Claim Missing Document
Check
Articles

Found 39 Documents
Search

Analisa Waste Material Konstruksi Dengan Menggunakan Metode Lean Construction Studi Kasus : Pekerjaan Pembangunan Puskesmas Purwodadi Kabupaten Tanjung Jabung Barat Yuniar, Riana; Handayani, Elvira; Amalia, Kiki Rizky
Jurnal Civronlit Unbari Vol 8, No 2 (2023): Oktober
Publisher : Universitas Batanghari

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.33087/civronlit.v8i2.119

Abstract

Material is one component of the cost that plays an important role in supporting the success of a project. In the implementation of building construction projects, leftover materials or Construction Waste cannot be avoided. Excess material, whether from work results or from construction materials that are left/scattered/destroyed and cannot be used again, is called construction waste. Thus, a method is needed for the efficiency of remaining construction materials (Intan et. Al,2005). Construction in Indonesia currently has many problems regarding inefficiency in the implementation of construction. The causes of this inefficiency include poor performance, waste of resources used during the construction process, but this does not add value to the function of the resources used. Based on data submitted by the Lean Construction Institute (LCI), waste in the construction industry is around 57% and activities that provide added value are only 10% (Abduh, 2007). In construction projects, problems are often found in the construction process, such as changes to project drawings, changes to specifications, poor storage, and other technical problems in the field that cause material waste. Problems like this can have an impact on project cost losses beyond what was planned.Lean Construction is very necessary in construction projects so that waste does not occur due to the problems that have been explained previously, it is hoped that it can reduce waste on the project. So that it can reduce costs caused by waste and can establish better relationships between individuals involved in the project.
Evaluasi Pengendalian Waktu dengan Metode Time Cost Trade Off pada Proyek Fiberline Building And Relocation New Area Woodyard Handayani, Elvira; Immanuddin, M.
Jurnal Civronlit Unbari Vol 8, No 2 (2023): Oktober
Publisher : Universitas Batanghari

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.33087/civronlit.v8i2.120

Abstract

Projects generally have a deadline, meaning that the project must be completed before or on time. In connection with this project problem, the success of a project can be measured from three things, namely, cost, quality and timeliness of completion. Many efforts must be made in order to achieve what has been planned, including calculating the correct strength of the structure, calculating cost estimates that are effective and economical. In implementing the construction of the Fiberline 3 Building (FL3B) & Relocation New Area Woodyard PT project. Riau Andalan Pulp And Paper indicated that there was a delay in the Excavation, Bacfilling & Cutting/Breaking Top Of Pile work, therefore the researchers accelerated it by rescheduling. This is intended so that this project can be completed according to the planned target. The method that will be used to speed up the duration of the project in this research is the Time Cost Trade Off method or also called the cost versus time exchange method. Based on the results of the Time Cost Trade Off Analysis on the Fiberline 3 Building project (FL3B) & Relocation New Area Woodyard PT. Riau Andalan Pulp And And Paper, it can be concluded as follows: Acceleration of project duration for the alternative of increasing overtime working hours by 4 (four) hours is obtained:The optimum time to accelerate the project duration is 142 calendar days with an increase in direct costs from Rp. 3,145,559,610.00 to Rp. 3,346,947,482.50. The total optimum project cost due to accelerated project duration increased from Rp. 3,806,175,528.10 to Rp. 4,007,523,400.60. Acceleration of project duration for the alternative of increasing the number of workers was obtained. The optimum time for accelerating the project duration was 142 calendar days with an increase in direct costs from Rp. 3,145,559,610.00 to Rp. 3,220,683,352.66 Total optimum project costs due to accelerated project duration increased from Rp. 3,806,175,528.10 to Rp. 3,881,259,270.76.
Kajian Pemeriksaan Kondisi Jembatan di Ruas Jalan Nasional Provinsi Jambi (Studi kasus: Jembatan Rangka) Handayani, Elvira; Nuklirullah, M.; Saputra, Wahyu
Jurnal Civronlit Unbari Vol 9, No 1 (2024): April
Publisher : Universitas Batanghari

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.33087/civronlit.v9i1.123

Abstract

Bridge inspection is one of the most important parts in a bridge management information system. Bridge inspection is related to bridge requirements, planning for maintenance or service improvement in the future. This study discusses the framework of bridges on several bridges which are stretched on Jambi provincial roads, specifically the Sei Bridge. Bernai, Lubuk Kuari and Sei Bridge. Trap Expected more than 25 years. The examination in this study only waits for the detailed inspection of the manual issued by the public works department. This study uses the calculation method proposed in the BMS (Bridge Management System) which has been translated into SMJ (Bridge Management System) based on conditions that occur in the field. The results of the bridge situation examination obtained from this study are Sei. Trapping has a condition value of 1, Lubuk Kuari has a condition value of 2, Sei. Bernai has a condition value of 1.
Penerapan Value Engineering pada Proyek Konstruksi di Masa Pandemi Covid-19 Zulfiati, Ria; Handayani, Elvira; Saputra, Ade Rio
Jurnal Civronlit Unbari Vol 8, No 2 (2023): Oktober
Publisher : Universitas Batanghari

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.33087/civronlit.v8i2.118

Abstract

Value Engineering is a function analysis approach that aims to reduce the cost of production or project. The amount of costs that will be needed both in the planning period and also the implementation and time saving process are sought not to increase the amount of cost itself. Gamil & Alhagar(2020) revealed that there are several impacts of Covid-19 in the construction sector, namely project suspensions, workers who lose their jobs, jobs that exceed the time limit, excessive costs, and financial impacts. Jallow et al (2020) stated the changes that must be made to the infrastructure sector in order to comply with health protocols and remain productive during lockdown. The problem in this study is how much the total cost savings can be obtained after Value Engineering method to the architectural work of the Facilities and Infrastructure Rehabilitation project at the Sungai Gelam Campground in the Hall Building. Through graphs and calculations is, the results of 4 work items with the highest percentage were obtained, namely on wall pair work, roofing work, floor formwork work, and frame, door and window work. At the creative stage, the idea of alternative replacements is given to the same quality, function and quality, but at a lower price. Then the analysis stage carries out the development of a comparison between the alternatives to be obtained. The recommendation stage is the result of the chosen alternative. At the recommendation stage, the result of applying the value engineering method is the Material used for the work of the red Masonry 5x11x22cm amounting to Rp.1,934,368.62 or 9.16% of the initial design cost. For Metal Tile Roofing Work of Rp.7,775,287.18 or 30.27% of the initial design cost. For Aluminum Frame, Door and Window Work, 8mm Glass is Rp.8,360,275 or 20% of the initial design cost. For Ceramic Floor Work measuring 40x40 cm (Plain) of Rp. 12,926,981.30 or 25.26% of the initial design cost. The cost efficiency that can be obtained using Rp. 30,996,912.10 or 6% of Rp. 514,217,599.92,- the total project
Identifikasi Urutan Prioritas Penanganan dalam Pemeriksaan Kondisi Jembatan dengan Metode Bridge Management System (BMS) Akbar, Abi Oktariva; Handayani, Elvira; Dwiretnani, Annisaa; Zulfiati, Ria
Jurnal Talenta Sipil Vol 7, No 2 (2024): Agustus
Publisher : Universitas Batanghari Jambi

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.33087/talentasipil.v7i2.613

Abstract

One piece of infrastructure that has an important role in a road network is a bridge. Bridges are land transportation infrastructure that is useful for continuing roads through existing obstacles such as rivers, so the collapse of a bridge will reduce or hold up traffic, which means disrupting the smooth transportation of people and goods. A bridge is a structure that crosses a river or other traffic barrier, so the collapse of the bridge will reduce or hold back traffic, which as a result will disrupt the comfort of traffic and disrupt economic relations. The purpose of a bridge inspection is to ensure that the bridge is in a safe condition for road users and also to secure the investment value of the bridge. In this thesis, we will discuss the identification of bridge condition checks which are carried out directly by conducting field surveys.
Analisa Penilaian Kondisi Jembatan Sarolangun Batang Tembesi Dengan Metode Bridge Manajemen System (BMS) Pratama, Dicky Ardian; Handayani, Elvira; Dwiretnani, Annisaa; Suhendra, Suhendra
Jurnal Talenta Sipil Vol 7, No 1 (2024): Februari
Publisher : Universitas Batanghari Jambi

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.33087/talentasipil.v7i1.449

Abstract

Bridges are an important part of a road network system because they have a significant impact if the bridge collapses or if it does not function properly. A bridge is a structure that crosses a river or other traffic barrier, so the collapse of the bridge will reduce or hold back traffic, which as a result will disrupt the comfort of the public in traffic and disrupt economic relations. A bridge is a structure that crosses a river or other traffic barrier, which as a result disrupts people's comfort in traffic and disrupts economic relations (Bridge Inspection Guidelines 2012). Bridges are built so that pedestrians, vehicle or train drivers can cross these obstacles. However, it turns out that there are many types of bridges which of course vary both in terms of structure, strength and even construction costs. The main components of a bridge are the unity of the road embankment structure approaching the bridge, the sub-bridge structure and the bridge super-structure (BMS, 1993). The main objective of this research is to analyze the condition of the Sarolangun Batang Tembesi Bridge by observing it visually, assessing the technical condition of the bridge, and determining the priority order for bridge maintenance based on its condition value. However, the database results produced in this bridge management system are only limited to screening and ranking results in preparing bridge management programs (Directorate General of Highways, Bridge Management Systems, (1993), "IBMS General Procedure Guide", BMS, Department of Public Works of the Republic of Indonesia.
Strategi Harga Penawaran Tender pada Proyek Konstruksi Dengan Memperhitungkan Faktor Resiko Wulandari, Annisa; Handayani, Elvira; Dony, Wari
Jurnal Talenta Sipil Vol 7, No 2 (2024): Agustus
Publisher : Universitas Batanghari Jambi

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.33087/talentasipil.v7i2.662

Abstract

To get a construction project through a process called a tender (auction). This process is very crucial in determining the party who will carry out the construction project. For this reason, a strategy is needed, one of which is determining the offering price. The bid price really determines the possibility of winning a construction project as well as the size of the profit or profit on the construction project. One of the problems that is often encountered is determining the offering price which should not be too high or too low. The aim of this research is to analyze the mark up value in construction project tenders at the Jambi City Electronic Procurement Institute (LPSE) using the Friedman Method, Gates Method, and Ackoff & Sasieni Method bidding strategy approaches and compare the strategic approaches that produce optimum mark up values so that can be used as an alternative in determining the offering price. The data used in this research is auction data for construction work that has been completed at Electronic Procurement Institute (LPSE) Jambi in 2022 using three statistical approaches, namely multi discrete distribution, multi normal distribution and single normal distribution. In this research it can be concluded that the Friedman Method and Ackoff & Sasieni Method produce the lowest optimum mark up value, while the Gates Method produces the highest optimum mark up value.
Pengaruh Penambahan Zat Aditif Anti Striping (WETFIX-BE) Pada Kinerja Campuran Aspal Beton (AC-WC) Fakhrul Rozi Yamali; Al Paris, Fadhil Qodri; Yamali, Fakhrul Rozi; Handayani, Elvira
Jurnal Civronlit Unbari Vol 9, No 2 (2024): Oktober
Publisher : Universitas Batanghari

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.33087/civronlit.v9i2.128

Abstract

The asphalt concrete layer is the top layer of road pavement construction which is in direct contact with vehicle wheel loads and the influence of weather. One type of asphalt concrete layer is Asphalt Concrete – Wearing Course (AC–WC). Asphalt functions as an aggregate adhesive. In asphalt concrete mixtures it is very important to maintain its characteristics. During the maintenance period, the mixture will easily experience striping or peeling of the asphalt from the aggregate. To maintain and improve the properties of asphalt, one way is to use an anti-striping additive, this additive is Wetfix-Be, which is a compound that contains chemicals. Anti-peeling materials are only used if the residual Marshall stability value (IRS-Index of Retained Stability) or the Indirect Tensile Strength Ratio (ITSR) value of the asphalt mixture before adding the anti-peeling agent is less than required. If an anti-flaking agent must be used then before the anti-flaking agent is added to the mixture, the residual marshall stability (after 24 hour immersion, 60 °C) must be at least 75%.
Faktor - Faktor Penyebab Waste Material pada Proyek Peningkatan Jalan dengan Cor Beton, Kec. Bayung Lencir Handayani, Elvira; Setiawan, Ari; Riananda, Agif
Jurnal Talenta Sipil Vol 8, No 1 (2025): Februari
Publisher : Universitas Batanghari Jambi

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.33087/talentasipil.v8i1.769

Abstract

Waste is a form of inefficiency and waste that arises from waiting time, materials, Human Resources, construction implementation, management, design and documentation, and external factors. This research aims to determine the factors causing high material waste in road improvement projects in Musi Banyuasin by taking samples at the construction project site. In analyzing the factors that cause material waste, there are several ways to find out, namely the data collection method in this research uses a questionnaire, while the analysis method uses the Descriptive Mean and the Borda method. This research shows that the waste that most often occurs in road improvement projects is external. Meanwhile, the waste variable that has the biggest impact on the project is soil type with a score of 510 using the Borda method calculation and 3.59 using the mean calculation.