Critical Chain Project Management for Hospital Reconstruction: Cost and Time Optimization Agusta, Berlinda Alveria; Tjendani, Hanie Teki; Gan, Buntara Sthenly
Acitya Wisesa: Journal of Multidisciplinary Research Vol. 5 Issue 2 (2026)
Publisher : jfpublisher

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.56943/jmr.v5i2.970

Abstract

Construction project delays represent a persistent challenge in Indonesian infrastructure development, with delay rates reaching 38% and causing substantial cost overruns and quality compromises. This research evaluated the application of Critical Chain Project Management methodology to optimize cost and time performance in the Undata Hospital Phase II-B Rehabilitation and Reconstruction Project in Palu, Central Sulawesi, which experienced significant delays from 240 contracted days to 426 actual implementation days. Using Microsoft Project for critical chain identification and Root Square Error Method for buffer calculation, the study analyzed 228 structural work activities to determine schedule optimization potential. Results identified nine critical chain activities concentrated in foundation work, requiring 60-day project buffer and 36-day feeding buffer allocation. CCPM application achieved 159-day duration reduction (43.1% improvement) compared to actual implementation, reducing total duration from 369 days to 210 days. Economic analysis revealed potential labour cost savings of IDR 7,398,931,383.36 (59.0% reduction) through elimination of embedded safety time and strategic buffer placement. Comparative evaluation demonstrated that traditional scheduling dispersed 183 days of safety time across individual activities, manifesting as work expansion through Parkinson's Law effects. Even under partial buffer consumption scenarios, CCPM maintained substantial performance advantages, confirming methodology robustness. These findings support CCPM adoption for Indonesian reconstruction projects requiring complex coordination, extended durations, and strategic schedule management under international funding frameworks.
Co-Authors Abdul Q, Muhammad Ali Hasymi Abid, Ahmad Rois Adam, Ijaz Agusta, Berlinda Alveria Alan Muin, Oskar Ezra Alifian, Muhammad Hilmi Alves, Agata Maria Orleans Aprilina, Sasa Ariyanto, Subkhan Asmoro, Mochamad Ranoe Assyifa, Moh Zahdi Aviska Triayaska Balido, Pandji Thoha S. Budi Witjaksana, Budi Dani, Bintang Arma Erni Puspanantasari Putri, Erni Puspanantasari Esti Wulandari Esti Wulandari Farokhman, Moh Fani Febryan, Daniswara Fawwaz Firdaus, Muhammad Bayu Firmansyah, Mochamad Gan, Buntara Sthenly Hastijanti, Ar. RA. Retno I Wayan Gunawan, I Wayan Intan Kusumaningayu Jaka Purnama Jamiludin, Jamiludin Khakimin, Achmad Lukmanul Klau, Maria Junita Koten, Oktafiano Agustinus Laksono Djoko Nugroho Luis, Laurenco Mardiah, Arifa Muchamad Lutfi, Muchamad Mughni, Amalia Fathimah Azh Zhahra Muhammad Efendi, Muhammad Muhammad Shohib, Muhammad Muqaddas, Zaiful Novianto, Muhammad Taufik Nugraha, Budidarma Ardi Nurkaruniati, Titik Oetomo, Wateno Patriadi, Andi Pramadha, Ichsan Yanuansyah Pratama, Arfi Wahyu Pratondo W, Wahyu Proboretno, Wuri Puspanantasari, Erni Rahmad Oktantiyo, Abiyyu Rahmatullah, Yan Rakasyiwi, Gilang Ramadhan Renden, Afrianto Tandi Riduwan, Sanda Praja Risma Marleno Riyadi, Noor Rizkiardi, Aditya Rochmat, Muhammad Fikri Ar Rohim, Abd. Rudiansyah Sajiyo Sajiyo, Sajiyo Saputri, Firda Auliya Ajie Selan, Mikdon Tobi Sembiring, Yuriza Fauziah SETIAWAN, ENDIK Setyagraha, Javan Agustian Shinta Berlinda Wulandari Slamet Riyadi Sugeng Hariyadi, Sugeng Suprapto, Aki’ Supriyanto, Yunaidi Veithzal Rivai Zainal Widyaningsari, Nidya Zuhri, Syaefuddin