Pengaruh Pengalaman Kerja Dan Insentif Terhadap Kinerja Pengawasan Proyek Pengembangan Bandar Udara Sultan Hasanuddin Makassar Nela Fatresia Tote; Muhammad Natsir Abduh; Savitri Prasandi Mulyani
Jurnal Penelitian Teknik Sipil Konsolidasi Vol. 4 No. 2 (2026): Jurnal Penelitian Teknik Sipil Konsolidasi, Mei 2026
Publisher : Program Studi Teknik Sipil Universitas Bosowa

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.56326/jptsk.v4i2.6395

Abstract

This study aims to determine the influence of work experience and incentives on the supervision performance of the Sultan Hasanuddin Airport development project in Makassar. A quantitative approach was employed, with data collected through questionnaires distributed to all supervisory consultants involved in the project, totaling 25 respondents. The data were analyzed using multiple linear regression, preceded by classical assumption tests, including normality, linearity, heteroscedasticity, and autocorrelation tests, to ensure the validity of the model and to examine both the simultaneous and partial effects of the independent variables (work experience and incentives) on the dependent variable (employee performance). The results indicate that work experience and incentives have a positive and significant effect on the supervision performance of the Sultan Hasanuddin Airport development project. The coefficient of determination (R²) value of 65.8% shows that both independent variables collectively explain the variation in supervision performance, while the remaining 34.2% is influenced by other variables outside this regression model or not examined in this study. These findings highlight the importance of work experience and the provision of incentives in improving the supervision performance of construction projects, particularly in the development of Sultan Hasanuddin Airport, Makassar.
Analisis Faktor-Faktor Penyebab Keterlambatan Proyek Peningkatan Ruas Jalan Bulo-Bungin Kabupaten Enrekang Muhammad Fatwa Anugrah; Natsir Abduh; Savitri Prasandi Mulyani
Jurnal Penelitian Teknik Sipil Konsolidasi Vol. 4 No. 2 (2026): Jurnal Penelitian Teknik Sipil Konsolidasi, Mei 2026
Publisher : Program Studi Teknik Sipil Universitas Bosowa

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.56326/jptsk.v4i2.6506

Abstract

Management is one of the key factors in the success of project implementation. Constraints in management, such as errors in istimating the time needed to complete the project during the planning stage, or various unforeseen obstacles, can hinder project execution. This study aims to indetify the factors causing delays in the Bulo-Bungin road improvement project in Enrekang Regency and to determine the most significant delay factors. The research results show that the factors influencing the delay in project completion, based on 49 indicators used to measure the research variables, have correlation coefficients greater than the table r = 0.279, indicating the questionnaire is valid. Based on the analysis, the five main factors causing delays in the Bulo-Bungin road project are Equipment usage skills 3.74, Workforce skills 3.70, Workforce discipline 3.64, Rework due to defect or errors 3.64, Communication between workers and foremen 3.62.
Evaluasi Penjadwalan Dengan Metode Earned Value: Studi Kasus Pada Pekerjaan Pengadaan Dan Pemasangan Baggage Handling System Di Bandar Udara  Sultan Hasanuddin Makassar Delvi Tiku; Muhammad Natsir Abduh; Savitri Prasandi Mulyani
Jurnal Penelitian Teknik Sipil Konsolidasi Vol. 4 No. 2 (2026): Jurnal Penelitian Teknik Sipil Konsolidasi, Mei 2026
Publisher : Program Studi Teknik Sipil Universitas Bosowa

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.56326/jptsk.v4i2.6893

Abstract

The procurement and installation of the Baggage Handling System (BHS) at Sultan Hasanuddin International Airport is a strategic project with high complexity. Common challenges faced in such projects include schedule delays and cost overruns, making it necessary to apply an evaluation method that provides a comprehensive picture of project performance.This study applies the Earned Value Management (EVM) method, which integrates cost, time, and work progress. Data were collected from the baseline schedule, S-curves, and weekly progress reports. The analysis was conducted by calculating the main EVM indicators (BCWS, BCWP, ACWP) and derivative measures such as CV, SV, CPI, and SPI, along with completion forecasts using Estimate at Completion (EAC) and Estimate at Schedule (EAS).The results show that the Schedule Performance Index (SPI) < 1 indicates project delays, while the Cost Performance Index (CPI) > 1 reflects cost efficiency. Although project costs are under control, the estimated completion time is likely to exceed the contractual schedule. Thus, EVM proves to be an effective tool for evaluating project performance and supporting strategic decision-making in construction project management
Analisis Produktivitas Tenaga Kerja Pada Proyek Pemasangan Saluran Pipa Beton RCP Di Green River View (GRV) Tanjung Bunga Kurniawan Kombong Langi; Savitri Prasandi Mulyani; Satriawati Cangara
Jurnal Penelitian Teknik Sipil Konsolidasi Vol. 4 No. 2 (2026): Jurnal Penelitian Teknik Sipil Konsolidasi, Mei 2026
Publisher : Program Studi Teknik Sipil Universitas Bosowa

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.56326/jptsk.v4i2.7329

Abstract

Construction projects heavily depend on efficient human resource utilization. Decreased productivity is a common issue, leading to project delays and increased costs. This study aims to analyze labor productivity in the installation of Reinforced Concrete Pipe (RCP) drainage in Green River View (GRV) Tanjung Bunga. This research employed a six-day field observation. Productivity data was analyzed using the Labor Utilization Rating (LUR) method to measure time efficiency, supplemented by interviews to identify qualitative factors. The average LUR was 53.20%, categorized as fairly efficient. Productivity fluctuated daily, influenced by factors such as weather, worker tardiness, differences in work tools, smoking habits, team coordination, and supervision quality. The work group with high discipline and modern tools showed the highest LUR. LUR proved to be an effective indicator for measuring work efficiency and management performance. This study recommends improving time management, standardizing tools, and enhancing supervision to boost overall project productivity.