Claim Missing Document
Check
Articles

Found 5 Documents
Search

Analysis of Technical Loss Calculation Using Load Curve Approach on 20 kV Distribution Network Maulana, Rizky Rahmat; Salahuddin, S; Ezwarsyah, E; Ismail, Baharuddin; Shrestha, Ashish; Astonkar, Dhiraj Vijayrao
Journal of Renewable Energy, Electrical, and Computer Engineering Vol 1, No 2 (2021): September 2021
Publisher : Institute for Research and Community Service, Universitas Malikussaleh, Indonesia

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.29103/jreece.v1i2.5238

Abstract

Energy loss (losses) is the loss of a certain amount of energy generated when it is distributed to consumers so that it affects the profitability of the company concerned. The size of the losses from an electric power system shows the level of efficiency of the system, the lower the percentage of losses that occur the more efficient the system. Energy losses in the distribution network are generally divided into two, namely technical and non-technical losses. The calculation of technical losses in the 20 KV medium distribution network of PT PLN (Persero) Ulp Matang Glumpang Dua is carried out using the load curve approach method and using the help of the Microsoft Exel program, while the technical losses calculated are technical losses on the Medium Voltage Network and Distribution Transformer. From the results of the analysis of the calculation of technical losses in 2020, the total technical loss value at MG-01 Matang City is in the range of 13.8% to 20.8% which consists of the average technical loss in the Medium Voltage Network feeder of 0.02%. and the loss of Distribution Transformer by 17.6%.
Power losses analysis for reduced switch 9-level cascaded H-bridge multilevel inverter Ismail, Mohammad Haziq; Isa, Zainuddin Mat; Arshad, Mohd Hafiz; Mid, Ernie Che; Ismail, Baharuddin; Talib, Md Hairul Nizam
International Journal of Applied Power Engineering (IJAPE) Vol 13, No 4: December 2024
Publisher : Institute of Advanced Engineering and Science

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.11591/ijape.v13.i4.pp808-814

Abstract

This study provides a thorough examination of power losses and total harmonic distortion (THD) in single-phase 9-level cascaded H-bridge multilevel inverters (CHB MLI) at low switching frequencies. The aim is to analyze the efficiency of a single-phase 9-level cascaded CHB MLI using three distinct switch configurations: 16-switch, 11-switch, and proposed 8-switch. The calculated switching angles are optimized using the feed-forward methodology. Two types of load conditions—R load and R-L load—are being examined. The results suggest that the proposed 8-switch design exhibits superior efficiency by limiting power losses compared to other topologies. Regarding THD, the conventional topology yields a somewhat lower value, however, the disparity is less than 1% when compared to both reduced switch topologies.
Analysis of Technical Loss Calculation Using Load Curve Approach on 20 kV Distribution Network Maulana, Rizky Rahmat; Salahuddin, S; Ezwarsyah, E; Ismail, Baharuddin; Shrestha, Ashish; Astonkar, Dhiraj Vijayrao
Journal of Renewable Energy, Electrical, and Computer Engineering Vol. 1 No. 2 (2021): September 2021
Publisher : Institute for Research and Community Service (LPPM), Universitas Malikussaleh, Indonesia

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.29103/jreece.v1i2.5238

Abstract

Energy loss (losses) is the loss of a certain amount of energy generated when it is distributed to consumers so that it affects the profitability of the company concerned. The size of the losses from an electric power system shows the level of efficiency of the system, the lower the percentage of losses that occur the more efficient the system. Energy losses in the distribution network are generally divided into two, namely technical and non-technical losses. The calculation of technical losses in the 20 KV medium distribution network of PT PLN (Persero) Ulp Matang Glumpang Dua is carried out using the load curve approach method and using the help of the Microsoft Exel program, while the technical losses calculated are technical losses on the Medium Voltage Network and Distribution Transformer. From the results of the analysis of the calculation of technical losses in 2020, the total technical loss value at MG-01 Matang City is in the range of 13.8% to 20.8% which consists of the average technical loss in the Medium Voltage Network feeder of 0.02%. and the loss of Distribution Transformer by 17.6%.
Planning to Reconfigure the 150 kV Transmission Network at PT. PLN (Persero) Tualang Cut Network and Substation Hasibuan, Arnawan; Asran, Asran; Adriansyah, Fery; Ismail, Baharuddin; Siregar, Widyana Verawaty; Sayuti, Muhammad
Journal of Renewable Energy, Electrical, and Computer Engineering Vol. 3 No. 2 (2023): September 2023
Publisher : Institute for Research and Community Service (LPPM), Universitas Malikussaleh, Indonesia

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.29103/jreece.v3i2.11740

Abstract

System condition at PT. PLN (Persero) Tualang Cut Substation where the reliability of the 150 kV system depends on the Langsa Substation, which we will reconfigure on the Lgs-P.B and Lgs-T.C channels to P.B-T. C and T.C-Lgs. The planning for the reconfiguration of the 150 kv transmission network of the Tualang Cut Substation was carried out by estimating the distance of the transmission line and the constraints that occurred. The condition of the electric power system that is currently operating at PT. PLN (Persero) Tualang Cut Substation is considered less efficient in receiving power from the 150 kV SUTT interconnection. The SUTT in Tualang Cut currently receives electrical power from the Langsa Substation with a Losses value on lines 1 and 2 of 771,4142474 kW and experiences a Voltage Drop on lines 1 and 2 of 4,38 kV. After we reconfigured the channel, from the results of the reconfiguration there was a decrease in Losses on channels 1 and 2 by 311,298581 kW which before the reconfiguration of power losses on the line amounted to 771,4142474 kW and after being reconfigured to 460,1156668 kW there was a decrease in Voltage Drop on channels 1 and 2 by 1,44 kV, before the reconfiguration of the voltage drop on the line of 4,38 kV and after the reconfiguration to 2,94 kV, the reconfiguration carried out is the best solution to reduce losses and voltage drops.
Parameter tuning of PIDG controller on maximum photovoltaic power point for battery charging system Irwanto, Muhammad; Timoteus Gultom, Togar; Satria, Habib; Ismail, Baharuddin; Erniati Panjaitan, Christin; Syukri, Mahdi
Bulletin of Electrical Engineering and Informatics Vol 14, No 6: December 2025
Publisher : Institute of Advanced Engineering and Science

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.11591/eei.v14i6.11044

Abstract

Maximum photovoltaic power point (MPVPP) based on DC-DC buck converter is supplied by photovoltaic module. A controller method is needed to control the signal that it drives the switching component of DC-DC buck converter. The previous researcher conducts proportional integral derivative (PID) controller applying the DC-DC buck converter, but only its parameters (proportional, KP, integral, KI, and derivative, KD) are studied. This paper presents MPVPP based on PID with gain (PIDG) controller on the DC-DC buck converter by tuning the parameters of KP. KI and KD and adding a gain, G connected to PIDG controller for charging 12 V, 7 Ah battery. The DC-DC buck converter is designed for the output voltage of 14.7 V and output power of 150 W and modelled using Simulink MATLAB. The simulation results show that the parameters of KP=0.0032, KI=1, and KD=4×10-7 are suitable to control the switching component. The gain, G gives significant effect on the settling time and the time to reach their steady state value of output voltage of 14.7 V. The battery SOC can increase 1.36% per second, if the initial SOC is 25%, thus it needs arround 55 seconds to reach the fully charging condition.