EVALUASI KEMAMPUAN PRODUKSI ALAT GALI-MUAT DAN ALAT ANGKUT GUNA MENCAPAI TARGET PRODUKSI BATUBARA 180.000 TON BULAN OKTOBER 2015 DI PIT LIMOA TAMBANG AIR LAYA EXTENTIONTIMUR PT BUKIT ASAM (PERSERO)TBK UPTE: Evaluation Of Excavator And Dump Truck Production Capability Means Order To Achieve The Production Target 180.000 Tons Of Coal In October 2015 At Eastern Extention Of Pit Air Laya Limoa Mine PT Bukit Asam (Persero) Tbk UPTE) Inggrid, Maria Jeane; Tono, E.P.S.B Taman; Pitulima, Janiar
MINERAL Vol 1 No 1 (2016): Mineral
Publisher : Program Studi Teknik Pertambangan Universitas Bangka Belitung

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.33019/mineral.v1i1.1609

Abstract

Eastern Extension of Pit Air Laya Limoa Mine was one of Air Laya Mine site that has coal miningbusiness license owned by PT Bukit Asam (Persero) Tbk. Excavator and truck method were applied inthat mine site. Mechanical equipments used in this site were 1 unit of Komatsu PC 800 SE Excavatorand 6 units of HINO LM 500 Dump Truck. Coal production target in Eastern Extension of Pit Air LayaLimoa Mine in October 2015 was 180.000 ton, but the production capacity of load haul equipment was157.179,39 ton with the work time efficiency at 14,07 hour/day and load haul equipment productiononly 129.245,20 ton with the work time efficiency at 13,97 hour/day. Therefore, evaluation wasnecessary throughout factors affecting working performance of mechanical equipment to achieve thetarget. Evaluation in achieving the target of coal production was conducted by calculating theproductivity, work efficiency and match factor. The data required to obtain these values includedequipment cycle time, the effective work time effeciency, the amount of bucket loading, density andcoal swell factor. Then the data was processed by using formula of mechanical soil removal andanalyzed based on literature related to the issue. After the evaluation of factors affectingperformance of mechanical equipments then work time effeciency corrected to be 15,61 hours/dayand additional of 6 to 7 unit of conveyance. There were changes in work time effeciency between loadhaul equipments and conveyance from 0,83 to 0,97. Production capabilities generated load haulequipment after being evaluated was 192.291,14 tons and production capabilities of conveyances,after the evaluation amounted to 188.236,03 tons.
EVALUASI KEMAMPUAN PRODUKSI RIPPING DOZER RIPPER D375 UNTUK MENCAPAI TARGET PRODUKSI BATUBARA 180.000 TON BULAN OKTOBER DI TAMBANG AIR LAYA EXTENTION TIMUR FRONT LIMOA PT BUKIT ASAM (PERSERO) TBK UPTE: Evaluate Performance Production Of Dozer Ripper D375 To Have Coal Production Target Was 180.000 Ton On Month October In East Extention Of Tambang Air Laya Front Limoa Pt Bukit Asam (Persero) Tbk Upte) Fredrick, Gregorius; Tono, E.P.S.B Taman; Irvani, Irvani
MINERAL Vol 1 No 1 (2016): Mineral
Publisher : Program Studi Teknik Pertambangan Universitas Bangka Belitung

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.33019/mineral.v1i1.1611

Abstract

Coal production target in East extension of TAL Limoa Front was 180.000 ton/month in October2015 but the target achieved only 115.967,59 ton with the percentage achievement of productiontarget at 64,4 %. Therefore it was necessary to evaluate performance of Dozer Ripper D375 numberseries DZ 521. The evaluation conducted by taking primer actual data in mine site such as cycletime, work distance, work effeciency, Ripper penetration and then the collecting data was processedto make reparations of DZ 521 type of D375 Ripper with the aim to meet the production target. Theachieved production after prior evaluation conducted by increasing work time effeciency was162.826,57 ton with the production achievement percentage at 90.45 % and the lack production was17.173,43 ton, a further evaluation was conducted by repairing of Ripper penetration performance andthe production was 206.138,22 ton with the production achievement percentage at 114% and theexceed production was 26138,22 ton. Then work time efficiency and Ripper penetration was improvedto obtain target production of 289.475,83 ton with the production achievement percentage at 160%and exceed production of 109.475,83 ton with time reserve 150 hours/month and 4,8 hours/daymaybe can back up the problems on location production. The evaluation had been met coalproduction target of Limoa Front.