The construction of the Sungai Cipelang Bridge at STA. 56+470 on the Cisumdawu Toll Road Section 6A is a critical structure connecting sections separated by the Cipelang River in Ujung Jaya, Sumedang. This study examines technical problems in constructing this approximately 100-meter precast segmental box girder bridge. Field observations over a three-month period focused on six construction activities: pier head construction, wall box underpass concreting, scaffolding installation, top slab concreting, girder stressing, and girder erection. The methodology combined direct field observation, documentation analysis, and comparative evaluation against SNI 2847:2019 and ACI 347R-14. Results show that reinforcement spacing errors in the pier head were corrected through reinstallation and stricter supervision. Concrete segregation risk in the wall box underpass was managed by pouring in two stages of 3.2 meters each. Scaffolding instability was resolved through joint inspection and jack calibration. Top slab leakage was prevented using polyethylene membrane lining. Stressing errors were addressed through equipment recalibration, and erection challenges were overcome through improved survey coordination and rescheduling. These findings show that effective problem-solving in bridge construction depends on rigorous technical supervision, adaptive methodology, and inter-team coordination, offering practical insights for similar toll road bridge construction projects in Indonesia.
Copyrights © 2026