ANALISIS PERCEPATAN WAKTU PELAKSANAAN PROYEK DENGAN PENAMBAHAN JAM KERJA (STUDI KASUS PEMBANGUNAN LAHAN PARKIR RUMAH SAKIT BANGLI MEDIKA CANTI) I PUTU YANA HERMAWAN; I GEDE NGURAH SUNATHA; ANAK AGUNG RATU RITAKA WANGSA; KADEK ANDY SADEWA
GANEC SWARA Vol 17, No 2 (2023): Juni 2023
Publisher : Universitas Mahasaraswati K. Mataram

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.35327/gara.v17i2.467

Abstract

Implementation of a construction project has a series of activities or jobs that are complex and interdependent on one another. Construction project development is carried out in several stages of work, one of which is making a work schedule. Work schedules are made to make it easier for each activity to be carried out sequentially and on time. In the implementation of the Parking Lot Construction Project at Bangli Medika Canti Hospital, there was a delay in weekly progress. To anticipate changes in implementation time, an acceleration of implementation time is carried out using the method of adding overtime hours. In this research, acceleration of implementation time was carried out using the method of adding overtime hours based on Microsoft Project. The data used in this study are in the form of a planned time schedule, realization time schedule, and weekly reports. The analysis was carried out to obtain the results of activities that can be accelerated and the project implementation time after being accelerated using the method of adding overtime hours. From the results of the analysis of the Microsoft Project, there are activities that can be accelerated, namely as many as 23 work items. After analyzing with the method of adding overtime hours on the implementation of the Parking Lot Development Project at Bangli Medika Canti Hospital, the project time was 122 days. This time is the same time at the initial planning. In the process of implementing the project, there was a delay in progress which resulted in a postponement of the project plan schedule to 129 days.
KAJIAN PERENCANAAN PASAR INDUK KABUPATEN BADUNG DENGAN PENDEKATAN TATA RUANG, ARSITEKTUR, DAN BUDAYA LOKAL BALI I MADE SASTRA WIBAWA; TJOKORDA ISTRI PRAGANINGRUM; ANAK AGUNG GDE SUTRISNA WIJAYA PUTRA; MADE WAHYU WIJAYA; I PUTU YANA HERMAWAN; I KETUT AGUS KARMADI
GANEC SWARA Vol 18, No 3 (2024): September 2024
Publisher : Universitas Mahasaraswati K. Mataram

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.35327/gara.v18i3.1060

Abstract

In the central market planning project in Badung Regency, Bali, the main objective was to develop an economic center that combines cultural elements with sustainable economic growth. The planning goes beyond the traditional paradigm of development by integrating cultural, social, environmental, architectural, civil engineering and economic factors, creating an entity that carries more value than just commercial transactions. The central market is intended to represent a balance between cultural heritage and the dynamics of modernity, with reference to the principles of Tri Hita Karana (balance with God, fellow humans, and the natural environment) as well as the concept of Hulu - Teben which directs the organization of space based on the flow of the river. The Tri Mandala and Sanga Mandala concepts guide the zone mapping and building orientation, optimizing air circulation and natural lighting. The market architecture adopts traditional Balinese elements such as limasan and jineng roof forms, and utilizes natural materials such as red bricks and temple stones. A purposeful and iconic signage system, including the Ratu Niang Sakti statue, became an important part of the design. The result is a synergy between cultural values and global progress, forming a neighborhood that functions not only as a place of transaction, but also as a vehicle for cultural preservation and a driver of inclusive economic growth. The project encourages active community participation in the development process, accelerates the welfare of local communities, and improves the competitiveness of the region. Thus, the project achieves its goal not only as physical infrastructure, but also as a platform that integrates cultural significance and economic dynamism within the framework of sustainable development