Evaluasi Kemajuan Proyek Pada Proses Pengendalian Kinerja Waktu Dan Biaya Dengan Metode Nilai Hasil Ahmad Zaki; Ade Nurdin; Fetty Febriasti Bahar
Jurnal KOMPOSITS Vol 2, No 2 (2021): September, Jurnal KOMPOSITS
Publisher : Universitas Muara Bungo

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.36355/jkts.v2i2.603

Abstract

This study has a purpose to analyze the progress of the cost of controlling time performance and with the Result Value method. Project performance is usually an assessment parameter in the success or failure of a project in general. Poor project management can be a bad cause and harm the project. One of the sources that causes poor project performance is usually a mismatch between the budget, implementation period, and the quality of work against the plan. One method of controlling costs and time is known as the Earned Value Method. This concept is a concept of calculating costs in accordance with the work that has been completed (budgeted cost of work performed). Road Preservation Job Packages Sp. Tuan - Bts. Kabupaten Muaro Jambi - Sp. Tiga Batara Gas Plant (Pematang Lumut) is a work package belonging to The Jambi Province Regional I National Road Implementation Unit with the Service Provider PT. Satya Wira Persada. This work package whose source of funds is from the 2021 State Budget has varied daily reports. The author evaluates the performance of the time and schedule on the project by getting the results of time and cost performance on the Road Preservation Work Package of Sp. Tuan - Bts. Kabupaten Muaro Jambi - Sp. Tiga Batara Gas Plant (Pematang Lumut) showed poor performance based on the CV = Rp. -3,037,850.00, CPI = 0.999 1000, SV = Rp. -428.871.785.62 and SPI = 0.935 1000. According to the results of the evaluation using the Value method, the predicted execution time to complete this work package is 380 days, while the time for implementation based on the contract is 360 days so that this project is predicted to experience a 20 day delay in completing the work. The Realization of the Implementation of the Road Preservation Work Package for Sp. Tuan - Bts. Kabupaten Muaro Jambi - Sp. Tiga Batara Gas Plant (Pematang Lumut) is not according to plan, this is based on reports in the twelfth week of progress of 25.680% while the planned progress is 28.554% so that there is a deviation of -2.875%. Road Preservation Work Package project conditions Sp. Tuan - Bts. Kabupaten Muaro Jambi - Sp. Tiga Batara Gas Plant (Pematang Lumut) in the twelfth week reporting period suffered losses when viewed from the cost aspect with the Yield Value method and delays when viewed from the schedule aspect with the Earned Value method
PENGARUH VARIASI PENAMBAHAN FLY ASH BATU BARA SEBAGAI PENGGANTI SEBAGIAN SEMEN TERHADAP NILAI KUAT TEKAN BATA RINGAN Reka Putri Maharani; Nazarudin Nazarudin; Fetty Febriasti Bahar
Jurnal KOMPOSITS Vol 3, No 2 (2022): September, Jurnal KOMPOSITS
Publisher : Universitas Muara Bungo

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.36355/jkts.v3i2.871

Abstract

Pada masa sekarang, terdapat berbagai jenis beton yang digunakan pada dunia konstruksi, salah satunya yaitu beton ringan.Beton ringan ini merupakan beton yang memiliki berat jenis yang rendah dibandingkan dengan jenis beton lainnya. Selain beton ringan, bata ringan juga banyak digunakan pada dunia konstruksi pada saat ini. Bata ringan memiliki perbedaan dengan beton ringan. Beton ringan menggunakan agregat kasar, sedangkan bata ringan tidak menggunakan agregat kasar. Bata ringan pada saat ini banyak digunakan pada dunia konstruksi dinding yang mana bata ringan ini menggantikan bata merah ataupun sebagai pengganti batako. Dalam upaya meminimalisir penggunaan semen maka diperlukanlah adanya inovasi baru yaitu seperti penambahan fly ash batu bara pada campuran bata ringan sebagai bahan pengganti sebagian semen. Pada penelitian ini melakukan pengujian dimana pada campupran bata ringan ini ditambahkan suatu variasi penambahan Fly Ash sebagai pengganti sebagian semen yg mana jumlah variasi pengganti sebagaian ini memiliki beberapa variasi yaitu mulai dari 5%, 7,5% hingga variasi 10%. Yg mana dari beberapa variasi ini dapat dilihat berapa nilai dari kuat tekan bata ringan pada setiap kenaikan variasi Fly Ash sebagai pengganti sebagian semen