METODE PLAKSANAAN PEKERJAAN SLAB PADA JEMBATAN CILUTUNG DI KEC. TOMO KAB. SUMEDANG Maryono; Juliar, Eka
SEMINAR TEKNOLOGI MAJALENGKA (STIMA) Vol 7 (2023): STIMA 7.0 "Transformasi Peradaban Akademik Menyongsong Revolusi Industri 5.0"
Publisher : Universitas Majalengka

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.31949/stima.v7i0.882

Abstract

Cilutung Bridge is one of the bridges located on Jalan Raya Tolengas, Tolengas, Tomo District, Sumedang Regency. Bridges have various types of bridges, namely girder bridges, arch bridges, truss bridges, suspension bridges. The bridge component is divided into two, namely the superstructure and the substructure. The structure of the bridge generally includes: sidewalks, vehicle floor slabs, girders, diaphragm beams, and platforms. The structure under the bridge generally includes: the base of the bridge (abutments), bridge pillars (piers) and foundations. The bridge slab is a horizontal structural element that functions to distribute dead and live loads to the vertical support frame of a structural system. The stages of implementing the bridge slab work are 1. Preparatory work, 2. Steel bridge deck installation, 3. Steel bridge deck grouting work, 4. Cantilever slab formwork assembly, 5. Slab and parapet reinforcement assembly, 6. Cantilever slab formwork installation, 7. Check completeness and measurement, 8. Bridge slab reinforcement installation, 9. Bridge parapet reinforcement installation, 10. Bridge slab formwork installation 11. Measurement, 12. Block out deck drain installation, 13. Bridge slab floor cleaning, 14. Inspection, 15. Bridge slab casting, 16. Slump and quality check, 17. Formwork demolition work, 18. Maintenance and tidiness.
METODE PELAKSANAAN PEKERJAAN LANTAI PARTISI DI SALURAN INDUK CIPELANG PADA RENTANG IRRIGATION MODERNIZATION PROJECT Sunarya, Yoyo; Juliar, Eka
SEMINAR TEKNOLOGI MAJALENGKA (STIMA) Vol 7 (2023): STIMA 7.0 "Transformasi Peradaban Akademik Menyongsong Revolusi Industri 5.0"
Publisher : Universitas Majalengka

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.31949/stima.v7i0.972

Abstract

The Range Irrigation Area is a national strategic project located in the lowlands of the lower reaches of the Cimanuk River in the Northeastern part of West Java Province. The modernization of Span Irrigation is carried out because the age of the irrigation system is decaded old, causing reduced water service performance due to narrowing of the enbankments, sediment and groundwater infiltration in the Cipelang Main Canal. The use of material for contruction that is on the ground surface of this irrigation canal is by using a concrete floor (partition floor) which aims to reduce the water loss factor in the Cipelang Main Canal. The techninal work for making concrete floors is carried out in a Cast In Site manner, meaning the type of concrete casting work on site or directly in the workplace. The Partition Concrete Floor work in the Cipelang main canal aims to reduce the water loss factor so that it can increase the efficiency of irrigation water use. Partition Concrete Floor use K-175 concrete quality with cast in site technical work, not using precast concrete. There are 9 (nine) stages regarding the Partition Floor Work Implementation Method, namely starting from the work of Preparation, Kisdam, Dewatering, Excavation + Furnishing and Installation Filter, Lean Concrete Floor, Wiremesh + Install Beam and Footing Reinsforcement, Casting In Site, Finishing Top Floor, Concrete Curing.
ANALISA PRODUKTIVITAS KERJA WAKTU DAN BIAYA ALAT BERAT PADA PROYEK MODERNISASI IRIGASI RENTANG KAB. INDRAMAYU Suminaryati, Sigit Aprilyanto Prabowo; Juliar, Eka
SEMINAR TEKNOLOGI MAJALENGKA (STIMA) Vol 8 (2024): STIMA 8.0 : Menuju Kesinambungan : Inovasi dan Adaptasi Teknologi untuk Pembangunan Be
Publisher : Universitas Majalengka

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.31949/stima.v8i0.1151

Abstract

Abstract The Modernization of the Rentang Irrigation Project in Indramayu Regency plays a strategic role in supporting food security and agricultural sector development. The use of heavy equipment is crucial for ensuring the smooth and efficient execution of irrigation work. This study aims to identify the heavy equipment used, the productivity of the heavy equipment, the duration of the activity cycles, and the estimated costs of operating the heavy equipment in the Rentang Irrigation Modernization Project. The research was conducted through direct field observations to collect data on the time required by each piece of heavy equipment during soil reclamation work. This data was then used to calculate the productivity of the heavy equipment. The results showed that the production capacity of the Kubota U50 Excavator is 27.79 m3/hour. The required working duration for the Excavator is 154.23 hours, with an estimated operational cost of Rp. 267,541,273. The production capacity of the Dump Truck is 5.45 m3/hour, with a required working duration of 147.73 hours and an estimated operational cost of Rp. 568,013,231. The production capacity of the Vibro Roller is 63.56 m3/hour, with a required working duration of 337.14 hours and an estimated operational cost of Rp. 112,817,843.