EVALUASI KINERJA WAKTU DAN BIAYA PADA PROYEK WU TOWER BANDUNG Utomo, Bagus Krido; Kusmana, Dody
Sistem Infrastruktur Teknik Sipil (SIMTEKS) Vol 4 No 2 (2024): SIMTEKS - September
Publisher : Program Studi Teknik Sipil, Fakultas Teknik, Universitas Sangga Buana

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.32897/simteks.v4i2.3947

Abstract

The research evaluates the time and cost performance of the Wu Tower Project in Bandung using the Earned Value (EV) method. The scope of the research includes a comprehensive literature study on the concept of Earned Value (EV) and its application in the evaluation of time and cost performance of construction projects. In addition, the research also includes the measurement of the actual time and cost performance of the Wu Tower Project using the EV method, analysis of influencing factors, especially those related to design complexity, scope changes, and labor, as well as comparison of actual time and cost performance with predetermined standards. The performance of the project implementation time in the 1st month (one) to the 8th month (eight) is progressing well as indicated by the SV (Schedule Variant) variant value is positive or the SPI performance index ≥ 1, this indicates that the work is progressing both in schedule and budget. For the 9th (ninth) to 11th (eleventh) month, the SV (Schedule Variant) value is negative, which means that the work is delayed, but the project completion expenditure budget is still quite efficient because the SPI value is ≥ 1. Based on the Performance Index value, the overall SPI value gets an average value of 1.73, which means that the project is progressing towards time performance, while the CPI value generally gets an average SPI value ≥ 1, which means that the costs incurred are more economical, so that the project is more efficient.
EVALUASI EFISIENSI BIAYA DAN WAKTU ANTARA METODE KONVENSIONAL DAN PRACETAK DALAM PEKERJAAN DRAINASE U-DITCH DI RUAS JALAN NASIONAL JAMBI Iskandar, Bugie Rastapi; Kusmana, Dody
Sistem Infrastruktur Teknik Sipil (SIMTEKS) Vol 4 No 2 (2024): SIMTEKS - September
Publisher : Program Studi Teknik Sipil, Fakultas Teknik, Universitas Sangga Buana

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.32897/simteks.v4i2.3949

Abstract

Cost and time efficiency are two crucial aspects that influence the success of a construction project. Conventional methods are usually used because they are considered more flexible and easily adapted to field conditions. However, the precast method is increasingly in demand because it is claimed to be more efficient and faster in implementation. This research uses a case study approach by collecting primary and secondary data from planned work. Cost data is obtained from the detailed cost budget (RAB), while time data is taken from the project implementation schedule (time schedule). The analysis was carried out by comparing the total costs and time duration between conventional and precast methods using the 2018 Bina Marga Specifications. The research results show that the precast method has advantages in time efficiency, with an average construction time that is shorter than conventional methods. However, in terms of costs, precast methods tend to be more expensive in the initial stages due to the high production costs of precast elements.