cover
Contact Name
Shiska Fauziah
Contact Email
jurnalcesunisnu@gmail.com
Phone
+6285850462694
Journal Mail Official
jurnalcesunisnu@gmail.com
Editorial Address
JL. TAMAN SISWA (pekeng) unisnu jepara, Kab. Jepara, Provinsi Jawa Tengah
Location
Kab. jepara,
Jawa tengah
INDONESIA
Jurnal Civil Engineering Study
ISSN : -     EISSN : 28300750     DOI : https://doi.org/10.34001/jces
Core Subject : Engineering,
Jurnal Civil Engineering Study (JCES) contains writings about applications in the field of Civil Engineering. This application may come from all branches of civil engineering, be it structural, geotechnical, construction management, hydrology, transportation, and civil engineering informatics. So this application is not only about the business of building a building project, but also makes it possible to model a shape with the help of software.
Articles 138 Documents
Perencanaan Struktur Gedung Perkuliahan (6) Enam Lantai Kampus II Universitas Tunas Pembangunan Surakarta Dengan Metode Sistem Ganda (Dual System) Okta Tri Kurniawan; Kukuh Kurniawan Dwi Sungkono; Dian Arumningsih Diah Purnamawanti
Jurnal Civil Engineering Study Vol. 6 No. 02 (2026): Jurnal Civil Engineering Study
Publisher : Civil Engineering of Universitas Islam Nahdlatul Ulama Jepara

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.34001/ces.v6i02.2058

Abstract

The construction of the lecture building at Tunas Pembangunan University (UTP) Surakarta is one of the facilities needed to create a comfortable and conducive learning environment, while also serving as a representation of the university's identity. The structural design of this lecture building employs a Dual System method. The project site is classified as Site Class D (medium soil condition). The structural analysis was carried out in accordance with SNI 2847:2019 for reinforced concrete design, SNI 1726:2019 for seismic load analysis, and loading requirements based on SNI 1727:2020 and PPPURG 1987. The results of the seismic force distribution analysis for the dual system indicate that the moment-resisting frame carries 83,801% of the base shear force in the X-direction and 59,573% in the Y-direction. Meanwhile, the shear wall carries 16,199% of the base shear force in the X-direction and 40,427% in the Y-direction. The structural design resulted in a roof slab thickness of 120 mm, floor slab thickness of 130 mm, B1 beams measuring 350/600 mm, B2 beams measuring 350/550 mm, B3 beams measuring 300/450 mm, B4 beams measuring 300/400 mm, K1 columns measuring 600/600 mm, K2 columns measuring 500/500 mm, K3 columns measuring 450/450 mm, tie beams measuring 400/500 mm, shear walls with a thickness of 200 mm, retaining walls with a thickness of 200 mm, and bored pile foundations with a diameter of 500 mm and a depth of 9 m.
Mixed-Methods Assessment of Schedule Performance: S-Curve Deviation and Delay Factors in a Warehouse Project Kikit Wulandari; Lutfi Marantica
Jurnal Civil Engineering Study Vol. 6 No. 02 (2026): Jurnal Civil Engineering Study
Publisher : Civil Engineering of Universitas Islam Nahdlatul Ulama Jepara

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.34001/ces.v6i02.2064

Abstract

Schedule delays in industrial construction raise costs and weaken contractor credibility. S-curve monitoring shows when and by how much a project departs from plan, but not why. This study assesses the schedule performance of a production warehouse project using a convergent mixed-methods design that links weekly S-curve deviation to stakeholders’ accounts of delay factors; delay means observed slippage (negative cumulative deviation from plan). Data comprised the 40-week S-curve, a 32-item Likert questionnaire (35 respondents) and interviews with seven informants, integrated in a joint display. The project led its plan by +4.10% in Week 22, turned negative in Week 26, peaked at -7.69% in Week 31 and stayed behind schedule for 15 weeks until contract end. Interviews identified steel erection as the work most affected. The highest-rated factors were communication barriers (M9, 4.43), extreme weather (E1, 4.43), insufficient labour (T4, 4.40) and no alternative bad-weather plan (E2, 4.40). Interviews added what the survey could not: all informants named delayed steel deliveries as a main reason for the deviation although this item ranked 32nd, and corrective action began only after deviations became critical. The findings suggest interacting factors and reactive schedule control; they are explanatory and case-specific, not statistical causality.
- Analisis Manajemen Material terhadap Efisiensi Proyek Konstruksi Perumahan di Kota Batam: - Afriand Hafied; Mulia Pamadi; Amelia Masza
Jurnal Civil Engineering Study Vol. 6 No. 02 (2026): Jurnal Civil Engineering Study
Publisher : Civil Engineering of Universitas Islam Nahdlatul Ulama Jepara

Show Abstract | Download Original | Original Source | Check in Google Scholar

Abstract

Material management is closely linked to cost, schedule, and quality in residential construction, but evidence on which material-management factors are statistically associated with project efficiency in Batam City is limited. This cross-sectional study surveyed 37 practitioners from residential projects in Batam (site engineers, project executors, foremen, head craftsmen, and logistics or purchasing staff), selected through purposive sampling. The 18-item questionnaire was checked with item-total correlations and Cronbach's alpha (0.633–0.753; marginal for the four predictors), and multiple linear regression was estimated in Jamovi. Project efficiency was measured as perceived efficiency, that is, agreement that good material management benefits cost, schedule, quality, and overall efficiency. The model was significant (F(4, 32) = 20.2, p < 0.001; R² = 0.716; adjusted R² = 0.680). Material-use efficiency (b = 0.422, p = 0.005; β = 0.385) and waste and delays (b = 0.267, p = 0.024) were significantly associated with perceived efficiency, whereas the material management system (p = 0.123) and material control (p = 0.118) were not. When one influential observation was excluded, only material-use efficiency remained clearly significant (β = 0.534, p <0.001). Given the small non-random sample, the perceptual outcome, and the conceptually unexpected positive sign for waste and delays, the results describe associations within this sample and do not establish causal effects.
Perbandingan Kebutuhan Rasio Tulangan Kolom dan Balok Bangunan Gedung KAI Boutique Hotel Bandung Akibat Beban Gempa dan Beban Gravitasi Nanang Chosim; Reynaldo Pratama Intan; Shofwan Donny Cahyono
Jurnal Civil Engineering Study Vol. 6 No. 02 (2026): Jurnal Civil Engineering Study
Publisher : Civil Engineering of Universitas Islam Nahdlatul Ulama Jepara

Show Abstract | Download Original | Original Source | Check in Google Scholar

Abstract

This study examines the comparison of reinforcement ratio requirements for beam and column components in the KAI Boutique Hotel Bandung building under the influence of seismic and gravity loads. This evaluation is based on the high seismic risk in Bandung City due to the activity of the Lembang Fault, as well as the mandatory compliance with SNI 1726:2019 and SNI 2847:2019 regulations using the Special Moment Resisting Frame System (SMRFS). Analysis was conducted through 3D structural modeling using finite element software to calculate the theoretical reinforcement area requirements, while maintaining fixed concrete cross-sectional dimensions in accordance with the project working drawings. Parameter comparison was reviewed based on the total weight of reinforcement steel volume (kg) between building floors to provide a quantitative overview from the owner's perspective. The results of the analysis indicate that the total reinforcement volume under seismic loads is 175,710.62 kg, whereas under pure gravity loads it is 114,667.73 kg. Overall, the integration of lateral seismic loads increases the reinforcement steel volume requirement by an average of 53.23% compared to gravity loads alone, with the most significant ratio difference detected on the 5th floor with a volume increase of 70.11% due to the substantial effect of the cumulative lateral base shear force.
Analysis Of The Dominant Causes Of Time Delay In The Rehabilitation Project Of The Medical Outpatient Unit At Ratu Zalecha Regional General Hospital Ahmad Muzakkiy; Ruliana Febrianty; Robiatul Adawiyah
Jurnal Civil Engineering Study Vol. 6 No. 02 (2026): Jurnal Civil Engineering Study
Publisher : Civil Engineering of Universitas Islam Nahdlatul Ulama Jepara

Show Abstract | Download Original | Original Source | Check in Google Scholar

Abstract

The rehabilitation project of the Medical Outpatient Unit at Ratu Zalecha Regional General Hospital (RSUD Ratu Zalecha) in Martapura was identified as experiencing schedule delays by Week 11, particularly in sanitary, mechanical, electrical, public address, and plumbing works. This study aims to evaluate the project's schedule performance using the Earned Value Management (EVM) method and to analyze and rank the dominant delay-causing activities based on the Schedule Performance Index (SPI). A quantitative approach was employed using secondary data, including weekly progress reports, the planned S-curve, and the project cost budget (Rencana Anggaran Biaya/RAB). The analysis revealed that the project's schedule performance fluctuated throughout the construction period, with the highest SPI of 2.47 recorded in Week 2 and the lowest critical SPI of 0.666 in Week 11, accompanied by a Schedule Variance (SV) of −IDR 342,921,182. Following acceleration measures implemented during Weeks 12 and 13, the project was completed on schedule with a final SPI of 1.00 and an actual expenditure of IDR 624,961,000 from the total budget of IDR 1,120,000,000. The ranking analysis of 16 work groups identified 11 groups with SPI values below 1.00 as the dominant contributors to project delays. The sanitary work group was the most critical (SPI = 0.235), followed by flooring (SPI = 0.311), painting (SPI = 0.356), and the public address system (SPI = 0.465). The two large weight groups, namely Sanitary and Flooring, are the most influential factors in the decline in project schedule performance in aggregate.
PERENCANAAN STRUKTUR BAJA GEDUNG SEKOLAH 4 LANTAI DENGAN SISTEM RANGKA BRESING Dimas Rama Putra; Fathur Rohman Robandi
Jurnal Civil Engineering Study Vol. 6 No. 02 (2026): Jurnal Civil Engineering Study
Publisher : Civil Engineering of Universitas Islam Nahdlatul Ulama Jepara

Show Abstract | Download Original | Original Source | Check in Google Scholar

Abstract

The Special Concentrically Braced Frame (SRBKK) system has proven to be most effective in increasing rigidity, eliminating seismic energy, and controlling drift safely and economically. This research focuses on the planning of steel structures for 4-storey buildings using the SRBKK system, with SMK Negeri Kertajati, Majalengka Regency, as the object of the research. Quantitative case study methods and engineering design were applied, referring to SNI 1726:2019 for seismic loads, SNI 1729:2020 for LRFD steel designs, and SNI 7860:2020 for concentric buffer capacity designs, with structural modeling in ETABS Software. Results showed that all structural elements met the LRFD interaction controls, with utilization ratios below 1.0 for columns, beams, and supports. The capacity design approach successfully positions the support as a fuse element, resulting before the beams and columns fail. Beam and support column joints, composite floor decks, and reinforced concrete stairs all meet strength and serviceability requirements. These findings confirm that the SRBKK system produces a safe, stable, and efficient structure that resists seismic shear forces, consistent with Indonesian steel and earthq design standards.
Analysis of Road Damage using the Pavement Condition Index Method on the Untung Surapati–Trikora Section, South Lampung Doni Agus Pratama; Kastamto; Vanita Kesumawati Yacub
Jurnal Civil Engineering Study Vol. 6 No. 02 (2026): Jurnal Civil Engineering Study
Publisher : Civil Engineering of Universitas Islam Nahdlatul Ulama Jepara

Show Abstract | Download Original | Original Source | Check in Google Scholar

Abstract

This study aims to analyze the level of pavement damage on the Untung Surapati–Trikora South Lampung road section using the Pavement Condition Index (PCI) method. This road section plays an important role as a collector route that supports community activities and vehicle movement, but in several segments it experiences surface damage such as potholes and alligator skin cracks. The research method used is quantitative through visual field surveys, damage dimension measurements, and analysis of density values, deduct value, total deduct value, corrected deduct value, and PCI values. Based on the analysis results, the PCI value in each segment shows varying conditions, ranging from perfect, very good, good, moderate, bad, very bad, to failed categories. The results of the study indicate that the PCI method can be used as a basis for quantitative evaluation of road conditions and helps determine priorities for handling road damage more precisely.
Hydrological Analysis and Optimization of the Ngraseh Village Reservoir through Rainwater Harvesting for Clean Water Supply Puji Rahayu
Jurnal Civil Engineering Study Vol. 6 No. 02 (2026): Jurnal Civil Engineering Study
Publisher : Civil Engineering of Universitas Islam Nahdlatul Ulama Jepara

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.34001/ces.v6i02.2210

Abstract

The availability of clean water is a basic community need that must be fulfilled sustainably. Ngraseh Village, Dander District, Bojonegoro Regency, experiences limited clean water supply, particularly during the dry season. Although the village has a reservoir, its utilization is mainly for irrigation, and its potential as a clean water source has not been optimized. This study aims to analyze the reservoir storage capacity, estimate community clean water demand, and formulate an optimization strategy using the Rainwater Harvesting method. A quantitative approach was employed using ten years of rainfall data, population data, and reservoir condition data. The analysis included rainfall consistency testing, regional rainfall, frequency distribution, rainfall intensity, runoff discharge, reservoir storage capacity, clean water demand, and water balance analysis. The results indicate that the effective reservoir capacity of 22,939,851 liters can only supply clean water to approximately 1,062 people (19.95% of the village population) and is only sufficient during the first month of the dry season, while a water deficit occurs in the following five months. Therefore, optimizing the reservoir through Rainwater Harvesting, periodic maintenance, and improved water management is necessary to enhance sustainable clean water availability.
Twenty Year Life Cycle Cost Assessment of the Banjarbaru City Observation Tower Building for Long-Term Asset Management Aliya Ananda; Dr.Ruliana febrianty ST.,MT M.Hum; Dr. (C). Ir. Fathurrahman S.T., M.T., IPM., ASEAN Eng; Ir. Tezar Aulia Rachman, ST., MT; Dr.(c) Muhammad Gunawan Perdana, ST., MT., IPM.
Jurnal Civil Engineering Study Vol. 6 No. 02 (2026): Jurnal Civil Engineering Study
Publisher : Civil Engineering of Universitas Islam Nahdlatul Ulama Jepara

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.34001/ces.v6i02.2216

Abstract

This study analyzes the life cycle cost (LCC) of the Banjarbaru City Observation Tower Building, South Kalimantan, over a 20-year analysis period. The method used was quantitative descriptive analysis based on the Cost Budget Plan (RAB), field observations, and interviews with relevant parties. The cost components analyzed included initial cost, operational cost, routine maintenance cost, and building component replacement cost. The results show that the total LCC for 2025–2045 was Rp2,648,062,764.49, consisting of an initial cost of Rp835,005,747.33 (31.53%), operational costs of Rp694,793,400.00 (26.24%), routine maintenance costs of Rp365,729,904.00 (13.81%), and component replacement costs of Rp752,533,713.16 (28.42%). Accumulated post-construction costs reached Rp1,813,057,017.16 or 68.47% of total LCC. The cost pattern shows spikes in years when components are replaced, particularly in 2040. Therefore, long-term cost planning is required to maintain the optimal function and performance of the observation tower throughout its service life.
Evaluation of the Suitability of the Implementation Schedule in the Construction Project of the Banjarbaru City Fire Department Office Noor Jannah
Jurnal Civil Engineering Study Vol. 6 No. 02 (2026): Jurnal Civil Engineering Study
Publisher : Civil Engineering of Universitas Islam Nahdlatul Ulama Jepara

Show Abstract | Download Original | Original Source | Check in Google Scholar

Abstract

The implementation of construction projects requires effective time control to ensure completion according to the planned schedule. Differences between planned and actual schedules can result in time deviations that affect project completion. This study aims to evaluate the suitability of the implementation schedule of the Banjarbaru City Fire Department Office Development Project by comparing planned and actual schedules, analyzing time deviations for each work item, and determining the project implementation status. A quantitative method was used based on primary and secondary data, including the planned schedule, actual schedule, and project progress. Analysis was conducted by comparing planned and actual work durations, calculating time deviations, and evaluating project progress using the S-Curve. The results showed that weekly time deviations fluctuated between a maximum delay of -2.88% (Week 30) and a maximum acceleration of +4.43% (Week 6). Despite work adjustments caused by a ground elevation discrepancy of 80 cm, effective time control allowed the project to achieve a final cumulative deviation of 0.00%. Overall, the project was completed 100% on schedule within the contractual duration of 210 calendar days. These quantitative findings demonstrate that project schedule control was executed effectively despite mid-project design adjustments.