Construction project is a process that manages several resources so it canachieve an aim. Planning and scheduling at construction project are related to time,cost and quality required since the balance of those three aspects is the main goalthat will be pursued. There are some scheduling methods which are usually used inconstruction project completion. A Repetitive Scheduling Method is a kind ofscheduling methods that is used for a project which has repetitive activities. Thismethod enables showing resources management that contains of human resources,tools and materials without separating among those aspects. Applying RSM atBeranda Mumbul housing can shorten completion day from 31 weeks to 27 weeksand decrease the cost from Rp. 26.575.454,- to Rp. 25.424.127,- in a unit.