METODE PEMASANGAN ALAT FORM TRAVELER PADA PENGECORAN SEGMEN 3-4 TERHADAP WAKTU PELAKSANAAN PEKERJAAN PROYEK LRT PHASE 1B VELODROME-MANGGARAI JAKARTA TIMUR

Damar Gusti Astapati (Program Studi Teknik Sipil, Fakultas Teknik, Universitas Majalengka)
Erni Sari Lumban Toruan (Program Studi Teknik Sipil, Fakultas Teknik, Universitas Majalengka)



Article Info

Publish Date
01 Oct 2026

Abstract

The construction of the Jakarta LRT Phase 1B Velodrome-Manggarai project applies the Balanced Cantilever Method to build prestressed concrete box girder segments in a dense urban corridor. A Form Traveler supports the casting of each segment without ground scaffolding, yet field evidence on how its installation sequence shapes schedule performance remains limited. This study addresses that gap by combining a systematic account of the installation method on segments 3 and 4 with a quantitative deviation analysis, a schedule performance index, and a structured risk assessment, an integration rarely presented in prior segmental bridge studies. Data were collected through field observation, documentation, and discussion with project engineers over one month at pier P46B to P50B. Planned duration in the Method Statement was compared with actual duration on site for every work stage, then analyzed descriptively using mean, standard deviation, and a schedule performance index. Results show that Form Traveler installation follows a systematic eight-stage sequence, and one segmental cycle, planned for ten working days under a 24-hour shift system, records an average stage deviation of 7.1 percent (SD 3.6 percent) with a schedule performance index of 0.94, indicating a slightly behind-plan but controlled pace. Technical factors, such as equipment readiness and hydraulic condition, combine with non-technical factors, such as weather and workspace limitation, to shape this pattern, while risk assessment identifies lifting and working-at-height as top-priority risks. The disciplined, risk-aware installation method keeps schedule performance stable under constrained urban conditions, while the single-cycle scope limits generalization and calls for multi-cycle validation

Copyrights © 2026






Journal Info

Abbrev

stima

Publisher

Subject

Computer Science & IT Control & Systems Engineering Industrial & Manufacturing Engineering Mechanical Engineering Transportation

Description

Prosiding SEMINAR TEKNOLOGI MAJALENGKA (STIMA) adalah publikasi ilmiah yang memuat hasil-hasil penelitian orisinal dan terkini dari para akademisi, peneliti, dan praktisi di berbagai bidang teknik dan manajemen. Prosiding ini memiliki sifat multidisiplin, berfokus pada integrasi ilmu pengetahuan ...