Heat pumps (HPs) are a key route to industrial decarbonization through electrification, but selecting a configuration requires more than maximizing thermodynamic performance: a highly efficient system may still be unable to supply the steam pressure and temperature that a process needs. Few studies evaluate HP configurations by combining thermodynamic performance with process delivery capability. This study compares four configurations of increasing complexity with a boiler–chiller baseline: (C1) boiler feedwater preheating, (C2) a simultaneous heating and cooling HP, (C3) a two-stage cascade high-temperature HP (HTHP), and (C4) a cascade HTHP with mechanical vapor recompression (MVR). The case is a dairy spray-drying plant that requires 12 barg steam (4 t/h) and 250 TR of cooling. Energy and exergy analyses used IAPWS-IF97 properties and the Gouy–Stodola formulation. Each COP was tested against its Lorenz limit and replaced by a cycle-based value where inadmissible, and C3 was modelled independently of C4. At the design point, exergy efficiency rose from 25.5% (baseline) to 27.4% (C1), 29.1% (C2), 34.5% (C3) and 42.2% (C4). Only C4 delivered 12 barg steam; C3 supplied saturated steam at 4 barg (152 °C). The vendor quoted COP of C2 (5.3) exceeded its Lorenz limit (5.12) and was replaced by a cycle-calculated value of 2.56. Operational CO₂ emissions of C3 and C4 exceed those of the baseline when the grid emission factor is above about 0.30 t CO₂/MWh (0.88 t CO₂/MWh was adopted). Delivery-envelope compliance and exergy efficiency are independent criteria: compliance is decided by the final steam pressure, whereas the exergy efficiency of C3 ranged from 31.6% to 60.0% across the sensitivity grid without changing its 4 barg limit. The proposed framework checks delivery-envelope compliance first and Lorenz-consistent thermodynamic performance second, allowing unsuitable configurations to be excluded before detailed techno-economic design.