Analisis Penjadwalan Perbaikan Gas Turbine Part dengan Metode PERT dan Gantt Chart pada Industri MRO

Rajagukguk, Leonard Yopandi (Unknown)
Winarsih, Neneng (Unknown)
Rahma, Rana Ardila (Unknown)
Arrafi, Muhammad Naufal (Unknown)



Article Info

Publish Date
28 Apr 2026

Abstract

Delays in the implementation of repair projects can significantly impact a company’s reputation and operational continuity. One of the main causes of such delays is the absence of effective project activity scheduling, which leads to untimely completion of tasks. Therefore, this study was conducted to minimize delays in the gas turbine repair process. By applying the Program Evaluation and Review Technique (PERT) and Gantt Chart methods to improve scheduling efficiency, this study aims not only to enhance the effectiveness of repair scheduling but also to forecast the achievable repair capacity within a one-year period, with a specific focus on the Transition Piece component. The findings indicate that the repair duration can be accelerated by 9%, and the repair capacity that can be achieved within one year is 22.22%. Keywords: Gantt Chart, PERT, Project Management, Scheduling  

Copyrights © 2026






Journal Info

Abbrev

indstrk

Publisher

Subject

Control & Systems Engineering Decision Sciences, Operations Research & Management Economics, Econometrics & Finance Engineering Industrial & Manufacturing Engineering

Description

INDUSTRIKA is a research journal which facilitates the publication of scientific articles in the field of Industrial Engineering. The published articles in INDUSTRIKA can be the result of research and literature review. Some of the topics are including: Business and strategy; decision analysis ...