ANALISIS PRODUKTIVITAS PEKERJA DALAM PEKERJAAN PEMASANGAN BATA RINGAN PADA PROYEK PEMBANGUNAN GEDUNG SERBAGUNA POLRES DAN REHABILITASI RUANG KAPOLRES KOTA BANJARBARU Putri, Tania Ananda Tasia Hariyanto; Cahyadi, Hendra; Rachman, Tezar Aulia
INFO-TEKNIK 2023: PROSIDING SEMNAS TAHUNAN X 2023
Publisher : Universitas Lambung Mangkurat

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.20527/infotek.v0i0.18643

Abstract

In the world of construction services, labor productivity is one of the determining factors for the success of a development project. In measuring the level of labor productivity there are various ways, one of which is by direct observation in the field by looking at the work of each worker. The purpose of this study was to determine the coefficient/index value of the workers in the brick wall laying work cycle in the Polres Multipurpose Building Development project and the Kapolres Room Rehabilitation project in Banjarbaru City and to determine the coefficient comparison of bricklaying workers in the POLRES Multipurpose Building Construction project and Spatial Rehabilitation The Banjarbaru City Police Chief when compared with the 2022 Work Unit Price Analysis (AHSP). This research was conducted by observing the productivity level of 4 light brick laying workers. From the data analysis that has been done, it can be seen that the coefficient or index of masons on the work of laying red brick walls on the construction project of the Banjarbaru Police Multipurpose Building and Kapolres Room Rehabilitation has an average of 0.064 OH. Meanwhile, the coefficient or masonry index according to Minister of Public Housing and Public Housing Regulation No. 1 of 2022 is 0.13 OH. This means that the coefficient or index value of the carpenter's data from the field is smaller in value compared to the coefficient or index in Regulation of the Minister of Public Affairs and Public Housing No. 1 of 2022. The percentage comparison of the coefficient or index of the masonry is obtained 0.066.
ANALISIS FAKTOR-FAKTOR YANG BERHUBUNGAN DENGAN PEMAKAIAN ALAT PELINDUNG DIRI PADA PEKERJA PROYEK PEMBANGUNAN PENGENDALI BANJIR SUNGAI BARABAI KAB. HULU SUNGAI TENGAH (MYC) Rachman, Tezar Aulia; Cahyadi, Hendra; Aulia, Risya
Jurnal Kacapuri : Jurnal keilmuan Teknik Sipil Vol 6, No 2 (2023): Vol 6, No 2 (2023 JURNAL KACAPURI : JURNAL KEILMUAN TEKNIK SIPIL (Edisi Desember
Publisher : Universitas Islam Kalimantan Muhammad Arsyad Al-Banjari Banjarmasin

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.31602/jk.v6i2.13182

Abstract

Banyak pekerja yang masih tidak memakai Alat Pelindung Diri (APD) dengan lengkap. Berbagai alasan yang diungkapkan antara lain sesak, risih, dan panas ketika memakai APD. Selain itu tidak adanya hukuman jika pekerja tidak memakai APD secara lengkap. Penelitian ini dilakukan untuk mengetahui faktor-faktor yang berhubungan dengan pemakaian alat pelindung diri (APD) pada pekerja Proyek Pembangunan Pengendali Banjir Sungai Barabai Kab. Hulu Sungai Tengah (MYC). Faktor yang diobservasi adalah pengetahuan pekerja, sikap pekerja dan ketersediaan APD.Jenis penelitian ini merupakan penelitian observasional dengan rancangan cross sectional. Sampel penelitian adalah jumlah total populasi pekerja yaitu sebanyak 20 responden. Pengumpulan data dilakukan dengan wawancara menggunakan kuesioner dan observasi langsung. Analisis data melalui tiga tahapan, yaitu univariat untuk melihat distribusi frekuensi, bivariat untuk melihat hubungan (chi square), dan multivariat untuk melihat faktor dengan hubungan yang paling bermakna (Regresi Logistik Berganda).Berdasarkan hasil analisis menunjukkan bahwa variabel ketersediaan APD merupakan faktor yang mempunyai pengaruh paling kuat untuk mempengaruhi pemakaian APD pada Proyek Pembangunan Pengendali Banjir Sungai Barabai Kab. Hulu Sungai Tengah (MYC)   dengan nilai sig sebesar 0,016. Kemudian dapat diketahui pula ada peluang 85% pekerja tidak memakai APD yang lengkap, sebelum variabel sikap, pengetahuan dan ketersediaan dimasukkan. Selanjutnya dari model summary dengan melihat nilai Nagelkerke R Square sebesar 0,577 (57,7%) dapat diketahui bahwa faktor pengetahuan dan ketersediaan APD secara simultan memberikan pengaruh sebesar 57,7% terhadap pemakaian APD yang dipakai pekerja walaupun dari nilai sig. variable pengetahuan dan sikap tidak memiliki pengaruh terhadap pemakaian APD.
Analisa Biaya Siklus Hidup pada Gedung Sekolah MAN 4 Kabupaten Banjar Rachman, Tezar Aulia; Badriani, Badriani
Jurnal Kacapuri : Jurnal keilmuan Teknik Sipil Vol 7, No 2 (2024): Vol 7, No 2 2024 JURNAL KACAPURI : JURNAL KEILMUAN TEKNIK SIPIL (Edisi Desember
Publisher : Universitas Islam Kalimantan Muhammad Arsyad Al-Banjari Banjarmasin

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.31602/jk.v7i2.17253

Abstract

Ketika bangunan telah lama digunakan dan usang, nilai ekonomi dan fungsionalnya menurun secara signifikan. Terdapat permasalahan terkait kinerja bangunan, seperti lingkungan dan penggunaan material yang tidak tepat. Bangunan harus dipelihara untuk menjamin kesinambungan penggunaannya sepanjang masa manfaatnya. Rumusan masalah penelitian adalah Life Cycle Cost untuk mengukur besarnya biaya pemeliharaan pada gedung MAN 4 Banjar selama 10 tahun ke depan, dan bagian mana yang mempunyai Life Cycle Cost tertinggi dan terendah berdasarkan siklus hidup bangunan tersebut.  Biaya pemeliharaan struktur dan komponen kelistrikan, mesin, tata letak eksterior dan pembersihan. Berdasarkan hasil penelitian, biaya pembangunan MAN 4 Banjar 10 tahun mendatang (2024-2033) dengan kenaikan sebesar 4,00% adalah Rp 133.961.875,00 (100%). Biaya pemeliharaan rumah MAN 4 Banjar setiap tahunnya selama 10 tahun sebesar Rp 133.961.875,00. Biaya pemeliharaan tertinggi dalam satu siklus hidup gedung MAN 4 Banjar adalah sebesar Rp. Sektor ketenagalistrikan sebesar 46.449.227 (34,67%), sektor terkecil sebesar Rp. Sektor konstruksi sebesar 624.318,00 (0,47%).
EVALUASI PERBANDINGAN ESTIMASI ANGGARAN BIAYA ANTARA METODE AHSP 2016 DAN METODE PELAKSANAAN KONTRAKTOR PADA PEMBANGUNAN KANTOR IMIGRASI KELAS I KABUPATEN TAPIN Gazali, Akhmad; Rachman, Tezar Aulia; Triningtyas, Yekti; Reizaldie, Raghmad
Jurnal Kacapuri : Jurnal keilmuan Teknik Sipil Vol 8, No 1 (2025): Vol 8, No 1 2025 JURNAL KACAPURI : JURNAL KEILMUAN TEKNIK SIPIL (Edisi Juni 2025
Publisher : Universitas Islam Kalimantan Muhammad Arsyad Al-Banjari Banjarmasin

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.31602/jk.v8i1.19253

Abstract

Pembangunan kantor merupakan salah satu inisiatif dari peningkatan fasilitas infrastrutur guna meningkatkan produktifitas pekerja yang lebih baik. Maka dari itu perencanaan bangunan dari segi keamanan, biaya, kegunaan, bentuk, arsitektural dan struktural ataupun jasa yang tersedia. Dalam pelaksanaan proyek Pembangunan Kantor Imigrasi Kabupaten Tapin ini menggunakan anggaran biaya lumayan besar, sehingga anggaran tersebut perlu diperhitungkan dengan seksama agar mampu menaikkan efisiensi dan efektifitas dari pelaksanaan proyek. Oleh karena itu, perlu adanya pedoman dasar dalam menentukan analisa harga satuan pekerjaan yang dipengaruhi oleh nilai indeks atau koefisien, sehingga analisa pada satuan harga pekerjaan tersebut sesuai terhadap biaya, mutu dan waktu pelaksanaan. Ada beberapa metode perhitungan rencana anggaran biaya diantaranya AHSP 2016 dan Penawaran Harga Kontraktor. Tujuan penelitian ini untuk mengetahui dari kedua perhitungan yang mana paling ekonomis. Dari hasil perhitungan rencana anggaran biaya pada proyek pembangunan Kantor Imigrasi Kabupaten Tapin dengan kedua perhitungan diperoleh hasil perhitungan Penawaran Harga Kontraktor (Lapangan) yang paling ekonomis sebesar Rp. 1.721.817.000,00 dan AHSP 2016 sebesar Rp. 2.529.527.000,00 dengan selisih sebesar Rp. 807.710.000,00. Faktor yang mempengaruhi besaran estimasi dari keduanya seperti material, asumsi perencana anggaran biaya, dan koefien kedua perhitungan.
Pengaruh Penggunaan Limbah Plastik Dengan Tipe Polyethlene Terephthalate (PET) Sebagai Subsitusi Agregat Pada Campuran Aspal Berpori Maulana, Muhammad Dony; Surya, Adhi; Rachman, Tezar Aulia
Jurnal Penelitian Teknik Vol. 1 No. 1 (2024): Jurnal Penelitian Teknik
Publisher : Jurnal Penelitian Teknik

Show Abstract | Download Original | Original Source | Check in Google Scholar

Abstract

Di era globalisasi ini, penggunaan kemasan plastik tidak bisa lepas dalam kehidupan sehari-hari. Jumlah konsumsi plastik terus meningkat disetiap tahunnya. Namun, limbah plastik yang semakin menumpuk belum dimanfaatkan sebaik mungkin. Selain sulit terurai dengan tanah, plastik juga apabila dibakar asap yang ditimbulkan dapat merusak kesehatan, proses pendaur-ulangan plastik pun hanya merubah plastik menjadi sesuatu yang baru yang ketika barang tersebut tidak terpakai lagi maka akan kembali menjadi sampah namun penelitian ini akan mencampurkan limbah plastik jenis PET pada aspal porus. Pengujian dilakukan di Laboratorium Struktur Teknik Sipil Universitas Islam Kalimantan Muhammad Arsyad Al Banjari, Kalimantan Selatan. Metode penelitian yang digunakan adalah eksperimental, dimana campuran plastik dengan variasi presentase agregat kasar plastik (10%, 20%, dan 30%) disiapkan diuji menggunakan uji Marshall, Cantabro Loss, dan Permeabilitas. Jadi dari hasil penelitian ini semua variasi plastik PET yang memenuhi spesifikasi adalah nilai Stabilitas, Flow, Kekakuan, dan Cantabro Loss. Sedangkan Kadar Rongga dan Permeabilitas 20% dan 30% belum memenuhi spesifikasi AAPA 2004. Jadi dapat disimpulkan bahwa semakin meningkat persentase plastik PET pada aspal maka akan menutupi rongga pada benda uji aspal pori, namun sebalik nya semakin meningkat nya persentase plastik PET maka akan meningkat nya hasil dari Stabilitas, Kelelehan (Flow), dan Cantabro Loss pada benda uji aspal pori
Analysis of Heavy Equipment Management Based on Cost and Time Values in the Local Road Improvement Project Package 6 Rachman, Tezar Aulia; Firdaus, Muhammad
Jurnal Teknik Sipil Vol 24, No 3 (2024): Vol 24, No 3 (2024): JURNAL TEKNIK SIPIL EDISI AGUSTUS 2024
Publisher : Fakultas Teknik Universitas Tanjungpura

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.26418/jts.v24i3.82050

Abstract

Heavy equipment is crucial in construction, significantly impacting the optimization of time and cost efficiency, particularly in road construction projects. This research involves analyzing data on the heavy equipment used, calculating productivity, and determining the most effective and efficient combination of heavy equipment using the trial and error analysis method.   From the analysis of cost and time productivity in the implementation of the aggregate foundation layer work, the productivity of heavy equipment was measured at two locations. At Jl. RT.040, the productivity rates were: Dump Truck at 5.27 m ³/hour, Motor Grader at 16.20 m ³/hour, Vibratory Roller at 14.58 m ³/hour, Wheel Loader at 174.96 m ³/hour, and Water Tanker at 16.20 m ³/hour. At Jl. Komp. Agis, the productivity rates were: Dump Truck at 4.58 m ³/hour, Motor Grader at 16.20 m ³/hour, Vibratory Roller at 14.58 m ³/hour, Wheel Loader at 174.96 m ³/hour, and Water Tanker at 16.20 m ³/hour.   Subsequent data processing aimed to determine the optimal combination of heavy equipment in terms of cost and time using the trial and error analysis method. The results showed that the original condition lasted 217 hours for Rp. 134,286,351.00. Alternative 1 had a duration of 157 hours for Rp. 109,094,993.00, and Alternative 2 had a duration of 124 hours for Rp. 123,202,383.00.Keywords: LRIP Package 6, Cost and time values, Heavy Equipment Management, Calculating productivity, Determining the most effective