Identifikasi dan Usulan Menangani Waste pada Proyek Mesin Selectifier dengan Pendekatan Lean Project Management Di PT. Z Firmansyah, Abdullah; Momon, Ade
Industrika : Jurnal Ilmiah Teknik Industri Vol. 8 No. 3 (2024): Industrika: Jurnal Ilmiah Teknik Industri
Publisher : Fakultas Teknik Universitas Tulang Bawang

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.37090/indstrk.v8i3.1299

Abstract

The delay of a project can occur due to poor planning of its necessary resources, causing waste or waste. The purpose of this research is to find out the waste and its factors that can potentially occur in the selectifier machine project and know the viable solution to choose to deal with the waste. Then careful planning is required by applying the Lean Project Management methodology, where waste and harm can be found using scoring matrices and fishbone diagramming tools. Based on the analysis results in the selectifier machine project at PT. Z, the potential waste appears, namely waste waiting, defects and overprocessing. Waste and its potential causes are materials or components that are late dating, workers waiting for certain information, machines or tools supporting machine manufacturing are damaged, manufacturing process is not suitable for SOP, materials or components of poor quality, less scrupulous workers, poor working techniques. And according to the evaluation matrix, the best solution obtained is to perform other tasks that do not involve doing material work or using components that have not yet arrived on site, and buying back better materials from vendors. Keywords : Evaluation Matrix, Fishbone Diagram, Lean Project Management, Waste
Pemanfaatan Air Fermentasi Dari Limbah Cucian Beras di Desa Adiarsa Barat, Kecamatan Karawang Barat, Kabupaten Karawang rahmi, Hayatul; Bayfurqon, Fawzy Muhammad; Momon, Ade
Jurnal Budiman: Pembangunan dan Pengabdian Masyarakat Nusantara Vol. 2 No. 1 (2024): April
Publisher : Fakultas Pertanian, Universitas Singaperbangsa Karawang

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.35706/budiman.v2i1.11072

Abstract

Desa Adiarsa Barat memiliki lahan/ fasilitas umum/ pekarangan rumah yang kurang dimanfaatkan dengan maksimal. Masyarakat dalam 1 tahun terakhir ini sudah mulai membuat taman pada lahan tersebut, tapi belum diberdayakan dengan optimal. PkM di desa ini diharapakan agar masyarakat desa bisa mengaplikasikan ilmu yang diberikan oleh Tim pengabdian. Sehingga diharapkan warga masyarakat bisa memanfaatkan lahan tersebut dengan semaksimal mungkin. Metode pelaksanaan PkM yaitu pertama pengenalan apa itu air cucian beras dan manfaatnya bagi tanaman, kedua pengenalan apa itu air fermentasi cucian beras, ketiga praktek pembuatan pupuk fermentasi air cucain beras secara langsung dan keempat sesi terakhir tanya jawab dengan warga. Hasil PkM yaitu didapatkan bahwa masyarakat Desa Adiarsa memiliki antusias yang tinggi dalam mengikuti pelatihan dan ingin mengaplikasikan pada tanaman yang ada pada halaman pekarangan rumahnya, dan ingin menanam tanaman obat keluarga pada lahan kosong perumahan. PkM ini telah membantu masyarakat dalam meningkatkan ilmu pengetahuan terkait kandungan air cucian beras dan meningkatkan keterampilan dalam pembuatan air fermentasi limbah cucian beras dan meningkatkan minat masyarakat dalam mempraktekkan aplikasi air fermentasi limbah cucian beras terhadap tanaman yang ada di pekarangan rumah warga masing-masing.
Analisis ANALISIS KINERJA KARYAWAN DENGAN MENGGUNAKAN METODE REGRESI LINEAR BERGANDA DI PT. EFG Fauzi Amin, Moh. Rizha; Fitriani, Risma; Momon, Ade; Nasution, Bakhtiar Alam; Martin, Riky
Industri Inovatif : Jurnal Teknik Industri Vol 14 No 2 (2024): Inovatif Vol. 14 No. 2
Publisher : Prodi Teknik Industri S1 Institut Teknologi Nasional Malang

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.36040/industri.v14i2.11513

Abstract

Penelitian ini bertujuan untuk mengetahui pengaruh variabel independen Motivasi Merja (X1), Lingkungan Kerja (X2), Pelatihan (X3), dan Kompensasi (X4) terhadap kinerja karyawan (Y), baik secara simultan maupun parsial. Fokus utama adalah untuk menganalisis seberapa signifikan pengaruh dari masing-masing variabel independent atau variabel X terhadap variabel dependen atau variable Y. Penelitian yang dilakukan pada kali ini menggunakan metode regresi linear berganda dengan pendekatan kuantitatif. Data diolah menggunakan perangkat lunak SPSS untuk menguji hipotesis melalui uji F (simultan) dan uji t (parsial). Uji F dilakukan untuk melihat pengaruh gabungan dari semua variabel independen, sedangkan uji t digunakan untuk mengetahui pengaruh individual dari masing-masing Motivasi Merja (X1), Lingkungan Kerja (X2), Pelatihan (X3), dan Kompensasi (X4) terhadap kinerja karyawan (Y), Hasil uji F menunjukkan bahwa variabel Motivasi Merja (X1), Lingkungan Kerja (X2), Pelatihan (X3), dan Kompensasi (X4) secara simultan berpengaruh signifikan terhadap kinerja karyawan (Y) dengan angka signifikansi sebesar 4.110. Uji t mengindikasikan bahwa independen Motivasi Merja Kompensasi (X4) berpengaruh terhadap kinerja karyawan (Y), sedangkan beberapa lainnya tidak menunjukkan pengaruh yang kuat. Nilai signifikansi > 2.262 mengkonfirmasi bahwa pengaruh signifikan dan tidak signifikan terjadi secara parsial pada variabel independen yang diuji. Penelitian ini memberikan kontribusi dalam memahami pentingnya analisis simultan variabel-variabel independen dalam mengevaluasi kinerja karyawan. Hasil ini relevan bagi manajer sumber daya manusia dalam pengambilan Keputusan keputusan strategis, terutama dalam merancang kebijakan yang dapat meningkatkan kinerja karyawan pada departemen Human Resources. Secara keseluruhan, penelitian ini memperoleh bahwa variabel independen secara bersamaan memiliki pengaruh signifikan terhadap kinerja karyawan. Namun, pengaruh dari masing-masing
Pengaruh Motivasi dan Kepuasan Kerja Terhadap Peningkatan Kinerja Karyawan CV. Sabrina Usaha Mandiri Jakarta Utara Muharram, Ari; Fitriani, Risma; Momon, Ade
JURMATIS (Jurnal Manajemen Teknologi dan Teknik Industri) Vol. 5 No. 2 (2023): August
Publisher : Universitas Kadiri

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.30737/jurmatis.v5i2.4163

Abstract

The problem of motivation and satisfaction at CV Sabrina Usaha Mandiri needs to be overcome through improving employee performance with training, support and rewards. This study is to determine the model of the corrected hypothesis from that perspective. It is hoped that the results of the research can help companies improve employee performance. Quantitative-associative design to test the hypothesis of the relationship between motivation, job satisfaction, and employee performance in CV. Sabrina Independent Business. A population of 24 employees, using google form instruments and processed with IBM SPSS 23. Validation and reliability are performed by partial testing procedures and simultaneous tests to produce corrected models. This study shows the results that employee motivation has a positive and significant correlation and reliability to improve the performance of street light installation projects in the North Jakarta area. The results of partial and simultaneous tests on the corrected hypothesis model also showed that motivation and job satisfaction had an effect on improving performance on the project. Therefore, it is important for project management to pay attention to and maintain the motivation and job satisfaction of the workers in the project in order to achieve optimal results. Motivation and job satisfaction can play a role in improving the performance of street light installation projects in the North Jakarta area by paying attention to the quality of motivation and job satisfaction of the employees involved
Analisis Penggunaan Alat Pelindung Diri pada Pekerja di PT.Djabesmen Menggunakan Metode Fishbone Susanto, Agus Dwi; Momon, Ade
Industrika : Jurnal Ilmiah Teknik Industri Vol. 8 No. 4 (2024): Industrika: Jurnal Ilmiah Teknik Industri
Publisher : Fakultas Teknik Universitas Tulang Bawang

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.37090/indstrk.v8i4.1387

Abstract

The possibility of accidents in a building project is one of the causes of hampering the effectiveness of project work activities. Workers are required to implement a good occupational safety and health (K3) management system to minimize the possibility of work accidents. An example of a case in the construction world occurred in the Gading Mediterania Apartment construction project located in Kelapa Gading. The accident that occurred killed four workers. Two people were killed by precast concrete and two people died from electric shock. Therefore, to prevent the recurrence of the incident, research was conducted using fishbone analysis. The purpose of this research is to analyze the importance of using personal protective equipment at PT Djabesmen. The method used helps the author in analyzing the possibility of accidents on the project. The results of the analysis explain that the percentage of PPE use at PT Djabesmen is good. Keywords: Analysis, Fishbone, K3
Analysis of Chlorine Inventory Using the Economic Order Quantity (EOQ) Method (Case Study of PT. Toya Indo Manunggal) Putri, Nirmala; Momon, Ade
JTI: Jurnal Teknik Industri Vol 10, No 1 (2024): JUNI 2024
Publisher : Universitas Islam Negeri Sultan Syarif Kasim Riau

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.24014/jti.v10i1.24733

Abstract

The purpose of this study was to determine the frequency of ordering chlorine for one year at PT. Toya Indo Manunggal using the Economic Order Quantity (EOQ) method, to determine the cost of chlorine supplies of PT. Toya Indo Manunggal with the Economic Order Quantity (EOQ) method, as well as to analyze the results of the application of the Economic Order Quantity (EOQ) method. The research method used in this study is the economic order quantity (EOQ) model. Data collection techniques are used to collect data according to research procedures so that the required data is obtained. The data used is secondary data in the form of literature studies, namely conducting literature research by reading and researching materials or theories related to chlorine supplies, and Economic Order Quantity (EOQ). The results showed that the frequency of ordering chlorine for one year at PT. Toya Indo Manunggal uses the Economic Order Quantity (EOQ) method of 112 chlorine cylinders per order with a total of 13 orders in one year, the distance between times reaches 20 days per order, and the company must provide security storage or Safety Stock of 142 chlorine cylinders with goods reorder activities when the inventory of the goods is 178 pcs. From data analysis, the total cost of inventory using the EOQ method is Rp. 940,802,000, while the total cost of inventory with orders above and below EOQ is Rp. 1,034,137,777 and Rp. 985,012,631, respectively. Every order for goods above or below the EOQ order will affect the cost of inventory, where the cost of inventory that occurs is greater than the cost of EOQ inventory. With the Economic Order Quantity (EOQ) method, companies can find out how many orders are economical for each inventory item and find out the frequency of orders during a period and when orders are made again, so that the demand for goods can be fulfilled optimally.
Perbandingan Metode Double Exponential Smoothing, Moving Average, dan Linear Regression pada Peramalan Permintaan Produk Pipa Spec Non-Api Tipe SNI 0068:2013 Kelas 2 /PKB (STK)-400 di WTM-8 PT XYZ Supriyatna, Muhamad; Momon, Ade
Angkasa: Jurnal Ilmiah Bidang Teknologi Vol 17, No 1 (2025): Mei
Publisher : Institut Teknologi Dirgantara Adisutjipto

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.28989/angkasa.v17i1.2334

Abstract

PT XYZ, as one of the leading steel pipe manufacturers in Indonesia, aims to compare the effectiveness of forecasting methods in predicting demand for SPEC NON-API TYPE SNI 0068:2013 CLASS 2 /PKB (STK)-400 in WTM-8. The methods compared include Double Exponential Smoothing, Moving Average, and Linear Regression. The forecasting results show that Linear Regression provides the best accuracy with an MSE of 2,619,446 and a MAPE of 96.80%, compared to Double Exponential Smoothing (MSE: 17,123,634.831, MAPE: 113.65%) and two variants of Moving Average, namely MA (2) (MSE: 4,193,150, MAPE: 136.68%) and MA (2x3) (MSE: 4,273,548, MAPE: 169.84%). These findings emphasize the importance of using Linear Regression for demand forecasting to improve the accuracy and efficiency of production planning. Continuous evaluation of forecasting methods and development of related staff skills are expected to support more effective decision making and reduce operational risks.
PENGENDALIAN PERSEDIAAN BAHAN BAKU PRODUK PIPA BAJA SPEC NON. API. KT 24 MENGGUNAKAN METODE ECONOMIC ORDER QUANTITY (EOQ) A'lala, Alvin Kurnia; Momon, Ade; Husniyah, Ulfah
Jurnal Pendidikan Ekonomi (JURKAMI) Vol 10, No 2 (2025): JURKAMI
Publisher : STKIP Persada Khatulistiwa Sintang

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.31932/jpe.v10i2.4632

Abstract

Raw material inventory is a vital component in the production process, especially in manufacturing industries such as PT Bakrie Pipe Industries, which specializes in steel pipe production. The main issue faced by the company is the suboptimal control of raw material inventory for the Non API.KT 24 specification steel pipe product, resulting in cost inefficiencies and unstructured ordering. This study aims to determine the optimal order quantity and total inventory cost using the Economic Order Quantity (EOQ) method. A quantitative approach was used, based on data of annual demand, ordering cost, and holding cost obtained from the company. The results indicate that the optimal order quantity (EOQ) is 43,577,128 kilograms per year. Based on this quantity, the total inventory cost incurred by the company is Rp14,402,700,962 per year. These findings demonstrate that the EOQ method effectively assists the company in minimizing inventory costs and improving raw material management efficiency. This study recommends that the EOQ model be consistently implemented as part of the company’s inventory management strategy.
PERANCANGAN SISTEM INFORMASI PENJUALAN PADA CENTRAL STUDIO PHOTOCOPY MENGGUNAKAN METODE WATERFALL Abdurrohman, Mumun Fadhilah; Momon, Ade; Fitriani, Risma
Jurnal Informatika dan Teknik Elektro Terapan Vol. 12 No. 2 (2024)
Publisher : Universitas Lampung

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.23960/jitet.v12i2.4220

Abstract

Adanya sistem informasi menjadi bagian yang sangat penting pada suatu perusahaan, banyak perusahaan menghadapi masalah dalam mengelola operasionalnya termasuk dalam sistem informasi. Selain itu, menggunakan bantuan dari sistem informasi sangat membantu dalam memudahkan segala kegiatan sehari-hari salah satunya adalah penjualan. Sistem penjualan ini sangat penting bagi perusahaan untuk membantu melaksanakan proses pendataan barang dan pelaporan secara sistematis, terencana, terkontrol, dan saling terintegrasi. Maka dari itu, Tujuan dari penelitian ini adalah untuk mempermudah dan mempercepat perhitungan transaksi penjualan barang antara sistem manual dan sistem yang menggunakan media komputer. Metode waterfall digunakan untuk pengembangan sistem dengan penelitian tindakan (Action Research) mencakup perencanaan, pelaksanaan, pengamatan, dan refleksi. Wawancara, dokumentasi, kuisioner, dan observasi adalah metode pengumpulan data. Dari hasil penelitian ini dapat disimpulkan bahwa proyek sistem informasi Central Studio Photocopy dalam melakukan penjualan barang sesuai dengan kebutuhan baik dari segi penjualan, pencarian, dan laporan penjualan. Diharapkan aplikasi ini dapat meningkatkan penjualan produk yang dilakukan di Central Studio Photocopy.
ANALISIS SISTEM ANTRIAN SEPEDA MOTOR DI SPBU 43.413.32 CIKAMPEK KABUPATEN KARAWANG Pratama, Fachri Dio; Momon, Ade
Jurnal Ilmiah Wahana Pendidikan Vol 10 No 4 (2024): Jurnal Ilmiah Wahana Pendidikan
Publisher : Peneliti.net

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.5281/zenodo.10516136

Abstract

SPBU is a place where people can buy fuel for vehicles such as motorbikes, cars, and so on. SPBU 34-41332 is located in Jalan BIC industrial area, Dawuan Tengah, Cikampek, Karawang. During busy hours such as going home from work, this gas station quite often experiences crowds, this is due to the location of this gas station which is quite strategic because it is located near the industrial area and close to the provincial highway where many motorists pass around this gas station, especially motorcyclists, this queue usually starts to occur from 15.00 WIB and usually starts to return to normal at 20.00 WIB and usually occurs at the pertalite fuel filling station for motorbikes. This study aims to determine whether the level of service and service time at SPBU 34-41332 is at the optimal level using the analysis of the queuing system method with the multiple-line queuing model (M/M/S). The data source obtained is primary data obtained by making direct observations carried out at SPBU 34-41332 and coupled with conducting interviews with several officers in the field to add the required data. The results obtained the average time the customer is in the longest system is in the time period between 15.00 to 16.00 WIB with a length of time of 0.8540 minutes and the average time the customer is in the shortest system is in the period between 13.00 to 14.00 WIB with a length of time of 0.6233 minutes.