Optimasi Pemotongan Besi Tulangan Pada Pekerjaan Struktur Menggunakan Metode Linear Programming Jajang Atmaja; Fauna Adibroto; Nurul Hidayah
Borneo Engineering : Jurnal Teknik Sipil Volume 4 Nomor 2 Tahun 2020
Publisher : Jurusan Teknik Sipil, Fakultas Teknik, Universitas Borneo Tarakan

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.35334/be.v4i2.1595

Abstract

In construction projects, reinforcing iron is a very important material in the implementation of construction work. The remaining iron material cannot be avoided in the field, so the figure for the remaining unused material affects the costs incurred by the contractor. Given that iron material is one of the materials with a high price on the market. One solution to reduce the amount of remaining iron material is to optimize iron cutting to get the number of pieces as needed with minimal cutting. The method used is Linear Programming with the help of the Solver Add-In program in Microsoft Excel. The research was conducted on a 3-storey building construction project, namely Puskesmas Kampung Dalam, Kab. Padang Pariaman. Works that reflect iron work on the upper and lower structures. The analysis results were obtained from 7.31% and cost Rp. 27.067.887,-.  for the ironworks reviewed. So that the use of the Linear Programming method in the case study of this research is able to optimize the remaining iron material quite well and produce minimum remaining reinforcing iron.
Perbandingan Cost Significant Model Dengan Metode Parametrik Untuk Estimasi Biaya Gedung Bertingkat 2 di Provinsi Sumatera Barat Jajang Atmaja -; Elvi Roza Syofyan; Anne Fadillah -
Jurnal Ilmiah Poli Rekayasa Vol 14, No 1 (2018)
Publisher : Pusat Penelitian dan pengabdian kepada Masyarakat (P3M) Politeknik Negeri Padang

Show Abstract | Download Original | Original Source | Check in Google Scholar | Full PDF (449.156 KB) | DOI: 10.30630/jipr.14.1.104

Abstract

The estimated cost at the initial or conceptual stage is an estimate made when there is still little information about the image, description and specifications of the work to be done. This estimate is needed to provide information on the initial description of the total construction costs. Estimated costs must be accurate so as not to cause problems in the future. To obtain a method that meets these needs, we compare two estimation methods, namely the Cost Significant Model and the Metode Parametrik. This study aims to determine the components of the calculation needed by the Cost Significant Model and Parametric Method and the comparison of the two in making cost estimates and for determining the most accurate method. This research was applied to the construction of a 2-storey building in the province of West Sumatra. Data related to the study were collected from consultants in the city of Padang with 9 (nine) RAB data complete with project information originating from 2013 s.d. 2016Based on the Cost Significant Model analysis, the regression analysis formula is obtained: Y = 1,340,187,179 + 3,175 X2 + 0,295 X10 + 7,072 X11 + 1,881 X4 - 4,134 X13, where X2 is Foundation Work Cost, X10 is Wall Work Cost, X11 is Door Work Cost and Window, X4 is Column Work Costs, X13 is Floor Work Costs. This cost estimation model has been validated with an average error percentage of 0%. Metode Parametrik Analysis using the formula set out in Presidential Regulation No. 73 of 2011 Article 14: Total Project Costs = HSBGN x K x Project Area, where HSBGN is the Price of the State Building Building Unit and K is the multiplier multiplier for multi-storey buildings. This cost estimation model has been validated with an average error percentage of 32%. Based on the results of this error percentage, it is concluded that the most accurate method is the Cost Significant Model.To obtain a small earth (near zero) resistivity value is determined by the number of planted electrodes and soil type properties. Difficulty in obtaining this small resistivity value often errors in estimating soil properties or soil type resistance so that failure to obtain soil barriers often occurs.To determine the desired amount of material can be measured soil type resistor value, by measuring the soil resistivity value so that the estimated material cost estimation can be achieved well. then in this research using geoelectric method with Schlumberger configuration. Schlumberger method is a method with a constant system of spacing rules with the note of the 'n' multiplier is the comparison of the distance between the C1-P1 or (C2-P2) electrodes with P1-P2. The instrument used is a resistivity meter ( Naniura) equipped with four electrodes which have the ability to read output voltage response due to current injected into the ground surface through two current electrodes and two potential electrodes. In this study used progress to map the 2D isoresistivity beneath the measured surface. .The results of this soil resistivity measurement can be determined with certainty the amount of material used and the cost of workmanship provided to establish the proper grounding system to be attached to a 20 kV Distribution substation at the State Polytechnic Padang State Electricity Laboratory. So that the grounding system in pairs meet the standards that have been determined and can be categorized both and safe for humans and equipment for grounding Distribution Distributors 20 kV Electricity Engineering Laboratory at the State Polytechnic Campus Padang.
Analisa Kajian Penggunaan Alat Berat Pada Pekerjaan Tanah Proyek Pembangunan Jalan (Studi Kasus : Zona I Pada Proyek Pembangunan Jalan Tol Padang-Pekanbaru By Pass Km 25) Jajang Atmaja
Jurnal Ilmiah Poli Rekayasa Vol 17, No 1 (2021)
Publisher : Pusat Penelitian dan pengabdian kepada Masyarakat (P3M) Politeknik Negeri Padang

Show Abstract | Download Original | Original Source | Check in Google Scholar | Full PDF (286.983 KB) | DOI: 10.30630/jipr.17.1.209

Abstract

A project work rarely runs smoothly, usually there will be some obstacles. Excavation, stockpiling, and compaction work is an early stage of road construction that requires heavy equipment assistance. One of the causes of problems that usually arise in earthworks using heavy equipment is in the form of an operator who is not skilled. This study aims to calculate the productivity, cost and time of heavy equipment and calculate the composition of heavy equipment usage. The method used in this study was to collect primary and secondary data. The results of the calculated analysis show that the most efficient composition is in the third alternative, namely 2 Excavators 676.04 m³ / day, 5 Dump Trucks 260.75 m³ / day, 2 Bulldozers; 807.93 m³ / day, 2 SheepFoot Rollers; 1215.90 m³ / day, 2 Vibration Rollers; 1215.90 m³ / day, and 3 Water Tanker Trucks; 479.99 m³ / day with a total cost of IDR 2,131,752,569.29
Optimalisasi Waktu dan Biaya dengan Metode Time Cost Trade Off Pada Proyek Konstruksi Jalan Monika Natalia; Jajang Atmaja
Jurnal Ilmiah Poli Rekayasa Vol 17, No 1 (2021)
Publisher : Pusat Penelitian dan pengabdian kepada Masyarakat (P3M) Politeknik Negeri Padang

Show Abstract | Download Original | Original Source | Check in Google Scholar | Full PDF (521.463 KB) | DOI: 10.30630/jipr.17.1.208

Abstract

During the implementation of project work, there are various kinds of problems that will hinder project performance, so that the project will not be completed as planned, whether it is not on time, quality, and the cost, which sometimes occurs swelling. The road widening project for Lubuk Alung - Kuraitaji Road, Padang Pariaman District experienced a delay in implementation in the 16th week with a deviation of -7.091%. For this reason, it is necessary to control project implementation using the earned value method. From the analysis, the total duration of the project is 170 days, while the contract time is 150 days. This indicates a delay in project implementation for 20 days. In order to keep the project duration in accordance with the contract duration, it is necessary to accelerate it using the Time Cost Trade Off method. Acceleration is done by comparing 2 alternatives, namely the addition of working hours (overtime) and additional work shifts. After the comparisons were made, the additional acceleration cost of overtime work hours was Rp. 1,676,510,600.23 and alternative work shifts of Rp. 307,721,835.6 for direct costs. So the alternative chosen is an alternative work shift, because it has a small incremental cost, and is more efficient than using an alternative working hour overtime, while the duration of the project completion has returned to the contract time. The additional cost that must be paid by the contractor if the acceleration is not carried out is IDR 1,013,632,840.6, it would be more appropriate if the acceleration was carried out to overcome the delays in the Lubuk Alung - Kuraitaji Road Section in Padang Pariaman Regency, with a loss of IDR 307,722,000
Analisa Perbandingan Percepatan Penyelesaian Proyek Dengan Metode (Studi Kasus : Proyek Mercu Suar,Yogyakarta) Jajang Atmaja -
Jurnal Ilmiah Poli Rekayasa Vol 14, No 2 (2019): -
Publisher : Pusat Penelitian dan pengabdian kepada Masyarakat (P3M) Politeknik Negeri Padang

Show Abstract | Download Original | Original Source | Check in Google Scholar | Full PDF (274.237 KB) | DOI: 10.30630/jipr.14.2.128

Abstract

Time constraints are often a problem in construction projects. Project scheduling and consistent evaluation are needed so that the project is completed on time. Evaluation is applied using performance intensity methods and Microsoft Project. Performance Intensity is a calculation carried out to determine the pace of project work. Performance intensity provides information on how quickly an activity can be completed. For the calculation of Performance Intensity use PPI, API and CPI. To control work in the field using CCS and CCP. Evaluation to find out the time performance applied to the Yogyakarta Lighthouse project. The project is planned to be completed on December 14, 2014 with a duration of 266 days. Evaluation is carried out for 35 periods. The results of this evaluation are differences in the analysis of the final day between the method of Performance Intensity and Microsoft project. The final day analysis of Performance Intensity at week 35 for 279 days, while analysis of Microsoft Project for 280 days. Differences in the range of predictions for the day-to-day analysis of a project are caused by the Performance Intensity method using the average cumulative work rate as a benchmark that changes every period. To pursue delays, the project acceleration method is used, namely Schedule. The time needed for the Schedule is 80 days.
Analisa Kinerja Proyek Menggunakan Metoda Earned Value Management dan Pengendalian dengan Metoda Time Cost Trade Off (Studi Kasus Proyek Pembangunan Jembatan Silaosinan Kabupaten Mentawai) Jajang Atmaja; Etri Suhelmidawati; Hendra Alexander; Monika Natalia; Rafella Nola Hanika
JURNAL TEKNIK SIPIL ITP Vol 7, No 2 (2020): JURNAL TEKNIK SIPIL (JTS) ITP
Publisher : LP2M ITP

Show Abstract | Download Original | Original Source | Check in Google Scholar

Abstract

Pengolahan
Analisis Konsep Nilai Hasil Dengan Metode Time Cost Trade-Off pada Proyek Rumah Susun Monika Natalia; Jajang Atmaja; Dini Sekar Putri; Putri Helena
JTERA (Jurnal Teknologi Rekayasa) Vol 7, No 1: June 2022
Publisher : Politeknik Sukabumi

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.31544/jtera.v7.i1.2022.163-172

Abstract

Konsep nilai hasil memberikan informasi kinerja proyek dan menghasilkan estimasi biaya dan waktu untuk penyelesaian seluruh pekerjaan proyek. Proyek rumah susun PIK Pulo Gadung Tahap II Jakarta Timur mengalami deviasi sebesar -12,70% pada hari ke-441 (minggu ke-63) pelaksanaan dari total durasi 569 hari akibat pandemi Covid-19. Hal ini karena pembatasan tenaga kerja, pembatasan pemasokan material, dan pembatasan waktu kerja instansi pemerintahan menyebabkan kepengurusan administrasi tidak maksimal. Penelitian ini bertujuan untuk mengukur kinerja proyek rumah susun PIK Pulo Gadung Jakarta Timur. Metode penelitian yang digunakan yaitu dengan analisis konsep nilai hasil menggunakan aplikasi Microsoft Project untuk mendapatkan kinerja proyek. Selanjutnya untuk percepatan waktu penyelesaian proyek dilakukan dengan metode Time Cost Trade-Off (TCTO) menggunakan crashing program. Hasil analisis didapat perkiraan waktu penyelesaian proyek adalah 666 hari atau selisih 97 hari dibandingkan rencana awal. Sisa durasi untuk menyelesaikan pekerjaan yang tersisa sebesar 225 hari dengan proyeksi biaya akhir sekitar 57 milyar rupiah atau terjadi penyimpangan sekitar 6 milyar rupiah dibandingkan biaya awal. Alternatif percepatan durasi proyek dengan metode TCTO yaitu dengan menambah shift kerja dimana proyek selesai lebih cepat tiga hari daripada penambahan jam kerja dan biaya lebih hemat sebesar 1,8 milyar rupiah.
Analisa Kinerja Proyek Menggunakan Metoda Earned Value Management dan Pengendalian dengan Metoda Time Cost Trade Off (Studi Kasus Proyek Pembangunan Jembatan Silaosinan Kabupaten Mentawai) Jajang Atmaja; Etri Suhelmidawati; Hendra Alexander; Monika Natalia; Merley Misriani; Rafella Nola
Jurnal Teknik Sipil Institut Teknologi Padang Vol 7 No 2 (2020): Jurnal Teknik Sipil Institut Teknologi Padang
Publisher : ITP Press

Show Abstract | Download Original | Original Source | Check in Google Scholar | Full PDF (367.581 KB) | DOI: 10.21063/jts.2020.V702.06

Abstract

Pengolahan suatu proyek sangat bergantung pada pengendalian setiap aktivitas, sehingga pelaksanaan suatu proyek konstruksi dapat senantiasa terkontrol. Earned Value Management method adalah salah satu cara yang dapat digunakan untuk mengetahui kinerja dari proyek. Pada pelaksanaan pekerjaan Pembangunan Jembatan Silaosinan, Kabupaten Mentawai, Sumatera Barat ini, terjadi keterlambatan dalam pelaksanaannya, maka penulis meninjau ulang dari minggu ke-26 dimana bobot realisasi 48,044% sedangkan bobot rencana 51,328%, terdapat deviasi (3,284%), maka perlu dilakukan perhitungan biaya sisa dan waktu tersisa sampai minggu ke-26, kemudian dilakukan percepatan agar proyek dapat kembali sesuai kontrak. Hasil yang didapatkan dari penelitian ini adalah nilai estimasi biaya penyelesaian proyek (Estimate at Completion) adalah sebesar Rp 28.091.045.542 , nilai estimasi waktu penyelesaian proyek (Time Estimate) 41,475 minggu. Alternatif penambahan tenaga kerja dan penambahan shift kerja dilakukan dalam mempercepat pelaksanaan proyek. Keadaan proyek kembali ke durasi rencana dengan penambahan biaya sebesar Rp 685.220.700.
Andromeda Table Merley Misriani; Jajang Atmaja
Jurnal Abdimas: Pengabdian dan Pengembangan Masyarakat Vol 2 No 1 (2020)
Publisher : Pusat Penelitian dan Pengabdian Kepada Masyarakat

Show Abstract | Download Original | Original Source | Check in Google Scholar | Full PDF (386.507 KB)

Abstract

Pada umumnya, sebagian besar pelajar-pelajar di Panti Asuhan setelah tamat dari SMA/SMK tidak melanjutkan pendidikan ke jenjang perguruan tinggi karena terkendala biaya. Sebagian dari mereka, akan melangkah ke dunia kerja. Namun melihat lapangan kerja yang ada, untuk tamatan SMA/SMK akan sangat sulit bagi mereka untuk mendapatkan pekerjaan yang baik dan layak. Oleh sebab itu, anak-anak Panti Asuhan harus dibekali dengan pengetahuan, wawasan, skill serta kreativitas untuk dapat menuangkan berbagai ide kreatif yang dapat membuka lapangan kerja sendiri. Salah satu upaya membuka lapangan kerja adalah dengan Andromeda Table (kayu bekas dengan resin). Andromeda Table bisa menjadi alternatif jitu untuk sumber penghasilan dan membuka lapangan kerja dalam rangka meggalakkan wirausaha mandiri untuk menghasilkan produk inovatif dalam menghadapi dunia kerja yang semakin sempit. Andromeda Table mengusung konsep eco living (hidup hemat energy dengan tujuan melestarikan alam) dapat diolah lagi menjadi perabotan rumah tangga dengan biaya yang jauh lebih ekonomis. Dengan sedikit kreativitas, Andromeda Table ini juga dapat dimanfaatkan untuk ide-ide komersil lainnya. Materialnya mudah didapat, tidak sulit dalam pengerjaannya, tidak membutuhkan biaya tinggi, menghasilkan produk yang unik, elegan dan bernilai jual. Tujuan yang ingin dicapai dari kegiatan pengabdian ini adalah dapat memberikan wawasan, meningkatkan ketrampilan/skill dan keinginan berwirausaha mandiri bagi anak-anak Panti Asuhan. Yaitu dengan mengolah sisa-sisa kayu yang terbuang menjadi sebuah furniture baru yang unik, elegan, bernilai seni dan nilai jual tinggi dengan penambahan resin dan pewarna.
Metode Kawat Strimin Untuk Mencegah Keruntuhan Getas Pada Dinding Yan Partawijaya; Mafriyal -; Jajang Atmaja; Satwarnirat -; Hendra Alexander
Jurnal Abdimas: Pengabdian dan Pengembangan Masyarakat Vol 3 No 1 (2021)
Publisher : Pusat Penelitian dan Pengabdian Kepada Masyarakat

Show Abstract | Download Original | Original Source | Check in Google Scholar | Full PDF (186.851 KB)

Abstract

Dinding bangunan umumnya terbuat dari bata yang mempunyai beberapa kelemahan diantaranya berat dan getas. Akibat beratnya yang cukup besar maka akan menaikkan beban mati struktur sehingga beban gempa juga akan naik. Hal ini disebabkan karena beban gempa akan meningkat secara linier terhadap berat struktur bangunan tersebut. Sedangkan akibat dari sifatnya yang getas maka pada tingkat perubahan bentuk (deformation) yang relatif rendah retak-retak tidak dapat dihindari (Satiawan, 2016). Salah satu metode perkuatan dinding terhadap keruntuhan adalah dengan metode kawat strimin. Nusantoro, A. 2012, Pemasangan kawat dstrimin dilakukan di sepanjang tulangan, di sebelah luar dan dalam dengan lebar minimal 45 cm. Kemudian kawat strimin diikat (luar dan dalam) dengan menggunakan 2 utas kawat D2 mm, terakahir ditutup dengan mortar. Dengan teknologi ini, masyarakat dapat memperkuat dinding rumah tinggal mereka terhadap gempa dengan biaya yang murah, material mudah didapat dan waktu pelaksanaan yang singkat serta pengerjaan yang tidak rumit. Tujuan yang ingin dicapai dari kegiatan pengabdian ini adalah dapat memberikan wawasan, meningkatkan ketrampilan/skill bagi masyarakat Kampani dalam memperbaiki rumah tinggal agar mempunyai perkuatan terhadap gempa dengan metode kawat strimin. Metode yang diterapkan pada kegiatan ini dengan melakukan penyuluhan, sosialisasi, diskusi dengan pemuka masyarakat dan memberikan palatihan pemasangan kawat strimin untuk mencegah keruntuhan getas.