PENERAPAN METODE CPM DAN CCPM UNTUK PERENCANAAN SUMBER DAYA DAN WAKTU PENYELESAIAN MULTI PROYEK Sri Rahayu; Pram Eliyah Yuliana; Kelvin Kelvin
JISO : Journal of Industrial and Systems Optimization Vol 5, No 2 (2022): Desember 2022
Publisher : Universitas Maarif Hasyim Latif

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.51804/jiso.v5i2.92-98

Abstract

ABSTRAK Penelitian ini dilakukan pada perusahaan yang bergerak di bidang supplies dan engineering dan berlokasi di Surabaya. Perusahaan mempunyai beberapa proyek dalam waktu yang dekat maupun bersamaan. Salah satunya adalah proyek alat pengupas bawang dan proyek exhaust silencer yang harus diselesaikan sesuai dengan waktu yang ditetapkan dengan sumber daya yang terbatas. Untuk menyelesaikan hal tersebut maka pentingnya untuk dilakukan perencanaan terhadap jadwal dengan menggunakan metode critical path method dan juga critical chain project management. Pada critical path method bertujuan untuk melihat kegiatan mana saja yang harus menjadi perhatian perusahaan dalam pelaksanaannya agar tidak menyebabkan keterlambatan penyelesaian. Lalu dengan mmetode critical chain project management bertujuan untuk mengatur penjadwalan terhadap tenaga kerja yang melakukan pekerjaan terhadap beberapa proyek. Setelah melakukan analisa, dari hasil penelitian didapatkan untuk proyek alat pengupas bawang pada metode critical path method adalah 56 hari dari waktu normal 59 hari, sedangkan untuk proyek exhaust silencer 46 hari dari waktu normal 47. Lalu untuk metode critical chain project management, kegiatan multiproyek mengalami kemunduran selama 15 hari pada proyek alat pengupas bawang, namun hal tersebut masih berada dalam project buffer.  ABSTRACTThis research was conducted at supplies and engineering company in Surabaya. The company has several projects in the near future or at the same time. One of them is the onion peeler project and the exhaust silencer project which must be completed in accordance with the specified time with limited resources. To solve this problem, it is important to plan the schedule using the critical path method and also critical chain project management. The critical path method aims to see which activities the company should pay attention to in its implementation so as not to cause delays in completion. Then the critical chain project management method aims to regulate the scheduling of workers who work on several projects. After conducting the analysis, the research results obtained for the onion peeler project on the critical path method is 56 days from the normal time of 59 days, while for the exhaust silencer project it is 46 days from the normal time of 47. Then for the critical chain project management method, multi-project activities experience 15 day setback on the onion peeler project, but it's still in the project buffer.
PENERAPAN METODE CPM DAN CCPM UNTUK PERENCANAAN SUMBER DAYA DAN WAKTU PENYELESAIAN MULTI PROYEK Rahayu, Sri; Yuliana, Pram Eliyah; Kelvin, Kelvin
JISO : Journal of Industrial and Systems Optimization Vol. 5 No. 2 (2022): Desember 2022
Publisher : Universitas Maarif Hasyim Latif

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.51804/jiso.v5i2.92-98

Abstract

ABSTRAK Penelitian ini dilakukan pada perusahaan yang bergerak di bidang supplies dan engineering dan berlokasi di Surabaya. Perusahaan mempunyai beberapa proyek dalam waktu yang dekat maupun bersamaan. Salah satunya adalah proyek alat pengupas bawang dan proyek exhaust silencer yang harus diselesaikan sesuai dengan waktu yang ditetapkan dengan sumber daya yang terbatas. Untuk menyelesaikan hal tersebut maka pentingnya untuk dilakukan perencanaan terhadap jadwal dengan menggunakan metode critical path method dan juga critical chain project management. Pada critical path method bertujuan untuk melihat kegiatan mana saja yang harus menjadi perhatian perusahaan dalam pelaksanaannya agar tidak menyebabkan keterlambatan penyelesaian. Lalu dengan mmetode critical chain project management bertujuan untuk mengatur penjadwalan terhadap tenaga kerja yang melakukan pekerjaan terhadap beberapa proyek. Setelah melakukan analisa, dari hasil penelitian didapatkan untuk proyek alat pengupas bawang pada metode critical path method adalah 56 hari dari waktu normal 59 hari, sedangkan untuk proyek exhaust silencer 46 hari dari waktu normal 47. Lalu untuk metode critical chain project management, kegiatan multiproyek mengalami kemunduran selama 15 hari pada proyek alat pengupas bawang, namun hal tersebut masih berada dalam project buffer.  ABSTRACTThis research was conducted at supplies and engineering company in Surabaya. The company has several projects in the near future or at the same time. One of them is the onion peeler project and the exhaust silencer project which must be completed in accordance with the specified time with limited resources. To solve this problem, it is important to plan the schedule using the critical path method and also critical chain project management. The critical path method aims to see which activities the company should pay attention to in its implementation so as not to cause delays in completion. Then the critical chain project management method aims to regulate the scheduling of workers who work on several projects. After conducting the analysis, the research results obtained for the onion peeler project on the critical path method is 56 days from the normal time of 59 days, while for the exhaust silencer project it is 46 days from the normal time of 47. Then for the critical chain project management method, multi-project activities experience 15 day setback on the onion peeler project, but it's still in the project buffer.
PERANCANGAN FASILITAS KERJA YANG ERGONOMIS PADA DIVISI FILLETING DENGAN MENGGUNAKAN NBM DAN SOFTWARE JACK Kelvin; Anggriawan, Armando Edo; Yuliana, Pram Eliyah; Lawrenta, Mattew; Rahayu, Sri
JISO : Journal of Industrial and Systems Optimization Vol. 7 No. 2 (2024): Desember 2024
Publisher : Universitas Maarif Hasyim Latif

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.51804/jiso.v7i2.8-15

Abstract

ABSTRAKPada sebuah perusahan frozen food di Surabaya, terdapat divisi Filleting, dimana operator bekerja selama 8 jam sehari untuk proses fillet ikan beku. Banyak keluhan terkait kesehatan yang dirasakan oleh para operator tersebut. Keluhan-keluhan tersebut kemudian dibuatkan tabel NBM dan diketahui beberapa frekuensi yang tinggi adalah pada leher atas, leher bawah, bahu, punggung, dan betis. Hal ini dikarenakan fasilitas kerja yang berupa konveyor yang digunakan pada proses fillet ikan beku tidak ergonomis. Untuk mengatasi hal tersebut, maka dibuatlah rancangan perbaikan konveyor dengan menggunakan data Anthropometri operator divisi filleting. Dimensi tubuh yang digunakan adalah tinggi bahu untuk tinggi rak konveyor dengan memakai persentil 50%, dimensi tinggi siku operator untuk menentukan tinggi meja konveyor dengan memakai persentil 5% sampai 95%, dimensi panjang lengan bawah operator untuk menentukan lebar meja konveyor dengan memakai persentil 5%, dimensi panjang rentangan tangan ke samping operator untuk menentukan panjang meja konveyor dengan memakai persentil 95%, dan dimensi panjang tinggi genggaman tangan keatas berdiri operator untuk menentukan tinggi rangka konveyor dengan memakai persentil 95%. Dan rancangan perbaikan konveyor yang dibuat dengan AutoCad kemudian disimulasikan dengan menggunakan software JACK untuk mengetahui efektifitasnya. Dan terbukti ketika simulasi dijalankan, indikator yang ada berwarna kuning yang artinya adalah kegiatan ini memiliki dampak yang cukup signifikan pada tubuh pekerja, terutama terkait dengan postur tubuh yang dianggap kurang nyaman. ABSTRACTAt a frozen food company in Surabaya, there is a Filleting division, where operators work 8 hours a day to process frozen fish fillets. There are many health complaints made by these operators. These complaints were then made into an NBM table and it was discovered that some of the high frequencies were in the upper neck, lower neck, shoulders, back and calves. This is because conveyor as the work facilities that used in the frozen fish fillet process are not ergonomic. To solved this problem, a conveyor repair plan was created using anthropometric data from filleting division operators. The body dimensions used are shoulder height for the height of the conveyor rack using the 50% percentile, the operator's elbow height dimension to determine the height of the conveyor table using the 5% to 95% percentile, the operator's forearm length dimension to determine the width of the conveyor table using the 5% percentile. , the long dimension of the operator's arm stretch to the side to determine the length of the conveyor table using the 95% percentile, and the long dimension of the height of the hand grip to the operator's stand to determine the height of the frame conveyor using the 95% percentile. And the conveyor repair design made in AutoCad is then simulated by using JACK software to determine its effectiveness. And it was proven that when the simulation was run, the indicator was yellow, which means that this activity has a quite significant impact on the worker's body, especially related to body postures that are considered uncomfortable.