek mengalami kemunduran selama 15 hari pada proyek alat pengupas bawang, namun hal tersebut masih berada dalam project buffer.  ABSTRACTThis research was conducted at supplies and engineering company in Surabaya. The company has several projects in the near future or at the same time. One of them is the onion peeler project and the exhaust silencer project which must be completed in accordance with the specified time with limited resources. To solve this problem, it is important to plan the schedule using the critical path method and also critical chain project management. The critical path method aims to see which activities the company should pay attention to in its implementation so as not to cause delays in completion. Then the critical chain project management method aims to regulate the scheduling of workers who work on several projects. After conducting the analysis, the research results obtained for the onion peeler project on the critical path method is 56 days from the normal time of 59 days, while for the exhaust silencer project it is 46 days from the normal time of 47. Then for the critical chain project management method, multi-project activities experience 15 day setback on the onion peeler project, but it's still in the project buffer.

Copyrights © 2022






Journal Info

Abbrev

jiso

Publisher

Subject

Environmental Science Industrial & Manufacturing Engineering Transportation

Description

JISO merupakan jurnal ilmiah yang menjadi wadah bagi para peneliti, akademisi dan praktisi untuk mempublikasikan hasil penelitiannya di bidang rekayasa sistem dan industri diterbitkan oleh LPPM Universitas Maarif Hasyim Latif (eISSN 2622-898X) (pISSN 2622-8971). Dengan fokus dan materi tentang ...