ANALISIS VARIASI PENAKSIRAN SUMBERDAYA BATUBARA MENGGUNAKAN METODE INVERSE DISTANCE WEIGHT DAN ORDINARY KRIGING Y. A. Yulanda; M. E. Hakim; R. Arafat; Ericson .
Jurnal Pertambangan Vol 6 No 2 (2022): Mei 2022
Publisher : Fakultas Teknik Universitas Sriwijaya

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.36706/jp.v6i2.1442

Abstract

Penaksiran sumberdaya batubara merupakan tahapan penting dalam kegiatan industri pertambangan batubara. Terdapat dua jenis metode yang lazim digunakan dalam penaksiran sumber daya yaitu Metode Inverse Distance Weight (IDW) dan Ordinary Kriging (OK). Kedua metode tersebut menggunakan sistem grid blok dalam penaksiran. Beberapa penelitian sebelumnya cenderung hanya memperlihatkan perbedaan selisih pada nilai total hasil penaksiran. Belum ditemukan penelitian yang memperlihatkan nilai variasi pada setiap grid blok estimasi. Penelitian ini bertujuan untuk mengetahui variasi nilai kedua metode tersebut pada setiap grid blok. Adapun data yang menjadi objek penaksiran adalah ketebalan batubara (coal thickness). Di dalam penelitian ini, kedua metode juga akan membandingkan tonase sumber daya batubara guna mengetahui perbedaan hasil perhitungan sumber daya. Data penelitian berupa 60 titik bor eksplorasi yang diolah menggunakan perangkat lunak perhitungan sumber daya batubara. Berdasarkan hasil penaksiran sumber daya batubara menggunakan Metode IDW diperoleh jumlah sumber daya batubara sebesar 49.101.422 Ton. Perolehan sumber daya batubara hasil kalkulasi Metode IDW menunjukkan selisih yang tidak terlalu signifikan dibandingkan dengan penggunaan Metode Ordinary Kriging yang menunjukkan nilai sebesar 47.521.660 Ton. Variasi nilai estimasi yang dihasilkan kedua metode tersebut rata-rata berkisar 3%.
EVALUASI KINERJA JIG TIPE PAN AMERICAN TERHADAP RECOVERY TIMAH HASIL PENCUCIAN BIJIH TIMAH PADA KAPAL ISAP PRODUKSI (KIP) TIMAH 17 DI LAUT TEMPILANG KABUPATEN BANGKA BARAT, PROVINSI BANGKA BELITUNG Abror, Muhammad; Lagowa, Muhammad Ikrar; Hakim, Muhammad El
Jurnal Teknologi Mineral dan Batubara Vol 20 No 3 (2024): Jurnal Teknologi Mineral dan Batubara Edisi September 2024
Publisher : Balai Besar Pengujian Mineral dan Batubara tekMIRA

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.30556/jtmb.Vol20.No3.2024.1589

Abstract

The early stage of mineral processing usually focuses mainly on recovery, not the grade of the concentrate. Tin dressing in Production Section Vessel on January 2023 did not meet target recovery of 96%. This study aimed to evaluate and optimize jig performance to achieve the desired target. The study focused on evaluating the configuration of variables such as feed velocity, bed thickness, as well as number and length of strokes. Measurement data of jig performance variables and tailings and concentrate samples were used as comparative data to the SOP. The calculation of the sample content was carried out through the grain counting analysis (GCA) method, which calculated the amount of concentrate and losses in each jig. The final results of washing recovery prior to washing evaluation were 92.70% Sn in observation I and 88.68% Sn in observation II, respectively. The washing process in observation I and II conditions were not considered optimal because the recovery had not reached the target. This is caused by variables that are not under the provisions To optimize the performance of the jig was the installation a comb in the flow section of the jig to standardize the flow that was too fast, remeasurement after the addition of the hematite stone, repairing pillow blocks and eccentric coupling bolts on the stroke length setting and resetting the variables in the jig performance following existing SOPs. After the evaluation and readjustment of the jig variables, the recovery was increased to 97.53% Sn. From this study it can be concluded that the failure to achieve the targeted recovery was caused by operational variables that did not meet the SOP including the length and number of strokes, bed thickness, and water flow rate due to technical constraints. After being repaired, the dressing recovery could meet or even exceed the recovery target.
EVALUASI KINERJA JIG TIPE PAN AMERICAN TERHADAP RECOVERY TIMAH HASIL PENCUCIAN BIJIH TIMAH PADA KAPAL ISAP PRODUKSI (KIP) TIMAH 17 DI LAUT TEMPILANG KABUPATEN BANGKA BARAT, PROVINSI BANGKA BELITUNG Abror, Muhammad; Lagowa, Muhammad Ikrar; Hakim, Muhammad El
Jurnal Teknologi Mineral dan Batubara Vol 20 No 3 (2024): Jurnal Teknologi Mineral dan Batubara Edisi September 2024
Publisher : Balai Besar Pengujian Mineral dan Batubara tekMIRA

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.30556/jtmb.Vol20.No3.2024.1589

Abstract

The early stage of mineral processing usually focuses mainly on recovery, not the grade of the concentrate. Tin dressing in Production Section Vessel on January 2023 did not meet target recovery of 96%. This study aimed to evaluate and optimize jig performance to achieve the desired target. The study focused on evaluating the configuration of variables such as feed velocity, bed thickness, as well as number and length of strokes. Measurement data of jig performance variables and tailings and concentrate samples were used as comparative data to the SOP. The calculation of the sample content was carried out through the grain counting analysis (GCA) method, which calculated the amount of concentrate and losses in each jig. The final results of washing recovery prior to washing evaluation were 92.70% Sn in observation I and 88.68% Sn in observation II, respectively. The washing process in observation I and II conditions were not considered optimal because the recovery had not reached the target. This is caused by variables that are not under the provisions To optimize the performance of the jig was the installation a comb in the flow section of the jig to standardize the flow that was too fast, remeasurement after the addition of the hematite stone, repairing pillow blocks and eccentric coupling bolts on the stroke length setting and resetting the variables in the jig performance following existing SOPs. After the evaluation and readjustment of the jig variables, the recovery was increased to 97.53% Sn. From this study it can be concluded that the failure to achieve the targeted recovery was caused by operational variables that did not meet the SOP including the length and number of strokes, bed thickness, and water flow rate due to technical constraints. After being repaired, the dressing recovery could meet or even exceed the recovery target.
ANALISIS PENCAMPURAN BATUBARA PADA PT. BUKIT ASAM TBK DALAM UPAYA MENINGKATKAN KUALITAS BATUBARA UNTUK MEMENUHI KRITERIA PERMINTAAN PLTU BUKIT ASAM TANJUNG ENIM, SUMATERA SELATAN Fitriani. A; Zahar, Wahyudi; El Hakim, Muhammad
Jurnal Teknologi Mineral dan Batubara Vol 20 No 3 (2024): Jurnal Teknologi Mineral dan Batubara Edisi September 2024
Publisher : Balai Besar Pengujian Mineral dan Batubara tekMIRA

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.30556/jtmb.Vol20.No3.2024.1563

Abstract

PT. Bukit Asam Tbk provides BA 50 type coal to be sent to the Bukit Asam Tanjung Enim PLTU. The aim of this research is to obtain coal that suits the needs of the Bukit Asam Tanjung Enim PLTU. The method used is to simulate the blending of several types of coal at PT. Bukit Asam Tbk such as mine brand AL 49, mine brand AL 51, mine brand AL 53 and mine brand AL 55. The blending method uses the stack arrangement method with the layer arrangement method using the layered method. The research results show that the blending  simulation consists of 11 types of blending, four of which cannot be used as recommendations because they have a higher calorific value than BA 50. Of the seven recommended simulations, the AL 49 AL 51 simulation has the highest profit price value compared to the agreed selling price, namely $0.38 per ton and $1,157.55 per day or equal to IDR 18,216,357.16 per day. In this research, it is not only recommended to blend coal with two types of coal of different qualities, but innovation is carried out by blending which can be done with more than two types of coal of different qualities.
ANALISIS PENCAMPURAN BATUBARA PADA PT. BUKIT ASAM TBK DALAM UPAYA MENINGKATKAN KUALITAS BATUBARA UNTUK MEMENUHI KRITERIA PERMINTAAN PLTU BUKIT ASAM TANJUNG ENIM, SUMATERA SELATAN Fitriani. A; Zahar, Wahyudi; El Hakim, Muhammad
Jurnal Teknologi Mineral dan Batubara Vol 20 No 3 (2024): Jurnal Teknologi Mineral dan Batubara Edisi September 2024
Publisher : Balai Besar Pengujian Mineral dan Batubara tekMIRA

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.30556/jtmb.Vol20.No3.2024.1563

Abstract

PT. Bukit Asam Tbk provides BA 50 type coal to be sent to the Bukit Asam Tanjung Enim PLTU. The aim of this research is to obtain coal that suits the needs of the Bukit Asam Tanjung Enim PLTU. The method used is to simulate the blending of several types of coal at PT. Bukit Asam Tbk such as mine brand AL 49, mine brand AL 51, mine brand AL 53 and mine brand AL 55. The blending method uses the stack arrangement method with the layer arrangement method using the layered method. The research results show that the blending  simulation consists of 11 types of blending, four of which cannot be used as recommendations because they have a higher calorific value than BA 50. Of the seven recommended simulations, the AL 49 AL 51 simulation has the highest profit price value compared to the agreed selling price, namely $0.38 per ton and $1,157.55 per day or equal to IDR 18,216,357.16 per day. In this research, it is not only recommended to blend coal with two types of coal of different qualities, but innovation is carried out by blending which can be done with more than two types of coal of different qualities.
Potensi Logam Tanah Jarang pada Fly Ash dan Bottom Ash Endapan Batubara Peringkat Rendah Formasi Muara Enim Wahyudi Zahar; Yudi Arista Yulanda; Jarot Wiratama; Muhammad El Hakim
Jurnal Sains dan Teknologi: Jurnal Keilmuan dan Aplikasi Teknologi Industri Vol. 25 No. 2 (2025): Regular Issue
Publisher : SEKOLAH TINGGI TEKNOLOGI INDUSTRI PADANG

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.36275/wffpht91

Abstract

Logam tanah jarang (LTJ) merupakan komoditas strategis saat ini seiring dengan perkembangan teknologi. Penggunaan LTJ banyak diaplikasikan pada industri pertahanan, kesehatan, mobil listrik, turbin, handphone, laptop, dan teknologi maju lainnya. Keterdapatan LTJ pada umumnya berasosiasi sebagai mineral-mineral aksesoris pada batuan berkomposisi granitoids seperti pada monasit, xenotim, allanit, titanit, dan zircon. Akan tetapi berdasarkan beberapa penelitian ditemukan adanya pengkayaan LTJ pada abu sisa pembakaran PLTU FABA (fly ash dan bottom ash). Pada penelitian ini bertujuan untuk menganalisis keterdapan LTJ pada kondisi batubara Peringkat Rendah di Formasi Muara Enim pada endapan insitu dan pengkayaan pada FABA. Sampel batubara diambil secara grab sampling pada lokasi tambang sedangkan sampel FABA diambil secara grab sampling di PLTU Mulut Tambang. Pengujian Laboratorium dilakukan melalui Uji XRF untuk melihat kandungan oksida mineral dan Laboratorium BRIN untuk dilakukan analisis ICP OES. Hasil analisis XRF menunjukkan elemen oksida utama penyusun batubara pada endapan batubara insitu terdiri atas Fe2O3, MgO, dan SO3. Hasil analisis ICP-OES memperlihatkan terjadi pengkayaan konsentrasi LTJ pada FABA. Pengkayaan paling besar terjadi pada unsur Cerium (Ce) dimana pada Fly Ash terjadi peningkatan 19 kali menjadi 40,12 Ppm dan pada Bottom Ash 17 kali menjadi 37,15 Ppm. Selanjutnya pada Lantanum (La) terjadi pengkayaan 27 kali pada fly ash menjadi 19,02 Ppm dan 24 kali pada bottom ash menjadi 16,86 Ppm. Secara umum pengkayaan terjadi lebih besar pada fly ash dibandingkan dengan bottom ash.
Pemodelan Endapan dan Estimasi Sumberdaya Batubara dengan Block Model di PT Batubara Jambi Lestari Kecamatan Mestong Kabupaten Muaro Jambi Yulian Aliffano; Yudi Arista Yulanda; Muhammad El Hakim
OPHIOLITE: Jurnal Geologi Terapan Vol 7 No 2 (2025): AGUSTUS 2025
Publisher : Universitas Halu Oleo

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.56099/ophi.v7i2.p67-74

Abstract

Jambi Province holds significant potential in energy and mineral resources, particularly coal, part of which has been exploited while others are still under exploration. PT Batubara Jambi Lestari plans to develop an open-pit mine in the northern block of its IUP-OP area, necessitating deposit modelling and coal resource estimation as the basis for mine planning. Thus far, coal modelling has generally relied on stratigraphic models for geological interpretation, whereas the application of block models to coal deposits remains limited. This study seeks to address this gap by examining the use of block models in coal deposit modelling. Resource estimation was conducted using the Nearest Neighbour Point (NNP) method, selected due to its suitability for relatively homogeneous coal deposits, computational efficiency, and minimal bias against local variability. The research focused on the northern block of the Muara Enim Formation, the main coal-bearing formation, with modelling carried out through correlation between drill holes. The resulting model illustrates a deposit shaped like a horse back, characterized by coal seams and sediments arching upward due to compressional forces, with an average dip of 12°. The application of the block model required manual adjustments through a trial-and-error approach to ensure consistency with the geological database, but it successfully represented the geological conditions. The estimation results indicate a measured coal resource of 2,013,750 tons, which provides an important reference for mine planning at PT Batubara Jambi Lestari.