Jurnal Vokasi Manajemen Dan Rekayasa Infrastruktur Sipil
Vol. 2 No. 1 (2025): JANUARI-JUNI 2025

Analysis of Acceleration of Completion of Palapa Market Revitalization Project Using Crash Program Method

Puspita Sari, Neri (Unknown)
Yasri, Desi (Unknown)
Ovirizalni, Nurul (Unknown)



Article Info

Publish Date
17 Jun 2025

Abstract

Timeliness in construction projects is a crucial factor that affects cost, quality, and stakeholder satisfaction. Delays in project completion can have serious consequences. The Palapa Market Revitalization Project in Pekanbaru City with a contract value of Rp2,791,647,140.00 and a planned duration of 120 calendar days experienced a delay of -7.42% in the 13th week. This problem prompted this study to analyze project scheduling using the Precedence Diagram Method (PDM) to identify critical path activities and accelerate them through the Crash Program method by adding overtime work for 1, 2, 3, and 4 hours. The results of the study indicate that critical activities that can be accelerated include Steel Column Work, Steel Beam Work, and Hollow Frame Painting Work. The optimal acceleration scenario is the addition of overtime for 1 hour per day, so that the duration of the Steel Column Work is reduced to 125 days from 129 days at a cost of Rp. 215,719,694.80 (from Rp. 190,999,200.00), Steel Beam Work reduced to 125 days from 129 days at a cost of Rp. 80,595,986.13 (from Rp. 72,212,000.00), and Hollow Frame Painting Work reduced to 126 days from 129 days at a cost of Rp. 17,591,213.87 (from Rp. 15,635,200.00). These results indicate the effectiveness of the schedule acceleration strategy in mitigating project delays by considering cost implications.

Copyrights © 2025






Journal Info

Abbrev

jvm

Publisher

Subject

Civil Engineering, Building, Construction & Architecture Engineering Environmental Science Materials Science & Nanotechnology Transportation

Description

JVMATRIKS: Jurnal Vokasi Manajemen dan Rekayasa Infrastruktur Sipil adalah jurnal open access dan peer-review yang diterbitkan oleh Program Studi Diploma Tiga Teknik Sipil, Universitas Riau, Indonesia. Jurnal ini memediasi hasil kajian, penelitian dan pengembangan Ilmu Pengetahuan dan Teknologi di ...