Evaluasi Penjadwalan Proyek Waste Water Treatment Plan Menggunakan Metode Precedence Diagram Method dan Crashing

Renata Alvita Loka Leonsi (Unknown)
Renanda Nia Rachmadita (Unknown)
Aulia Nadia Rachmat (Unknown)



Article Info

Publish Date
06 Jul 2023

Abstract

Abstract - Scheduling is needed to run the project optimally, efficiently and according to the planned schedule. There are several factors that make the project late. The causes are ineffective working hours, late arrival of materials, and high work productivity. Waste water treatment plan is one of the many projects undertaken by PT.Samudra Mas Nusantara. In this project there was a delay of 34 days from the planned duration of 75 days to 109 days. The scheduling method used is the Precedence Diagram Method. The duration of project completion is accelerated by analyzing the acceleration of each activity. The s-curve is used to see the progress of the project each week. The results of the research show that there is 1 critical path, namely the path with activities A-B1-B2-C1-C2-D111-D121-D131- D141-D21-D22-D23-D24-D25-E1-E4-F-G H. The duration of the activity can be accelerated by 35 days from 109 days to 74 days with an increase in costs of 3.03% from Rp.1,822,201,012- up to Rp1,877,287,312,-.

Copyrights © 2021






Journal Info

Abbrev

CDMA

Publisher

Subject

Control & Systems Engineering Engineering Industrial & Manufacturing Engineering Materials Science & Nanotechnology Mechanical Engineering

Description

The aim of the Conference on Design Manufacture Engineering and Its Application (CDMA) is to provide a scientific platform for researchers, academics, and professionals to share and disseminate original research, innovative ideas, and practical developments in the fields of design engineering, ...