The Design of Project Procurement Management to Improve Company Performance Project (Study Case: Warehouse Manufacture) Mochammad Ravi Armanda Putra; Gatot Yudoko; Muhammad Hanafi
Cerdika: Jurnal Ilmiah Indonesia Vol. 5 No. 10 (2025): Cerdika: Jurnal Ilmiah Indonesia
Publisher : Publikasi Indonesia

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.59141/cerdika.v5i10.2687

Abstract

The Indonesian construction industry continues to face significant challenges related to project delays, especially in warehouse manufacturing projects. These delays often result in increased costs, reduced quality, and weakened stakeholder trust. This research aims to analyze the primary causes of delays in the warehouse construction project of PT. WMA and to design a procurement management framework that improves project performance. By conducting qualitative methods such as group discussions, the study identifies key contributing factors, including poor planning, weak interdepartmental coordination, supplier delays, and insufficient procurement monitoring. Root cause analysis was conducted using the Current Reality Tree (CRT), revealing that the lack of effective procurement management was the central issue. The study proposes a comprehensive procurement management framework based on the PMBOK 6th Edition, emphasizing the importance of planning, executing, and controlling procurement processes. Implementation of this framework is expected to reduce project delays and enhance the overall performance of construction projects. The findings not only contribute to academic knowledge but also provide practical recommendations for improving procurement practices in Indonesia’s construction sector.
Integration of Lean Management, Agile/Scrum, and PMBOK in Improving The UAT Process (A Case Study of Banking Co.) Dedi Yusuf Hernanto; Gatot Yudoko
Jurnal Locus Penelitian dan Pengabdian Vol. 5 No. 7 (2026): JURNAL LOCUS: Penelitian dan Pengabdian
Publisher : Riviera Publishing

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.58344/locus.v5i7.5920

Abstract

Digital transformation in the Indonesian banking industry has significantly in-creased pressure on software testing processes. At Banking Co., the number of features under testing rose by 295% between 2022 and 2024, from 5,840 to 43,595 features, while the existing UAT work procedures remained unchanged. This imbalance led to systematic waste, repeated rework, and increased burnout risk, threatening both operational sustainability and human capital. This study aims to identify dominant waste types in the UAT process, formulate an integrated Lean–Agile/Scrum–PMBOK solution, and analyze its potential impact on efficiency and team sustainability. A mixed methods approach was applied through a 65-item Likert survey targeting a population of 371 Testing Analysts, yielding 52 valid responses, and in-depth interviews with three expert informants from different management levels. Waste prioritization was analyzed using the Relative Im-portance Index (RII) and Composite RII. The findings identified seven categories of waste across 12 UAT activities, with Defects (0.756), Movement (0.735), and Waiting (0.725) ranking as the most dominant. The study also revealed a significant perception gap between practitioners and management regarding Movement waste, demonstrating the importance of triangulation in identifying hidden operational problems. Based on these findings, eight improvement op-tions integrating Lean Management, Agile/Scrum, and PMBOK principles were proposed, including Shared Accountability, System Stabilization, WIP Limit, Definition of Ready, and Lean-based UAT procedures. The results indicate that eliminating systemic waste could significantly reduce burnout risk and improve long-term team sustainability.
Strategic Product Mix Decisions Through Route-Level Costing: A Case Study in the Polypropylene Manufacturing Industry Gabriela Melati Sari; Gatot Yudoko
Almana : Jurnal Manajemen dan Bisnis Vol. 10 No. 2 (2026): August
Publisher : Bandung: Prodi Manajemen FE Universitas Langlangbuana

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.36555/almana.v10i2.3037

Abstract

Polypropylene manufacturers are impacted by volatile costs for raw materials (feedstocks), price competition from the marketplace, and their own plant capacities. As such, product mix decision-making is becoming increasingly reliant upon the accuracy of margins. This study was conducted to create a Route Level Costing Framework to aid in Margin-Informed Product Mix Planning within a Polypropylene Manufacturing Company. The methodology used for this research project involved a Quantitative Descriptive Case Study. Secondary Internal Data were collected from PT PRP, including Production Data, Grade-Formula-Route Mapping, Bill of materials (BOM) listings, Utility Consumption information, Costs and Selling Price Data. The developed framework will integrate both BOM-based cost calculations and Activity-Based Costing (ABC) Logic to Recalculate Production Costs at each Grade-Formula-Route combination. Additionally, it will compare the recalculated production cost with the Selling Price to determine Contribution Margin. The results indicate that grade-level costing may mask differences in costs and margins across different production routes. There exists a wide variation in Contribution Margin between the Current Costing Methodology and the proposed ABC-BOM Route-Level Cost Visibility framework. A total of 36 combinations of grades-formula-routes have been analyzed, and as a result there exist variations ranging from less than 1 USD/ton to greater than 17 USD/ton.
Improving Construction Performances and Reducing Delay Through Lesson Learned and Project Management Office (PMO) Implementation: A Case Study of Kucing Liar Fan 7, PT. Freeport Indonesia Rega Rinaldo Johnjudika; Gatot Yudoko
Advances In Social Humanities Research Vol. 4 No. 9 (2026): Advances In Social Humanities Research
Publisher : Sahabat Publikasi

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.46799/adv.v4i9.652

Abstract

The Kucing Liar Fan 7 project is an underground ventilation construction project within the Central Services Division of PT Freeport Indonesia. The problems arose not from a single cause but from the interaction of management, construction method, material availability, people and communication, equipment, and the underground working environment. This study aims to identify and evaluate the key lessons learned from the Kucing Liar Fan 7 project, determine how these lessons can be institutionalized through a Project Management Office (PMO), and develop an implementation roadmap to improve future construction performance. A mixed-method approach was used, combining a five-point Likert questionnaire distributed to 27 project stakeholders across six factors (Management, Method, Material, People, Environment, Equipment) with historical project data, interviews, observation, and two sessions of Focus Group Discussion (FGD). The questionnaire results were analysed using mean scores, Relative Importance Index (RII), Cronbach's alpha, and Pareto analysis. The analysis identified Management, Method, Material, People, and Environment as the prioritized factors, jointly accounting for 84.93% of the cumulative relative importance, with root causes concentrated in design readiness, change control, material planning, communication, and constrained underground working space. The lessons learned were translated into a Lesson Learned Register and a phased Controlling PMO implementation roadmap consisting of organizational assessment, pilot implementation, organizational integration, and continuous improvement. The proposed PMO does not replace the existing balanced-matrix structure but strengthens governance, standardization, coordination, monitoring, and knowledge management to reduce the recurrence of delays in future underground ventilation construction projects.
Improvement and Acceleration of Rebuild and Conversion Process for ore Wagon at Grasberg Block Cave Mine PT Freeport Indonesia Panji Adino; Gatot Yudoko
Advances In Social Humanities Research Vol. 4 No. 9 (2026): Advances In Social Humanities Research
Publisher : Sahabat Publikasi

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.46799/adv.v4i9.661

Abstract

The transition to wet muck-dominated production at PT Freeport Indonesia’s Grasberg Block Cave mine requires reliable conversion of dry-model ore wagons into wet-model units; however, delays in transportation and workshop activities have constrained production output. This study aimed to identify the root causes of inefficiencies across the Underground–Highland–Lowland logistics route and the rebuild station, as well as to formulate measures capable of sustaining a conversion rate of two wagons per week. A mixed-method approach was employed, combining field observations, project progress records, and a focus group discussion involving five stakeholder representatives. Fishbone analysis was used to examine logistics-related delays, while the Current Reality Tree was applied to identify workshop bottlenecks. Eleven alternatives were evaluated using Kepner–Tregoe Decision Analysis and Potential Problem Analysis. The findings revealed several constraints, including limited lowboy availability, access queues, coordination gaps, restricted workshop space, shared labor resources, wheelset queues, unsuitable tools, inaccurate rubber component dimensions, and paint damage risks. The use of Flat Rack Container transportation, exclusion of wheelsets from the main rebuild quotation, and separate quotations for decoupler fabrication emerged as priority short-term solutions. Five cumulative capacity improvement levers were projected to reduce the average cycle time from 23.84 to 14–15 days per wagon and increase sustainable output from approximately 2.5 to eight wagons per month. These measures provide a roadmap for meeting conversion demand before wet muck becomes the dominant production condition.
Lean Six Sigma Improvement for Reducing Material Storage in Underground Mine at PT Freeport Indonesia Andi Firdaus; Gatot Yudoko
Advances In Social Humanities Research Vol. 4 No. 9 (2026): Advances In Social Humanities Research
Publisher : Sahabat Publikasi

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.46799/adv.v4i9.664

Abstract

Material availability is essential for underground mining operations; however, fragmented storage, limited inventory visibility, and delivery delays can disrupt production and increase operational waste. This study aimed to identify the root causes of inventory control and storage management issues for ground support materials at the Grasberg Block Cave, Kucing Liar, and Deep Mill Level Zone mines of PT Freeport Indonesia and to formulate prioritized improvement strategies. A case study approach was conducted using the Lean Six Sigma DMAIC framework, incorporating observations, 5S assessments, questionnaires, semi-structured interviews, operational records, Value Stream Mapping, Pareto analysis, Current Reality Tree analysis, Action Priority Matrix, and Impact-Complexity Analysis. The findings showed that waiting was the dominant waste, with a score of 115, followed by inventory waste with a score of 98; together, these two categories accounted for 44.9% of the identified waste. Six of seven storage locations were rated as fair or poor. Four root causes were identified: the absence of standardized inventory management, inadequate control and staffing in shadow storage areas, weak storage and 5S standards, and limited availability of transportation equipment. Dedicated storemen achieved the highest Impact-Complexity Ratio score of 3.23, followed by 5S compliance at 2.59 and daily inventory reporting at 1.91. The study concludes that implementing these initiatives can strengthen traceability, accessibility, inventory accuracy, and material flow reliability across mining operations.
Project Delay Analysis and Improvement Strategy for the Mataloko Geothermal Infrastructure Project Taufan Febri Herdian; Gatot Yudoko
Eduvest - Journal of Universal Studies Vol. 6 No. 8 (2026): Eduvest - Journal of Universal Studies
Publisher : Green Publisher Indonesia

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.59188/eduvest.v6i8.53464

Abstract

Indonesia’s energy transition requires the timely delivery of geothermal infrastructure; however, project delays continue to threaten investment efficiency and renewable energy targets. This study aimed to identify and measure the factors affecting delays in the Mataloko Geothermal Infrastructure Project and formulate appropriate improvement strategies. A quantitative research design was employed using data from 74 respondents representing PT PLN (Persero), construction supervision consultants, contractors, and subcontractors. Data were collected through a five-point Likert-scale questionnaire and analyzed using Partial Least Squares Structural Equation Modeling (PLS-SEM), predictive assessment, and Importance–Performance Map Analysis (IPMA). Project documents and focus group discussions were also used to support the interpretation of findings. The model explained 59.5% of the variance in project delay impacts. Financial factors had the strongest significant effect (β = 0.409), followed by project resource management (β = 0.394) and external factors (β = 0.391). Contractor cash-flow difficulties, delayed supplier payments, low labor productivity, material shortages, manpower limitations, and community-related issues emerged as the main priorities for improvement. Planning, design, contractor-related, and owner-related factors did not have significant direct effects. The study concluded that integrated cash-flow control, resource-loaded look-ahead planning, stakeholder readiness, and accelerated owner decision-making were essential to reduce delays and improve the delivery of future geothermal infrastructure projects in Indonesia.