Analisis Penjadwalan Dengan Menggunakan Kurva S Pada Proyek Pembuatan Reactor Tank 30m3 Abdillah, Giyo Sekhan; Waluyo, Minto
Jurnal Penelitian Dan Pengkajian Ilmiah Eksakta Vol 4 No 1 (2025): Jurnal Hasi Penelitian Dan Pengkajian Ilmiah Eksakta - JPPIE
Publisher : LPPM Universitas Dharma Andalas

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.47233/jppie.v4i1.1772

Abstract

Construction project activities can be defined as an activity that takes place within a limited period of time that has been determined with the allocation of certain resources and is intended to produce products whose quality criteria have been clearly outlined. In completing a construction job, scheduling is one of the things that is very important and needs to be paid attention to. PT. PDK received various projects, one of which was making a 30m^3 reactor tank. This tank work was carried out at the PT workshop. Putra Dharma Kencana. The S curve is a curve that describes the relationship between the accumulated value of development project implementation and project implementation. The weight on the S curve is the percentage of price for each job divided by the total price. If the total weight value is less than 100% then there is an error in the calculation which will affect the S curve. Work on the reactor tank was carried out according to the target, namely for 12 weeks. The disadvantage of the S curve method is the weight calculation. The weight used is the percentage of the price for each job with the total price.