Analisis Keterlambatan Proyek Terhadap Cost Overruns Berbasis Project Risk Management Pada Proyek Pembangunan Infrastruktur Pabrik NPK Chemical PT Pupuk Iskandar Muda

ikmal, teuku (Unknown)
Wesli, Wesli (Unknown)
Maizuar, Maizuar (Unknown)
Khairullah, Khairullah (Unknown)
Hamzani, Hamzani (Unknown)



Article Info

Publish Date
25 Mar 2024

Abstract

Abstrak Proyek Pembangunan Pabrik NPK Chemical di PT PIM mengalami keterlambatan significant sehingga terjadi cost overrun. Penelitian ini untuk mengetahui banyaknya faktor risiko paling dominan dengan pendekatan Project Risk Management. Metode penelitian menggunakan metode deskriptif kuantitatif dengan menyebarkan kuesioner kepada personil di proyek Pabrik NPK Chemical PT PIM. Data kuesioner diolah menggunakan programming SPSS. Setelah itu, dilakukan analisis penilaian risiko untuk memperoleh risiko keterlambatan yang dominan. Hasil penelitian menunjukkan faktor risiko kategori œhigh risk sebanyak 31 risiko atau berkontribusi sebesar 84,67%. Adapun 5 faktor risiko dominan penyebab keterlambatan proyek yaitu: Pengiriman material tidak sesuai sequential di lapangan; Mismanagement project Kontraktor; Keterlambatan karena pekerjaan subkontraktor; Mobilisasi sumberdaya yang lambat; serta Koordinasi dan komunikasi yang tidak baik antar bagian dalam organisasi kerja Kontraktor sehingga tidak dapat mengelola interface pekerjaan. Kata kunci: Keterlambatan Proyek, Cost Overrun, Project Risk Management   Abstract The NPK Chemical Plant Construction Project at PT PIM experienced significant delays resulting in cost overrun. This study is to determine the number of most dominant risk factors with the Project Risk Management approach. The research method used quantitative descriptive methods by distributing questionnaires to personnel at PT PIM's NPK Chemical Plant project. Questionnaire data is processed using SPSS programming. After that, a risk assessment analysis is carried out to obtain the dominant risk of delay. The results showed that the risk factors in the "high risk" category were 31 risks or contributed 84.67%. The 5 dominant risk factors that cause project delays are: Material delivery is not in accordance with sequential in the field; Mismanagement of the Contractor's project; Delays due to the work of subcontractors; Slow resource mobilization; and Poor coordination and communication between parts of the Contractor's work organization so that they cannot manage the work interface. Keywords:   Project Delay, Cost Overrun, Project Risk Management

Copyrights © 2024






Journal Info

Abbrev

teras

Publisher

Subject

Civil Engineering, Building, Construction & Architecture Engineering Environmental Science

Description

Teras Jurnal is a journal that communicates the results of research within the scope of civil engineering and scientific development as well as aspects of practitioners. The process of manuscript submission is open throughout the year. All submitted manuscript will be screened with double-blind peer ...