Management is one of the key factors in the success of project implementation. Constraints in management, such as errors in istimating the time needed to complete the project during the planning stage, or various unforeseen obstacles, can hinder project execution. This study aims to indetify the factors causing delays in the Bulo-Bungin road improvement project in Enrekang Regency and to determine the most significant delay factors. The research results show that the factors influencing the delay in project completion, based on 49 indicators used to measure the research variables, have correlation coefficients greater than the table r = 0.279, indicating the questionnaire is valid. Based on the analysis, the five main factors causing delays in the Bulo-Bungin road project are Equipment usage skills 3.74, Workforce skills 3.70, Workforce discipline 3.64, Rework due to defect or errors 3.64, Communication between workers and foremen 3.62.