ANALYSIS OF THE APPLICATION OF TIME MANAGEMENT USING THE CPM METHOD IN THE REHABILITATION WORK PROJECT OF THE DISDIKBUDPORA HALL BUILDING Shinta Ayu Ramadhany; Putri Anggi Permata Suwandi; Diah Rahmawati; Anggits Burhanudin; Yesenia Laura; Mohammad Mukhdif Al-Afghoni
DEARSIP : Journal of Architecture and Civil Vol. 6 No. 01 (2026): Desember 2025 - Mei 2026
Publisher : Faculty of Engineering, Universitas Islam Darul Ulum Lamongan

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.52166/dearsip.v6i01.13009

Abstract

Time management is one of the important factors in the successful implementation of construction projects because it is directly related to time efficiency, cost, and quality of work. In the Semarang Regency Disdikbudpora Hall Rehabilitation Project, the preparation of the implementation schedule is still not optimal due to the determination of the duration of work that has not considered the complexity and relationship between activities properly. This study aims to analyze the application of time management using the Critical Path Method (CPM) method to obtain a more effective project implementation duration and identify activities that are on the critical path. The research method used is a quantitative descriptive method by utilizing primary data in the form of field observations and secondary data in the form of time schedules, weekly reports, work drawings, and Cost Budget Plans (RAB). The analysis was carried out using the CPM method through forward pass, backward pass, and total float to determine the critical trajectory of the project. Data processing is done using Microsoft Excel and network visualization is created using AutoCAD. The results showed that the normal duration of project completion based on the CPM method is 54 working days, 3 days faster than the existing implementation schedule of 57 calendar days. Activities included in the critical path include preparatory work, certain earthworks and foundations, concrete work, wall pairing, floor and wall coverings, and painting work. Activities on critical lines have a total float value of zero, so delays in the work will affect the overall duration of project completion. Based on the results of the analysis, the application of the Critical Path Method (CPM) has proven to be effective in optimizing project scheduling because it is able to identify critical activities and accelerate project completion time. This method can be used as a reference in controlling the implementation time of construction projects to be more efficient and planned.
ACCESSIBILITY OF TRANSPORTATION FACILITIES FOR DISABILITIES (CASE STUDY OF TRANS SEMARANG) Suwandi, Putri Anggi Permata; Saputro, Bayu Singgih; Hermanto, Wilarso; Kristiawan, Agung
International Journal of Sustainable Building, Infrastructure and Environment (IJOSBIE) Vol 1, No 2 (2020)
Publisher : Science and Technology Research Centre, Universitas PGRI Semarang

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.26877/ijosbie.v1i2.6998

Abstract

Accessibility related to public transport is a means of advancing the economic welfare of the community, creating and increasing economic degrees, as well as a precursor sector of other sectors. Therefore, people with disabilities are also entitled to the same service to the public transportation as an effort to realize similarities, the equality of citizens and the enhancement of the role of disability. This research aims to analyse disability access and the role of the transportation service of Semarang and PT. Trans Semarang on Bus Rapid Transit in Semarang City. This research uses a type of qualitative approach that is implemented through interviews, observations and documentation. The conclusion of this research shows that from the regulatory aspects, the government of Semarang should be appreciated because the government of Semarang has tried to fulfill the rights of the disabled. But from the implementation aspect, there needs to be an improvement because the accessibility of disabled people running optimally can be seen through the condition of public facilities in the city of Semarang. Public facilities in the city of Semarang do not completely ignore the reference accessibility means there are public facilities that have been good enough but many more are not optimal.
REWORK COST ANALYSIS ON COLUMN WORK IMPLEMENTATION METHODS "CASE STUDY: CONSTRUCTION PROJECT OF HOSPITAL ROEMANI MUHAMMADIYAH PARKING BUILDING SEMARANG" Suep, Muhamad; Husodo, Ibnu Toto; Suwandi, Putri Anggi Permata; Kristiawan, Agung
International Journal of Sustainable Building, Infrastructure and Environment (IJOSBIE) Vol 3, No 1 (2022)
Publisher : Science and Technology Research Centre, Universitas PGRI Semarang

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.26877/ijosbie.v3i1.12980

Abstract

The word of construction is no stranger to rework. In the course of the implementation of construction, rework work may occur which can cause delays in the work process and swelling of the project cost budget. This can be influenced by several problems or factors that are often encountered during development work such as human resourse factors, documentation and disign, managerial with this can be from sevaral that have been mentioned that must be considered when planning construction development. In this study using descriptive research that directly takes data in the field by means of interviews, documentation, observation in order to be able to answer the research objectives properly and correctly according to the data obtained from the aforementioned data collection process. So that it can be seen the most frequently encountered rework jobs in the field. Based on the results of the study, it was shown that the dominant factor causing rework was managerial factor. The type of work that often experiences rework work is the finishing work of the second floor column casting. With the details of the causes of rework, the results obtained are design and documentation 22.5%, managerial 40.4%, and human resources 37.2%. The process of rework in the construction of the R S Roemani Semarang building can be concluded that there are several problems or identification of rework, namely porous columns, column slopes and column centring.
Comparison of Cut and Fill Volume Calculation Using Building Information Modeling BIM and Conventional Methods Cut and Fill Project of KIT Batang Block A Lots 9 10 11 12 and 12A RAMADHONY, FERDY YOLA; WIDYANINGSIH, MAY KRISTINA; IKHWANUDIN, IKHWANUDIN; SUWANDI, PUTRI ANGGI PERMATA
International Journal of Sustainable Building, Infrastructure and Environment (IJOSBIE) Vol 7, No 1 (2026)
Publisher : Science and Technology Research Centre, Universitas PGRI Semarang

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.26877/ijosbie.v7i1.25456

Abstract

Abstract. Land preparation is a crucial initial stage in construction work to adjust the site’s topography to the planned elevation. One of the main activities in this phase is earthwork, specifically the cut and fill process. This study compares the conventional method and the Building Information Modeling (BIM) method in calculating earthwork volumes for the Cut Fill Project at KIT Batang, Block A Lots 9, 10, 11, 12, and 12A. The conventional method uses AutoCAD, Civil 3D, and Microsoft Excel with the Average End Area method, while the BIM method applies an integrated 3D digital model in Civil 3D through the Compute Materials and Volumes Dashboard commands. The results show that the conventional method produced excavation (cut) and embankment (fill) volumes of 5,715.65 m³ and 111,196.22 m³, respectively. Meanwhile, the BIM method generated 5,894.19 m³ (cut) and 112,093.61 m³ (fill) using Compute Materials, and 5,665.10 m³ (cut) and 112,038.57 m³ (fill) using Volumes Dashboard. The deviation of BIM results compared to the conventional method was less than 5%, with +3.12% and +0.81% for Compute Materials, and –0.88% and +0.76% for Volumes Dashboard. These small deviations indicate that the BIM method provides higher accuracy and efficiency, as it automatically calculates volumes based on an integrated digital surface model, reducing potential human error.Keywords: Cut and Fill, Earthwork, Conventional Method, Building Information Modeling (BIM), Civil 3D
Implementation of Reinforced Concrete Floor Beams and Plates in a 5-Storey Hospital Building Construction Project Rosiyani, Tissa Rahayu; Kristiawan, Agung; Suwandi, Putri Anggi Permata
International Journal of Sustainable Building, Infrastructure and Environment (IJOSBIE) Vol 6, No 2 (2025)
Publisher : Science and Technology Research Centre, Universitas PGRI Semarang

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.26877/ijosbie.v6i2.22425

Abstract

Hospitals are health care institutions that provide a full range of individual health services and provide inpatient, outpatient and emergency services. The comprehensive health services referred to in this case include promotive, preventive, curative and rehabilitative.[1] The construction of the new building at PKU Muhammadiyah Blora Hospital will be the center of the physiotherapy clinic, pharmaceutical satellite, commercial area, drop off, ICU, inpatient, office. The existence of the new building is a step to improve the quality of health services for patients. The new hospital building is located to the east of the main building in the PKU Muhammadiyah Blora Hospital complex. The work observed is the work of beams and reinforced concrete floor slabs. This work has several steps of workmanship. The work on the beams and floor slabs must complete the reinforcement and formwork simultaneously first, then the casting can be done.
Cost and Time Control Analysis in the Neucentrix Building Renovation Project Using the Earned Value Method Pinuji, Putri; Suwandi, Putri Anggi Permata; Rizani, Mohammad Debby
International Journal of Sustainable Building, Infrastructure and Environment (IJOSBIE) Vol 6, No 1 (2025)
Publisher : Science and Technology Research Centre, Universitas PGRI Semarang

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.26877/ijosbie.v6i1.20122

Abstract

In the Neucentrix renovation project, an addendum caused an extension. This study analyzes the weekly performance of the 2023 Neucentrix Pugeran Yogyakarta Project in terms of cost and time using the Earned Value method. The data analyzed using the Earned Value method using ACWP, BCWS, and BCWP indicators. From these indicators, CV, SV, CPI, SPI, EAS and EAC values are obtained. The analysis reveals cost savings from the first to the seventeenth week, with initial acceleration in the first four weeks followed by delays from weeks five to seventeen. The project is expected to take 19 weeks to complete, with a final estimated cost of IDR 2,294,673,540.
Analysis of Time Management Implementation Using the Crashing Method on the Rehabilitation Project of the Disdikbudpora Hall Building in Semarang Regency Ramadhany, Shinta Ayu; Suwandi, Putri Anggi Permata; Husodo, Ibnu Toto
International Journal of Sustainable Building, Infrastructure and Environment (IJOSBIE) Vol 7, No 1 (2026)
Publisher : Science and Technology Research Centre, Universitas PGRI Semarang

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.26877/ijosbie.v7i1.24267

Abstract

This study analyzes the application of time management using the crashing method on the Rehabilitation Project of the Disdikbudpora’s Hall Building in Semarang Regency. This project has an implementation period of 57 calendar days. To assess whether this duration could be optimized, the crashing method was applied to critical path activities by adding overtime work hours (1 to 3 hours/day). The research utilized a qualitative method with a quantitative approach, using primary data from field observations and secondary data such as schedules and weekly reports. Results showed that by adding 1, 2, and 3 hours of overtime, the project duration could be reduced to 54, 49, and 48 days, respectively. Cost analysis revealed that adding 2 hours of overtime provided the most optimal balance between shortened duration and additional labor costs, totaling IDR 58,556,562.50. This option offered a 5 day acceleration with a relatively small cost difference compared to 1 hour overtime. Therefore, adding 2 hours of overtime is considered the most efficient strategy for project acceleration.
ANALYSIS OF VEHICLE OPERATING COSTS USING METHOD (PACIFIC CONSULTANT INTERNATIONAL) PCI ON SEMARANG TOLL ROAD SECTION A AND NON-TOLL ROAD (KRAPYAK-JATINGALEH) Mahendra, Rega; Asih, Veni; Suwandi, Putri Anggi Permata; Yudaningrum, Farida
International Journal of Sustainable Building, Infrastructure and Environment (IJOSBIE) Vol 3, No 1 (2022)
Publisher : Science and Technology Research Centre, Universitas PGRI Semarang

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.26877/ijosbie.v3i1.11710

Abstract

Abstract. The Semarang toll road is the only toll road network in the city of Semarang at this time. The construction of toll roads aims to reduce congestion and improve travel time efficiency. In addition, the benefit of toll roads is that toll road users will benefit in the form of vehicle operational cost savings (BOK) and time compared to if they pass through non-toll roads. For alternative routes or non-toll roads, conventional roads can be chosen by motorists without passing through toll roads. This study aims to calculate vehicle operating costs (BOK), vehicle operating cost benefits (BKBOK) using the Pacific Consultant International (PCI) method as a limit to determine toll rates and analyze the comparison of Vehicle Operating Costs (BOK) on toll and non-toll roads. . Data collection techniques in this study used primary and secondary data collection techniques. The analysis was carried out using an interactive analysis model. The calculation of vehicle operating costs using the PCI method is taken from the lowest vehicle operating costs from various speed variations. For toll roads, the lowest vehicle operating costs occur at a speed of 60 km/hour with a total BOK of Rp. 6,803.54. Meanwhile, for non-toll roads, the lowest vehicle operating costs occur at a speed of 60 km/hour with a total BOK of Rp. 10,641.27. According to the analysis we have obtained, toll roads are cheaper than non-toll roads. For road users in the city of Semarang, it is recommended to use the Semarang section A toll road compared to non-toll roads, because vehicle operating costs are more efficient and have a much faster travel time.Keyword : BOK,BKBOK, speed, PCI, Toll Road
Parking Analysis at Banyumanik 2 General Hospital, Semarang City Khoir, Muhamad Walidul; Setiawan, Muhammad Agus; Suwandi, Putri Anggi Permata; Yudaningrum, Farida
International Journal of Sustainable Building, Infrastructure and Environment (IJOSBIE) Vol 6, No 2 (2025)
Publisher : Science and Technology Research Centre, Universitas PGRI Semarang

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.26877/ijosbie.v6i2.21020

Abstract

Vehicle movement will be hampered if the available parking space is insufficient to meet the needs of the facility itselfThe method taken in making this final assignment is to use quantitative methods.the total parking revenue in the Banyumanik 2 Hospital area, Semarang City at the time of the research, based on predetermined parking planning, resulted in an estimated parking levy of Rp. 888,000.00,- per 2 hours.This planning results in a total parking pattern of 46 cars and 153 motorcycles. total income during the research was IDR 668,000.00 per 2 hours. Based on parking planning during research with 46 car lots and 153 motorbikes, there is a total planned levy of IDR 888,000.00 per 2 hours.
COST EFFICIENCY ANALYSIS AND RISK MANAGEMENT OF THE SELFMANAGED BATCHING PLANT METHOD MUSI TOLL KAYU AGUNGPALEMBANGBETUNG BRIDGE PROJECT Supriyono, Joko; Kristiawan, Agung; Ramadhani, Vicha Silviana; Suwandi, Putri Anggi Permata
International Journal of Sustainable Building, Infrastructure and Environment (IJOSBIE) Vol 7, No 1 (2026)
Publisher : Science and Technology Research Centre, Universitas PGRI Semarang

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.26877/ijosbie.v7i1.27063

Abstract

This study was conducted on the Musi Bridge Project of the Kayu Agung–Palembang–Betung Toll Road to determine the most efficient and controlled concrete supply method, considering the high proportion of concrete costs, potential distribution delays, and structural quality requirements in strategic infrastructure projects. The research aimed to compare the self-managed batching plant method and the ready-mix method in terms of cost efficiency, technical and non-technical risks, and concrete quality performance. A quantitative descriptive-comparative approach was applied using primary data from project documents, including cost summaries, material quantities and prices, job mix formulas, risk matrices, and quality testing reports, supported by field observations. The analysis involved cost calculations, risk scoring and categorization, and evaluation of compliance with technical specifications. The results show that the self-managed method achieved cost savings of 15.7% and lower risk levels compared to the ready-mix method, while both methods met structural quality requirements. Therefore, the study concludes that self-managed batching plants are more effective for large-scale projects when supported by adequate technical and operational capacity. Keywords: concrete supply method, self managed batching plant, ready-mix concrete, cost and risk analysis ;