Claim Missing Document
Check
Articles

Found 39 Documents
Search

CASH FLOW PROYEK DENGAN SUMBER MODAL BANK SYARIAH PADA PEMBANGUNAN DAN REHABILITASI GEDUNG PELAYANAN KESEHATAN PEMERINTAH KABUPATEN GUNUNG KIDUL Vendie Abma; Fitri Nugraheni; Metalindra Metalindra
Construction and Material Journal Vol. 2 No. 2 (2020): Construction and Material Journal Vol. 2 No. 2 Juli 2020
Publisher : Politeknik Negeri Jakarta

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.32722/cmj.v2i2.3088

Abstract

A construction project has several factors that affect the success of a project. One of the factors was an optimal project’s cash flow. Optimizing cash flow of a construction project can be done by making several cash flow plans, and choosing the best one considering appropriate project’s time and cost constraints. The purpose of this study is to obtain an optimal cash flow plan on a construction project using a capital loan from Sharia Bank. This research will be carried out on a specific project which is Construction and Rehabilitation Project of Government Health Service Building, District of Gunungkidul. In this study, the method used to analyze data is to make several project cash flow based on “Earliest Start” scheme by determining the duration for each activity and creating a network diagram using the Precedence Diagram Method (PDM). The final step is analysing the cash flow by calculating negative overdraft for each cash flow plan to determine the amount of capital loan from Sharia Bank and then comparing profits to obtain the optimal one. Analysis and discussion reveal that on the system of given Down Payment, and Project’s Termyn 50%, 75% and 100%, and a loan from Sharia Bank it is found that the optimum cash flow will make profit of 7.49%. Keywords: Cash Flow, Earliest Start (ES), Optimal Profit, Sharia Bank.
Scheduling of Application for Siteplan Authorization Permit (Case of Licensing Process at Investment and Integrated Licensing Services Office in Sleman Regency) Fitri Nugraheni; Vendie Abma; Sigit Yasien
Applied Research on Civil Engineering and Environment (ARCEE) Vol. 1 No. 02 (2020): Urban Building and Infrastructure
Publisher : POLITEKNIK NEGERI JAKARTA

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.32722/arcee.v1i02.2680

Abstract

The permit process must comply with laws and regulations. The permit functions as controlling and supervising tool from the government of activities in certain cases based on the guidelines that must be implemented. The permit also functions as a disciplinarian and regulator in accordance with the law in the administration of government. In the process, several constrains or obstacles often occur in terms of the period of the process as well as technical and non-technical constrains. In this research, an analysis of the scheduling of the site plan permit approval process is based on field data related to the site plan permit approval process with the PERT method. The data used are primary data in the form of interviews and filling in the form of questions and secondary data in the form of a site plan approval process flow. The data that has been collected is then processed and analyzed in several stages. First, calculate the expected time period (te) using interview data and the results of filling in the expected time period (te), so that the expected time period for each activity will be found in accordance with the site plan approval process flow. Second, determine the dependency relationship between activities. In this stage, the relationship between each activity is determined. Third, create a network by changing the existing site authorization process flow into a form of network planning. The results of the schedule using the PERT method are a period of 38 days with alternatives that can be done to reach the time (Tx) of 18 working days in accordance with the Regent Regulations. In addition, the probability of the overall activity being completed is 0.8531 or 85.31%.
Success Factor Management Analysis of Self-Management System For Building Projects Jamal; Albani Musyafa; Faisol AM; Fitri Nugraheni
Jurnal Internasional Teknik, Teknologi dan Ilmu Pengetahuan Alam Vol 4 No 2 (2022): International Journal of Engineering, Technology and Natural Sciences
Publisher : University of Technology Yogyakarta

Show Abstract | Download Original | Original Source | Check in Google Scholar | Full PDF (331.495 KB) | DOI: 10.46923/ijets.v4i2.176

Abstract

The requirement of project management in construction is needed to be able to set priority aspects of implementation from the beginning to the end, to make it succeed and happen as a plan. Self-management is one of the managements to the owner and some scope is to universities that have resources qualified as self-management. Success factor analysis of self-management aims to determine the priority success factors and characteristics of buildings that can be used for self-management. The analytical method used in this research is Analytical Hierarchy Project or AHP. Based on the results of the study, it was obtained 4 respondents who met the criteria for self-management and 10 factors of success, namely quality with 21.33%, leadership / managerial 16.94%, cost 16.89%, 15.68% customer satisfaction, administration 8%, human resources 7.40%, and the other factors such as time with 4.79%, suppliers 3.24%, labor 3.17%, and place characteristics 1.99%. The characteristics of buildings can be done independently, namely; having location or place of development that is owned by the community in a certain area, possessing the development that empowers human resources belonging to mass organizations and community groups, and owning a team of consultants and supervisors to improve planning, scheduling, and increased supervision.
Pemanfaatan FMEA sebagai Instrumen Identifikasi Potensi Bahaya pada Pekerjaan Galian Timbunan (Studi Kasus Proyek Jalan Tol Solo - Yogyakarta - YIA Kulonprogo) Lutfi Andriawan Putra; Fitri Nugraheni
Jurnal TESLINK : Teknik Sipil dan Lingkungan Vol 5 No 1 (2023): March 2023
Publisher : Universitas Nusa Putra

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.52005/teslink.v5i1.226

Abstract

Proyek konstruksi merupakan salah satu aspek yang berkontribusi dalam pembangunan dan pengembangan infrastruktur di Indonesia. Pada penelitian ini, studi kasus dilakukan pada Proyek Pembangunan Jalan Tol Solo - Yogyakarta - YIA Kulonprogo Seksi 1 Paket 1.1 dengan objek pekerjaan galian dan timbunan. Dalam pelaksanaannya, proyek konstruksi memiliki banyak rangkaian pekerjaan dengan melibatkan banyak sumber daya, sehingga banyak risiko yang dapat terjadi. Sebagai upaya pengendalian risiko, Root Cause Analysis menggunakan FMEA dapat mengetahui potensi bahaya berdasarkan kegagalan (failure mode) yang ada sehingga nantinya dapat dilakukan pengendalian. Setiap pekerjaan diuraikan berdasarkan prinsip Work Breakdown Structure, selanjutnya FMEA digunakan untuk mengidentifikasi kegagalan (failure mode) dan menganalisis dampak atau potensi bahaya. Pada pekerjaan galian, angkut material, dan pekerjaan timbunan Proyek Pembangunan Jalan Tol Solo - Yogyakarta - YIA Kulonprogo Seksi 1 Paket 1.1 dengan 9 uraian pekerjaan diketahui memiliki 20 kegagalan (failure mode) dengan 24 potensi bahaya.
PENGARUH JOB SECURITY TERHADAP PERSEPSI KESELAMATAN PADA PEKERJA KONSTRUKSI LAPANGAN DI INDUSTRI MINYAK DAN GAS Bagos, Bagos Armansyah; Fitri Nugraheni
AGREGAT Vol 9 No 1 (2024)
Publisher : Universitas Muhammadiyah Surabaya

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.30651/ag.v9i1.21981

Abstract

Construction projects are activities that are prone to work accidents, so work safety management is needed to prevent work accidents. One of the factors that greatly influences the perception of work safety is the job security. The aim of this research is to identify job security factors and safety perceptions and analyze the influence of the relationship between job security and the perception of safety among field workers in the oil and gas industry, especially in the Riau province work area. The respondents were field workers and numbered 106 people. The research methods used are qualitative and quantitative. There were respondents who stated that the implementation of work safety was very high, but several dimensions such as sustainable salary increases were still not good (34.91%) and respondents stated that understanding and implementation of the perception of safety was very high. The results of the linear regression test show that job security has a positive and significant effect on the perception of safety among field construction workers, where job security contributes to the perception of safety by 21.5%. The more workers do not fulfill job security, the less workers will care about the perception of safety which can lead to not creating a good safety climate and increasing work accidents
ANALISIS PENENTUAN SOLUSI DESAIN PROPERTI BERDASARKAN PENDAPATAN GENERASI MILENIAL DI YOGYAKARTA MENGGUNAKAN N-VIVO Muhammad, Faiz Ihsan; nugraheni, fitri; Musyafa’, Albani
STORAGE: Jurnal Ilmiah Teknik dan Ilmu Komputer Vol. 3 No. 3 (2024): Agustus
Publisher : Yayasan Literasi Sains Indonesia

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.55123/storage.v3i3.3920

Abstract

Generasi milenial berusia 25-40 tahun banyak yang belum memiliki hunian pertama. Di Amerika Serikat, hanya sekitar 37% milenial yang memiliki hunian pribadi, meski minat terhadap properti meningkat dengan pencarian online mencapai 26,4% pada tahun 2022. Namun, mereka menghadapi kesulitan finansial akibat harga properti tinggi dan pendapatan yang tidak sebanding. Di Indonesia, bonus demografi 2020-2035 meningkatkan kebutuhan perumahan terjangkau bagi milenial, yang juga menghadapi lingkungan kerja yang kurang nyaman. Kota Yogyakarta, dengan potensi investasi ekonomi di bidang properti, menghadapi tantangan menyediakan perumahan terjangkau karena kenaikan harga properti yang tidak sebanding dengan pertumbuhan pendapatan. Solusi inovatif dan berkelanjutan diperlukan, selaras dengan Tujuan Pembangunan Berkelanjutan (SDGs) yang menekankan kota inklusif, aman, tangguh, dan berkelanjutan. Penelitian ini menggunakan metode deskriptif kualitatif dengan wawancara semi-terstruktur dan analisis data NVivo, berfokus mengidentifikasi faktor-faktor yang mempengaruhi kesulitan milenial di Yogyakarta dalam memiliki properti, memahami kebutuhan desain properti yang sesuai dengan pendapatan mereka, dan mencari solusi desain properti terjangkau dan relevan. Faktor utama yang mempengaruhi kesulitan tersebut adalah gaya hidup dan prioritas berbeda, harga properti yang terus meningkat, dan kenaikan biaya hidup. Solusi desain properti yang sesuai dengan keterjangkauan generasi milenial meliputi fleksibilitas ruang, desain rumah lebih privat, ruang terbuka hijau, fokus pada fungsi, dan bangunan dengan beberapa massa.
Analisis Perbandingan Biaya dan Waktu pada Penggunaan Duct Spacer dengan Prefabricated dan Hollow Baja Ringan Untuk Pekerjaan Underground Ducting : Studi Kasus Pekerjaan Underground Ducting Untuk Instalasi Airfield Lighting System di Bandara Dhoho Kediri, Jawa Timur Ali Masrodin; Albani Musyafa; Fitri Nugraheni; Taufik Dwi Laksono
Globe: Publikasi Ilmu Teknik, Teknologi Kebumian, Ilmu Perkapalan Vol. 2 No. 3 (2024): Publikasi Ilmu Teknik, Teknologi Kebumian, Ilmu Perkapalan
Publisher : Asosiasi Riset Ilmu Teknik Indonesia

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.61132/globe.v2i3.496

Abstract

The Kediri Airport development project encountered challenges related to underground ducting work. The design of Kediri Airport adheres to international standards, which led to the use of materials not readily available in Indonesia, specifically pipes and duct spacers. Duct spacers are tools used to arrange ducting pipes according to their formation and prevent them from floating during concrete pouring due to buoyancy. The SKEP/114/VI/2002 serves as a reference for underground cable installation, involving direct burial of cables at a depth of 70 cm, covered with a 5 cm layer of sand above the cable surface. These two approaches significantly differ, necessitating problem-solving solutions. To address this issue, research was conducted to find suitable duct spacers in Indonesia. Two alternative materials were considered: PVC and lightweight hollow steel. The study compared costs and time associated with these materials. PVC duct spacers would be imported and be fabricated in Indonesia, while hollow steel duct spacers would be fabricated on-site. The research focused on three aspects: ducting work methods, duct spacer design, and cost-time analysis. Given tight installation spaces and busy schedules, duct spacers needed to be compact, simple, and adaptable to various pipe formations. The design for hollow steel duct spacers aimed for simplicity to reduce on-site construction work. However, care was taken to avoid potential injuries from exposed bolts on the hollow steel frame. The PVC duct spacer design utilized Polytam PF 1000 material, with a nominal shear strength of 399 kg and a nominal moment of 266 kg·cm—sufficient to withstand saturated soil loads up to 162 cm but not vehicular loads. Analyzing procurement time, PVC duct spacers from Indonesian manufacturers were the quickest, taking only 56 days due to no port clearance delays. The fastest completion time for the project was achieved using PVC duct spacers, taking 122 seconds—three times faster than hollow steel duct spacers. While lightweight steel was the most cost-effective option for on-site procurement, combining cost and time analysis favored PVC duct spacers. The minimal cost difference allowed for accelerated production, minimizing the risk of delays
Pengaruh Tingkat Penerapan Rencana Keselamatan Konstruksi Terhadap Risiko Kecelakaan Konstruksi Magfira Lestaluhu; Albani Musyafa'; Edy Purwanto; Fitri Nugraheni
JURNAL ILMIAH NUSANTARA Vol. 1 No. 5 (2024): Jurnal Ilmiah Nusantara
Publisher : CV. KAMPUS AKADEMIK PUBLISING

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.61722/jinu.v1i5.2628

Abstract

This research aims to identify: (1) the level of implementation of the RKK; (2) the risk of construction accidents occurring on construction projects; and (3) the influence of the level of implementation of construction safety risks on construction safety. The research results show that (1) the level of implementation of the RKK in the IBS Building Construction project is stated to be in accordance with the provisions of these statutory regulations and is in accordance with Minister of PUPR Regulation No. 10 of 2021 amounted to 84.8% based on the results of the correlation test. (2) The risk of construction accidents occurring on the IBS Building Construction project includes structural work on reinforced concrete which is analyzed through 10 main provisions including implementing the K3 policy and guaranteeing commitment to implementing the K3 Management System; K3 policy stated in writing; adequate resources are available; an initial description of K3 conditions; Policy monitoring planning, goals and objectives for implementing the K3 management system; existence of planning regarding hazard elimination, risk assessment and control; an understanding of regulations and other requirements relating to K3; the establishment of policy goals and targets in the field of K3; the existence of K3 performance indicators that can be measured; and the existence of initial planning and planning of ongoing activities. (3) There is an influence between the level of implementation of construction safety plans on the risk of construction accidents on construction projects. This is shown by the calculated r value being greater than the table r value (0.848>0.521) and the significance value of 0.002 is less than 0.05 (0.002<0.05).
ANALISIS KELAYAKAN DAN MANAJEMEN RISIKO INVESTASI DALAM PEMBUATAN “QUARY ANDESIT” UNTUK MEMENUHI KEBUTUHAN PROYEK TOLL BOCIMI “BOGOR CIAWI SUKABUMI” Wahid Agung; Fitri Nugraheni; Rossy Armyn M; Albani Musyafa
JOURNAL SAINS STUDENT RESEARCH Vol. 2 No. 5 (2024): Oktober : Jurnal Sains Student Research
Publisher : CV. KAMPUS AKADEMIK PUBLISING

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.61722/jssr.v2i5.2683

Abstract

The Bocimi Toll construction project in the Bogor - Sukabumi area is one of the national strategic projects initiated by the government, according to (Indonesiabaik.id, 2017) this project costs an investment of Rp. 7.77 trillion. With these conditions, the need for aggregate material should be large and this quarry business is attractive to run, but in the process the quarry built by PT. TS experienced operational closures, therefore the author wants to evaluate and conduct an analysis related to the investment made.This analyzes using the formula (Net Present Value), (Internal Rate Of Return) and (Payback Period) and identifies the risks that will occur in a quarry construction so that it can be a decision maker when a construction project or someone will open a quarry. In the research conducted, the total investment value was obtained of Rp. 2,300,000,000 and this business process is planned to run for 5 years, the NPV value was obtained with an Interest value of 10.94% positive Rp.34,848,413,722, the IRR value of 51% is greater than the MARR value determined at 15% and the Payback Period value of 0.7 years this business is considered feasible, then conducting a literacy study and interviews obtained 26 variables, there are 9 variables classified as medium risk and 17 high risk variables, Risk response based on probability and impact values ​​there are owners who have 4 variables with the status of risk avoidance, 3 transfer variables and 1 risk reduction variable. The implementer has 3 risk avoidance variables, 6 risk transfer variables and 1 risk reduction variable. The community has 3 risk avoidance variables.Consumers/project owners have 3 risk avoidance, 1 risk transfer and 1 risk reduction. After the variables from the risk analysis are known, they are re-sorted where the risk factors that can increase the cost burden in investment are then analyzed and the costs incurred are known to be Rp. 1,004,222,260 of that value adds to the capital value, then the NPV value is obtained of Rp. 30,127,078,830 has a positive value, the IRR value is known to be 49% is said to be feasible because it exceeds the MARR value, and after calculating the Payback Period value, it is obtained 1.1 years, analytically it can be said that it is still feasible to run. In this study, risk factors that cannot be assessed are also expected to be a reference for ongoing investment considerations, this is to avoid a loss in the construction of the quarry.
KOMPARASI WAKTU DAN BIAYA KONSTRUKSI MELALUI REDESIGN PANEL HALF DEPTH SLAB DENGAN IMPLEMENTASI BIM PADA PEMBANGUNAN INFRASTRUKTUR AKSES JALAN JETTY KIT BATANG Nur Ashmi Hafian; Fitri Nugraheni; Taufik Dwi Laksono
JOURNAL SAINS STUDENT RESEARCH Vol. 2 No. 5 (2024): Oktober : Jurnal Sains Student Research
Publisher : CV. KAMPUS AKADEMIK PUBLISING

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.61722/jssr.v2i5.2694

Abstract

Kabupaten Batang, yang terletak strategis di sepanjang Jalur Pantura, saat ini sedang melaksanakan pembangunan infrastruktur untuk meningkatkan aksesibilitas transportasi barang dan bahan baku antara pelabuhan dan kawasan industri. Salah satu proyek penting yang sedang berlangsung adalah Pembangunan Akses Jalan Jetty Kawasan Industri Terpadu (KIT) Batang, yang termasuk dalam Proyek Strategis Nasional. Salah satu elemen kunci dalam proyek ini adalah pekerjaan half slab, yang menggunakan sistem pelat beton pracetak dan pengecoran konvensional. Penelitian ini bertujuan untuk mengoptimalkan waktu dan biaya pelaksanaan pekerjaan half slab dengan melakukan redesign menggunakan metode Building Information Modeling (BIM) 3D, 4D, dan 5D. BIM 3D digunakan untuk visualisasi desain, BIM 4D untuk simulasi jadwal, dan BIM 5D untuk perhitungan kuantitas material serta biaya. Dalam studi ini, terdapat empat tipe half slab yang digunakan, dan melalui analisis teknis, ditemukan bahwa redesign half slab dapat mempercepat waktu pemasangan di beberapa area proyek. Di area EJ5 – EJ4, waktu pengerjaan dapat dipersingkat 9 hari, sementara di area EJ4 – EJ3 dan EJ3 – EJ2, dapat dipersingkat masing-masing 1 hari. Dari segi biaya, hasil analisis menunjukkan bahwa meskipun biaya pengadaan half slab redesign lebih tinggi sebesar Rp. 27.350.749 dibandingkan dengan half slab eksisting, desain ulang ini menghilangkan kebutuhan biaya bekisting sebesar Rp. 23.969.984 dan memangkas biaya beton lantai jembatan sebesar Rp. 513.207.303. Total biaya pemasangan half slab redesign sebesar Rp. 4.221.200.440. Penelitian ini diharapkan dapat memberikan kontribusi signifikan dalam mengoptimalkan waktu dan biaya pada proyek infrastruktur, serta memberikan manfaat jangka panjang bagi efisiensi transportasi di Kabupaten Batang.
Co-Authors Abma, Vendie Achmad Djunaedi Adam Rahmad Yani Adwitya Bhaskara Adwitya Bhaskara Ahmad, Chairul Albani Musyafa Albani Musyafa Albani Musyafa' Albani Musyafa, Albani Ali Masrodin Anisah, Fitri Arasya Maharika, Raka Affa Armansyah, Bagos Bagos Armansyah Bagos, Bagos Armansyah Benjamin Razaan Ditama Diah Ayu Apriliasari DYAH ASTRIANI Eliza Kristiana Dewi Fadillah, Titania Nur Faisol Faisol A.M Faisol AM Fifin Rafina Yunitasari Firdamarsha Benadikta Firmansyah, Mochamad Hakim Muganga Hanafi, N. Faried HARI PURNOMO Hari Purnomo Ida Ayu Putu Sri Widnyani Ilya Fadjar Maharika Irwan Nuryana Kurniawan Istina Putri Rahayu Jaka Nugraha Jamal Nur Alim Koko Heru Satmoko Lalu Makrup Lutfi Andriawan Putra M. Agung Wibowo Magfira Lestaluhu Makrup, Lalu Medilla Kusriyanto, Medilla Metalindra Metalindra Metalindra, Metalindra Muhammad David Gilang Putra Ramadhan Muhammad Nadhif Al Ghani Muhammad, Faiz Ihsan Muntafi, Yunalia Musyafa', Albani Musyafa’, Albani N. Faried Hanafi Nahdliyatul Faiziyah Nur Ashmi Hafian Nurmianto, Awaluddin Putri Dwi Anugrahani Risdiyono Risdiyono Rishma Nurwijaya Ningrum Rizkianto, Handi Rossy Armyn Machfudiyanto Rudatin, Ari Salsabilla Septianingrum Saputra, Elvis Sarwidi Sely Novita Sari Septianugraha, Agastya Fauzan Setya Winarno Sigit Yasien Sri Amini Yuni Astuti Sri Kusumadewi Sujarwo, Ari Sulistio, Adi Susetyo, Gayuh Adi Suswardana, Suswardana Taufik Dwi Laksono, Taufik Dwi Taufiq Arya Putra N Tri Nugroho Sulistyantoro Wahid Agung Widodo . Widodo Pawirodikromo, Widodo Yasien, Sigit