Anticipation and Solution of Equipment Cost Overrun Factor in Toll Road Construction Project Isfahani, Muhammad Nafhan; Sumirin, Antonius; Wibowo, Kartono
JURNAL TEKNIK SIPIL-ARSITEKTUR Vol. 24 No. 1 (2025): EDISI BULAN MEI 2025
Publisher : FTSP Universitas Jayabaya

Show Abstract | Download Original | Original Source | Check in Google Scholar

Abstract

This paper presents research on anticipation and solutions for equipment cost overruns on toll road construction projects in Jabodetabek. A survey was conducted with 76 respondents (Managers, Consultants, Contractors). The dominant factor causing equipment cost overrun is breakdown of heavy equipment (mean = 4.32), followed by delay in mobilization (mean = 4.18). Preventive maintenance schedules and contractual penalty clauses are established as key solutions.