ANALISIS FAKTOR-FAKTOR PENYEBAB TERJADINYA KETERLAMBATAN PENYELESAIAN PEKERJAAN FISIK PADA PROYEK PNPM MANDIRI DI KOTA AMBON Leuhery, Lenora
Jurnal Teknik Sipil Vol 3, No 1 (2014): JURNAL TEKNIK SIPIL
Publisher : Jurnal Teknik Sipil

Show Abstract | Download Original | Original Source | Check in Google Scholar | Full PDF (197.103 KB)

Abstract

National Program for Community Empowerment (PNPM Mandiri) that have been implemented in the city of Ambon since 2007, is believed to have contributed greatly to the city government in reducing poverty and improving social welfare. But one of the problems that a lot happening in the field is the delay in the completion of physical work on PNPM Urban city of Ambon, which is not optimal impact on the work and impeding the implementation of PNPM Mandiri, especially in terms of physical work completion PNPM Mandiri. This study aims to analyze the factors that cause delays in the completion of the physical work on the project in the city of Ambon PNPM Mandiri. The analysis was performed on the questionnaire respondents were represented from all parties involved in the project, namely PNPM employer / government (the owner), executing the work / community directly (KSM) and the executive supervisor jobs / employment coordinator (BKM). Performed with SPSS data processing and concluded that the factors that influence the occurrence of delays in completion of the work is the physical aspect Inspection Systems, Control and Evaluation of Work (X5), reporting on the indicators work slow and incomplete, with the percentage of agreement value of the intensity scale and the scale of determine respectively are: intensity scale (BKM 93%; KSM 97%; owners 95%) and determine the scale (BKM 96%; KSM 98%, owner 96%).
ANALISIS FAKTOR-FAKTOR PENYEBAB TERJADINYA KETERLAMBATAN PENYELESAIAN PEKERJAAN FISIK PADA PROYEK PNPM MANDIRI DI KOTA AMBON Leuhery, Lenora
Jurnal Teknik Sipil Vol 3, No 1 (2014): JURNAL TEKNIK SIPIL
Publisher : Jurnal Teknik Sipil

Show Abstract | Download Original | Original Source | Check in Google Scholar | Full PDF (197.103 KB)

Abstract

National Program for Community Empowerment (PNPM Mandiri) that have been implemented in the city of Ambon since 2007, is believed to have contributed greatly to the city government in reducing poverty and improving social welfare. But one of the problems that a lot happening in the field is the delay in the completion of physical work on PNPM Urban city of Ambon, which is not optimal impact on the work and impeding the implementation of PNPM Mandiri, especially in terms of physical work completion PNPM Mandiri. This study aims to analyze the factors that cause delays in the completion of the physical work on the project in the city of Ambon PNPM Mandiri. The analysis was performed on the questionnaire respondents were represented from all parties involved in the project, namely PNPM employer / government (the owner), executing the work / community directly (KSM) and the executive supervisor jobs / employment coordinator (BKM). Performed with SPSS data processing and concluded that the factors that influence the occurrence of delays in completion of the work is the physical aspect Inspection Systems, Control and Evaluation of Work (X5), reporting on the indicators work slow and incomplete, with the percentage of agreement value of the intensity scale and the scale of determine respectively are: intensity scale (BKM 93%; KSM 97%; owners 95%) and determine the scale (BKM 96%; KSM 98%, owner 96%).
PERAN POLITEKNIK NEGERI AMBON DALAM MENUNJANG PENGEMBANGAN NEGERI OMA MENUJU DESA WISATA Latuconsina, Rina; Leuhery, Lenora; Saptenno, Sammy; Manuputty, Evandro; Pattiasina, Nanse Henny; Jamlaay, Marselin
Conference on Innovation and Application of Science and Technology (CIASTECH) CIASTECH 2021 "Kesiapan Indonesia Dalam Menghadapi Krisis Energi Global"
Publisher : Universitas Widyagama Malang

Show Abstract | Download Original | Original Source | Check in Google Scholar

Abstract

Provinsi Maluku merupakan salah satu provinsi yang terdiri dari gugusan pulau kecil, Negeri Oma merupakan salah satu negeri adat yang berada di Pulau Haruku Kabupaten Maluku Tengah. Negeri Oma sendiri memiliki potensi alam yang melimpah baik di bidang kelautan ataupun perkebunan, selain itu Negeri Oma juga menyimpan pesona alam yang indah dan beberapa lokasi wisata yang alami diantaranya : permandian kolam Air Asol, Batu Kapal serta sumber air panas. Dari potensi alam yang ada dan ekonomi kreatif belum tersentuh secara optimal baik dari segi pengolahan, promosi maupun pemasaran. Pusat Penelitian dan Pengabdian Masyarakat Politeknik Negeri Ambon menjadikan Negeri Oma sebagai Desa Binaan pada tahun 2021. P3M dalam hal ini yang menjembatani para peneliti dan pengabdi untuk berkontribusi dalam pembangunan Negeri Oma. Tujuannya adalah untuk meningkatkan perekonomin masyarakat dan menciptakan kawasan Negeri Oma sebagai desa Wisata yang dinteggrasikan dan disinergikan dengan berbagai program. Kegiatan yang dilakukan adalah memperkenalkan Teknologi Tepat Guna dalam berbagai bidang diantaranya pembuatan Webbsite, perancangan alat pengering otomatis, pembuatan booth untuk tempat jualan, pembuatan tempat cuci tangan semi otomatis, pengembangan SDM melalui berbagai macam pelatihan kepada masyarakat yang berumur produktif serta pengembangan sarana dan prasarana pendukung lokasi wisata. Hasil Kegiatan dilaksanakan di Negeri Oma pada tanggal 11 September 2021 pada Kantor Desa Negeri Oma serta penyerahan alat-alat prasarana pendukung lokasi wisata langsung pada lokasi masing-masing. Dengan adanya pengembangan Pariwisata di negeri Oma, maka akan berdampak terhadap pendapatan masyarakat negeri Oma.
EVALUASI FAKTOR-FAKTOR SISTEM MANAJEMEN KESELAMATAN DAN KESEHATAN KERJA (SMK3) PADA PROYEK REHAB RUMDIS 2 LANTAI HUBDAM XVI/PATTIMURA-AMBON Lekatompessy, Marchel; Leuhery, Lenora; Istia, Penina
Journal Agregate Vol. 3 No. 1 (2024): Maret
Publisher : Jurusan Teknik Sipil

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.31959/ja.v3i1.1819

Abstract

The Hubdam XVI/Pattimura-Ambon 2-Storey Rumdis Rehab Project is one of the construction projects that has a high risk of work accidents because workers who do not comply with regulations to wear PPE are also because they are close to other official housing and close to road access commonly used by the surrounding community. This study aims to determine what factors affect SMK3 and the implementation and implementation of the SMK3 program. The method used in this study used a survey method through a questionnaire that was distributed to 35 respondents and then processed using SPSS software and presented in the form of a table. The results of the study stated that four variables that affect the SMK3 Implementation System, namely knowledge variables, work environment variables, K3 commitment variables, and compliance variables are statutory because the significance value of the four variables is < 0.05 also the results of the calculation analysis > table and the application of the Safety and Health Management System (SMK3) in the Rumdis Hubdam XVI / Pattimura-Ambon Rehab project, have been implemented very well.
OPTIMASI WAKTU DAN BIAYA DENGAN METODE TIME COST TRADE OFF PADA PROYEK PEMBANGUNAN RUANG KELAS BARU MTSN 6 MALTENG Launuru, Julfirawati; Leuhery, Lenora; Marantika, Meyke
Journal Agregate Vol. 3 No. 1 (2024): Maret
Publisher : Jurusan Teknik Sipil

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.31959/ja.v3i1.1907

Abstract

The construction of the new classroom construction project at MTSN 6 Malteng was intended to be the object of this study because it was based on the background that occurred in the project, namely delays. Based on secondary data obtained from the project, the Budget Plan (RAB) and Time Schedule are used as project’s duration and normal costs of the project. Then the time cost trade-off method is applied which aims to be able to reduce the duration and find out the total cost needed so that the project can reach the planned time target so as not to experience delays. After accelerating with the addition of 3 hours, it could save time by 8,33% where the project cost is reduced by around 0,21%. Meanwhile, the addition of 2 hours could save time by 6,67% where the project cost is also reduced by around 0,17%. While the optimal duration and optimal costs were known in the alternative addition of 3 hours of overtime obtained 110 working days for IDR 2,992,374,365.55. Meanwhile, in addition to 2 hours of overtime, 112 working days were obtained for IDR 2,993,479,584.03.
ANALISIS PERCEPATAN PADA PROYEK PEMBANGUNAN RUANG KELAS BARU MADRASAH IBTIDAIYAH NEGERI 5 MALUKU TENGAH DENGAN MENGGUNAKAN METODE CRASHING PROGRAM Salong, Ahmat ikbal; Leuhery, Lenora; Abdin, Maslan
Journal Agregate Vol. 3 No. 1 (2024): Maret
Publisher : Jurusan Teknik Sipil

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.31959/ja.v3i1.2123

Abstract

There are several aspects of project implementation management, such as implementation plans, schedules, and others. The emergence of problems in the implementation management aspect hurts project implementation. Then the alternatives that are usually used to support the acceleration of activities is to increase working hours so that it has an impact on the total project cost. The Madrasah Ibtidaiyah Negeri 5 Maluku Tengah New Classroom Construction Project was chosen for the research study because it experienced delays. The CPM (critical path method) is used to analyze the project implementation time to obtain critical work that has no leeway days to be accelerated. The optimal time and cost are obtained from the Crash Program using the Crashing method by adding working hours to each accelerated critical work. From the acceleration, the cost slope value is obtained. the purpose of this research is to determine what work is critical in the project and also get the results of analyzing the calculation of time and cost of work after being accelerated. The result showed that the total normal project cost budget of Rp 2,891,000,000 with an implementation duration of 120 days, in conditions after crashing with an alternative of adding working hours for two hours obtained a cost of Rp 2,943,185,364 greater than the total project cost budget under normal conditions and a reduction in duration to 110 days or faster than the normal duration. The total cost slope value obtained was Rp 64,231,234.
Tinjauan Rencana Anggaran Biaya Proyek Rehabilitasi Kantor Gubernur Maluku Menggunakan AHSP Permen PUPR No 1 Tahun 2022 Toisutta, Siti Aisa; Leuhery, Lenora; Abdin, Maslan
Jurnal Penelitian Multidisiplin Bangsa Vol. 1 No. 4 (2024): September
Publisher : Amirul Bangun Bangsa Publishing

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.59837/jpnmb.v1i4.60

Abstract

Rencana anggaran biaya adalah perencanaan anggaran biaya suatu proyek yang disusun agar dapat mengetahui seberapa besar kebutuhan biaya suatu proyek. Untuk itu Sebuah proyek konstruksi memerlukan perkiraan biaya dalam penyelenggaraan suatu proyek yang disusun dengan baik dan teliti berdasarkan metode analisa yang dipakai. Metode SNI merupakan pembaharuan dari analisa BOW (Burgeslijke Openbare Werken) 1921 yang dikeluarkan oleh Pusat Penelitian dan Pengembangan Permukiman. Metode AHSP (Analisa Harga Satuan Pekerjaan) adalah pedoman analisa yang dikeluarkan oleh Kementrian Pekerjaan Umum dan Perumahan Rakyat (PUPR). Hasil estimasi anggaran biaya menggunakan metode AHSP Permen PUPR 2022 sebesar Rp.6.389,724,000,00 dan estimasi anggaran biaya menggunakan metode SNI 2008 sebesar Rp.5.971,082,000,00 dengan selisih dari metode AHSP permen pupr 2022 dan SNI 2008 sebesar Rp.418,642,000,00 dan presentasi selisih 6,55%.
Investment Analysis Of The Masela Block Project. Will The Masela Block Become A Natural Resource Paradox? (A Pestle Analysis) Sandanafu, Sally Paulina; Leuhery, Lenora; Wattimena, Sefnath J; Patty, Meidylisa
Jurnal Ilmu Sosial Mamangan Vol 12, No 2 (2023): Special Issue
Publisher : LPPM Universitas PGRI Sumatera Barat

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.22202/mamangan.v12i3.8108

Abstract

The unsustainable investment in the Masela block due to the recent pandemic has delayed several steps by the Maluku provincial government and local communities in realizing the investment capital participation (PI). This study aims to determine and analyze the factors that hinder the operation and investment in the Masela block. The analysis technique used in this study is the PESTLE analysis which is reinforced by secondary data and survey results and interviews with PT MEA, namely the industry appointed by the local government (BUMD) in implementing the investment capital participation in the Masela block and informants from the Latdalam and Lermatang village governments who know and are directly affected by the development of the Masela Block project. The results of this study indicate that the priority concentration of the Lermatang and Latdalam village communities is on the social and environmental aspects where there will be many social changes in the community's way of life so that this aspect must be truly considered because these two villages highly uphold customary and cultural values and depend on natural resources.
Tinjauan Kinerja Biaya dan Waktu Dengan Metode Earned Value pada Proyek Pembangunan Fasilitas Pelabuhan Laut Saumlaki Laisina, Freetz Gerald; Leuhery, Lenora; Titaley, Henriette Dorothy
Jurnal Penelitian Multidisiplin Bangsa Vol. 1 No. 8 (2025): Januari
Publisher : Amirul Bangun Bangsa Publishing

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.59837/jpnmb.v1i8.312

Abstract

Proyek konstruksi adalah upaya terencana dan terorganisir untuk membangun, memperbaiki, serta mengembangkan suatu struktur fisik. Dalam suatu proyek konstruksi, perencanaan dan pengendalian biaya dan waktu merupakan hal pokok dalam mewujudkan pencapaian target dengan tujuan mengurangi resiko penyimpangan didalam sebuah proyek. Metode nilai hasil (earned value method) merupakan metode yang dapat digunakan untuk mengendalikan biaya dan waktu dengan tiga indikator utama diantaranya Actual Cost of Work Performance (ACWP), Budgeted Cost for Work Schedule (BCWS), dan Budgeted Cost for Work Performance (BCWP). Tujuan penelitian ini adalah mengetahui kinerja biaya dan waktu yang dibutuhkan agar bisa mengejar keterlambatan pekerjaan di pelabuhan laut yang terletak di Kelurahan Saumlaki, Kecamatan Tanimbar Selatan, Kabupaten Kepulauan Tanimbar, Provinsi Maluku. Hasil penelitian menunjukan bahwa kinerja biaya yang ditandai dengan CPI pada minggu ke-69 bernilai <1 serta didukung dengan CV yang bernilai negatif menunjukan bahwa biaya aktual yang dikeluarkan lebih besar dari yang direncanakan, dan kinerja waktu yang ditandai dengan SPI pada minggu ke-69 bernilai <1 serta didukung dengan SV yang bernilai negatif menunjukan bahwa durasi pengerjaan proyek lebih lambat dari yang direncanakan. Maka diperlukan pengendalian biaya dan waktu yang lebih efektif agar memperkecil kemungkinan terjadinya penyimpangan biaya dan waktu seiring berjalannya proyek.
Analisis Kemampuan, Pengalaman dan Motivasi Melalui Produktivitas Tenaga Kerja pada Proyek Pembangunan Gedung Kantor Bahasa Provinsi Maluku Wattimena, Angel C; Leuhery, Lenora; Langi, Jeffrey Payung
JURNAL ILMIAH NUSANTARA Vol. 2 No. 1 (2025): Jurnal Ilmiah Nusantara
Publisher : CV. KAMPUS AKADEMIK PUBLISING

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.61722/jinu.v2i1.4110

Abstract

The success rate of a construction project depends on labor productivity. Construction project labor is required to work effectively, efficiently and is expected to be in accordance with the plans that have been made. However, in reality found in the field, it is still less effective at work. This study aims to determine the effect of work ability, work experience and work motivation on labor productivity in the Construction of Maluku Province Language Building. In the field data collection is done by direct observation, while for the calculation of work volume using excel calculations. This research was also conducted by distributing questionnaires to the workforce to find out the factors that affect labor productivity. Questionnaire data was processed using SPSS version 25. From the results of the study, it was found that the volume of light brick installation work on labor productivity. Then obtained a total overall average of 15.9375 m2 / day. From the results of SPSS analysis obtained factors affecting labor productivity in the installation of lightweight bricks in the Construction of Language Building Maluku Province shows that the coefficient of determination (R2) value of 0.911. This means that 91.1% of the dependent variable in the form of work productivity in the construction of the language office building can be influenced by the variables of work ability, work experience and work motivation while the remaining 8.9% is influenced by other variables not included in this study.