Claim Missing Document
Check
Articles

Found 13 Documents
Search

ANALYSIS OF HEAVY EQUIPMENT PERFORMANCE ON THE PROBOLINGGO-BANYUWANGI TOLL ROAD PROJECT KM SECTION KM 09 + 125 TO KM 09 + 725 BILHAN GAMALIEL HARTANTO; YONAS PRIMA ARGA RUMBYARSO
INTERNATIONAL JOURNAL OF MULTI SCIENCE Vol. 4 No. 03 (2024): INTERNATIONAL JOURNAL OF MULTISCIENCE - EDITION SEPTEMBER - DECEMBER 2024
Publisher : CV KULTURA DIGITAL MEDIA

Show Abstract | Download Original | Original Source | Check in Google Scholar

Abstract

Infrastructure projects, especially in flexible pavement works, are highly dependent on the utilization of heavy equipment. The use of such heavy equipment is an important element that determines the success of asphalt road construction, with the production capacity of heavy equipment being a major factor in the progress of project implementation. Therefore, the analysis of production volume capacity is very important. This study aims to determine the production volume capacity of construction works on the Probolinggo - Banyuwangi Toll Road KM 09+125 to KM 09+725, including an analysis of the capacity of asphalt finisher, dump truck, pneumatic tire roller, and tandem roller. The volumetric method was applied in this study to calculate the volume capacity and productivity of heavy vehicles. The results of the analysis showed that the calculated volume and productivity of the heavy equipment had met the target according to the planned schedule.
PERFORMANCE EVALUATION OF HEAVY EQUIPMENT IN THE JAKARTA LRT PHASE 1B PROJECT BILHAN GAMALIEL HARTANTO
INTERNATIONAL JOURNAL OF MULTI SCIENCE Vol. 5 No. 02 (2025): INTERNATIONAL JOURNAL OF MULTISCIENCE - MAY -AUGUST 2025
Publisher : CV KULTURA DIGITAL MEDIA

Show Abstract | Download Original | Original Source | Check in Google Scholar

Abstract

Infrastructure projects, particularly in the development of mass transportation systems such as light rail transit (LRT), are highly dependent on the role of heavy equipment. The use of heavy equipment is a determining factor in the success of specialized rail transportation development, where the production capacity of heavy equipment plays a major role in influencing project progress. Therefore, an analysis of production volume capacity is essential. This study aims to evaluate production volume capacity in the Jakarta LRT Phase 1B project, including an analysis of the capacity of cranes, excavators, dump trucks, compactors, and other heavy equipment. Volumetric methods were applied to calculate the volume capacity and productivity of heavy vehicles. The analysis results show that the calculated volume and productivity of heavy equipment have met the targets in accordance with the established schedule.
RISK MANAGEMENT IN HEAVY EQUIPMENT PERFORMANCE EVALUATION IN JAKARTA LRT PROJECT PHASE 1B Faizal Addin Achmad; Bilhan Gamaliel Hartanto
INTERNATIONAL JOURNAL OF MULTI SCIENCE Vol. 6 No. 01 (2026): INTERNATIONAL JOURNAL OF MULTISCIENCE - JANUARY-APRIL 2026
Publisher : CV KULTURA DIGITAL MEDIA

Show Abstract | Download Original | Original Source | Check in Google Scholar

Abstract

Infrastructure projects, especially in the development of mass transportation systems such as light rail transit (LRT), rely heavily on the role of heavy equipment. The use of these machines is a decisive factor in the successful construction of a special mode of rail transport, in which the production capacity of the machine plays a major role in influencing the progress of the project. Therefore, an analysis of the capacity of production volumes is necessary. This study aims to evaluate the production volume capacity of The Jakarta LRT project Phase 1b, including analysis of the capacity of cranes, excavators, dump trucks, compactors, and other heavy equipment. The volumetric method is applied to calculate the volume capacity and productivity of heavy vehicles. The results of the analysis showed that the calculated volume and productivity of the machine have met the target according to the established schedule.