Scheduling a construction in the presence of various obstacles including work delays that result in time delays from the planned time. The research method used to obtain data is carried out directly from the research object. So the research used the AOA (Activity On Arrow) method. This writing method begins with the calculation of ES, LS, EF, LF, and then AOA. Based on the results of the analysis used, the needs and implementation of the project have been categorized as good enough, but not supported by proper supervision. By applying the right AOA method, the amount of time required for each activity can be known and the critical trajectory of the work process can be known. The proper supervision is needed when the AOA method has a critical path / path. With the analysis of the AOA method, it takes 112 calendar days