Analysis of System Performance Improvement Due to DG Integration on 20kV Feeder Ampelgading: Case Study Using ETAP Simulation Akbar, Fajar Maulana; Sulistiawati, Irrine Budi; Wartana, I Made
SinarFe7 Vol. 7 No. 1 (2025): SinarFe7-7 2025
Publisher : FORTEI Regional VII Jawa Timur

Show Abstract | Download Original | Original Source | Check in Google Scholar

Abstract

The 20 kV Ampelgading feeder, which is integrated with the Ampelgading Hydropower Plant (PLTA) as a Distributed Generation (DG), still faces technical challenges such as low voltage at the downstream part of the network and relatively high active power losses. These issues are mainly caused by the long distribution line of approximately ±180 km and the uneven load distribution, which results in suboptimal power quality. This research aims to analyze the impact of capacitor bank installation on the voltage profile and line losses of the distribution system. The method employed is a simulation using ETAP 21.0.1 software under peak load conditions as the basis of analysis. The improvement strategy is implemented through the Optimal Capacitor Placement (OCP) method, which recommends the installation of 220 kVAR capacitors at Bus 62, Bus 70, and Bus 80 as the optimal locations based on voltage sensitivity analysis. The simulation results indicate that the capacitor bank injection successfully improves the minimum bus voltage from 0.939 p.u. in the base case to 0.973 p.u., ensuring that all buses meet the lower voltage limit standard of 0.95 p.u. Furthermore, total active power losses are reduced from 93.36 kW to 83.37 kW, representing a decrease of approximately 10.7%. These findings demonstrate that the OCP method is an effective technical solution for optimizing the performance of distribution networks, particularly for feeders with geographical and load characteristics similar to the Ampelgading feeder.
Pelatihan Pembuatan Frekuensi Osilasi dan Amplifier Audio pada Wireless Power Transmision untuk SMK Nurcahyo, Eko; Hidayat, Taufik; Soleh, Choirul; Parada Dian Palevi, Bima Romadhon; Yuwono, Alfarid Hendro; Wartana, I Made; Somawirata, I Komang; Isbadrianingtyas, Nafi
Jurnal Pengabdian kepada Masyarakat Nusantara Vol. 6 No. 4 (2025): Edisi Oktober - Desember
Publisher : Lembaga Dongan Dosen

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.55338/jpkmn.v6i4.7598

Abstract

Pelatihan pembuatan teknologi terus dikembangkan pada siswa Menengah Kejuruan sebagai pengembangan Kurikulum Berbasis Kompetensi Menuju Pendidikan Berkualitas. Salah satu SMK di Jawa Timur ini dituntut menyusun konsep awal, mengembangkan rencana kurikulum, dan melaksanakan uji coba kurikulum di lapangan. Pengembangan kurikulum di lapangan ini menjadi tantangan sendiri bagi SMK PGRI 2 Kertosono yang menciptakan pengembangan kurikulum dengan mengadakan pelatihan di kampus ITN Malang. Pelatihan yang mengarah ke teknologi ponsel dimana sebuah ponsel tidak dapat dilepaskan dari penggunaan charger. Charger yang umumnya digunakan membutuhkan energi listrik dari PLN dan generator. Sebagai alternatif baru, panel surya dapat menjadi solusi untuk menyediakan sumber energi listrik. Pelatihan ini berfokus pada penggunaan pengisian nirkabel yang menggunakan elektromagnetik dalam sistemnya, sehingga tidak memerlukan kabel saat digunakan. Tujuan pelatihan ini adalah melatih siswa agar dapat merancang pembuatan frekuensi osilasi dan amplifier audio pada Wireless Power Transmission dengan pengisian daya yang lebih besar sehingga bisa menciptakan produk yang di inginkan masyarakat dan dapat bersaing secara global.
Penggunaan Metode Rolling Sphere untuk Pengamanan Jaringan 150 kV dari Sambaran Petir Langsung Irrine Budi Sulistiawati; M Zaid Sahlan Shaufi; I Made Wartana
Jurnal JEETech Vol. 4 No. 1 (2023): Nomor 1 May
Publisher : Universitas Darul Ulum

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.32492/jeetech.v4i1.4104

Abstract

Lightning strikes can cause protection failure at substations such as equipment damage at substations due to insulation failure or what is known as flashover. Because of that, a lightning strike protection system is needed to minimize the occurrence of direct lightning strikes to equipment and buses at the substation. This study discusses the modeling of the protection of the substation from direct lightning strikes using the rolling sphere method at the Wonosari-pedan 150 kV substation using lightning rod poles. The calculation results show that with the configuration of a lightning rod as high as 21 m and the use of a ground wire of 17.8 m it meets the safe criteria for the height of the protected area in the case study of this research.
Kelayakan Finansial Pembangunan Pembangkit Listrik Tenaga Hybrid Di Sanggar Kota Batu, Jawa Timur WIDODO PUDJI MULJANTO; BELDA ROSALIE PUTRI WIYOGA; I MADE WARTANA; IRRINE BUDI SULISTIAWATI
ELKOMIKA: Jurnal Teknik Energi Elektrik, Teknik Telekomunikasi, & Teknik Elektronika Vol 12, No 4: Published October 2024
Publisher : Institut Teknologi Nasional, Bandung

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.26760/elkomika.v12i4.1063

Abstract

ABSTRAKIndonesia masih bergantung pada energi fosil untuk sumber pembangkit listrik. Mengingat, bahan bakar fosil terbatas, upaya melakukan peralihan ke energi terbarukan dan ramah lingkungan semakin digiatkan. Studi kasus penelitian dilakukan di Sanggar Latar di Batu dengan melakukan analisa kelayakan pembangunan Pembangkit Listrik Tenaga Phikohidro dan Pembangkit Lisrik Tenaga Surya. Analisa yang digunakan untuk melihat layak dan tidaknya proyek dengan menghitung selisih kas masuk dan keluar (NPV), tingkat pengembalian yang diharapkan dari proyek (IRR), serta total manfaat yang diperoleh beserta pengeluaran biaya yang dilakukan. Menggunakan asumsi investasi selama 25 tahun dan suku bunga 6 %, diperoleh besar selisih kas sebesar Rp 86.158.036,-, Tingkat pengembalian (IRR) 47%, dengan total manfaat sebesar (BCR) 4,10. Waktu yang dibutuhkan untuk pengembalian investasi selama 2,33 tahun artinya pembangunan pembangkit listrik tenaga hybrid dapat direalisasikan.Kata kunci: analisis investasi, kelayakan proyek, pembangkit listrik tenaga hibrid ABSTRACTIndonesia still relies on fossil energy as a power plant. Knowing that fossil fuels are limited, the efforts of new and environmentally friendly energy resources are being intensified. A case study conducted at Sanggar Latar in Batu, using the analysis of the feasability of establishing both a biomass power plant (PLTPh) and a solar power plant (PLST). The analysis that is used to the project on worthy or not with calculating differences of cash in and out (NPV), the level of returning that is hoped from the project (IRR), and the total of benefits received with the expenses that is done. Using investment assumption for 25 years and interest rate 6%, a large differences was obtained with Rp 86.158.036,-, cash, level of return (IRR) 47%, and the benefit total (BCR) 4,10. Time needed for the investment return is 2,33 years that is the development of hybrid power plant can be realized.Keywords: investment analysis, project feasibility, hybrid power plant
Co-Authors Abdelfatah, Magdy S. Abidin, Dimas Zainal Abraham Lomi achmad_bashori_kurniawan Ahmad Fauzan Akbar, Fajar Maulana Alfarid Alfarid Hendro Yuwono Alfian Daniel Toding Anang Tri Wibowo Awan Uji Krismanto BELDA ROSALIE PUTRI WIYOGA Bernadus Halik Bima Romadhon Parada Dian Palevi Choirul Saleh Choirul Saleh Choirul Saleh Cholis Setiawan Citra Dewi Megawati Decky Satrio Pamungkas Deva Nur Rifdah Efendi, Khorul Fahmi EKO NURCAHYO Eko Yohanes Setyawan Fransiscus R B N Kabosu Harry Prayogo Herbasuki, Teguh Hidayat, Rian Arby Hidayat Huda, Muhamad Tri Agus Latifatul Huda I Gusti Agung Rai Yuda Wardana I Kadek Rangga Satria Billy I Komang Somawirata Ida Soewarni Ignatius Iktinus Widiantoro Irrine B Sulistiawati Irrine Budi Sulistiawati Jai Govind Singh Lauhil Mahfudz Hayusman Lauhil Mahfudz Hayusman Lauhil Mahfudz Hayusman, Lauhil Mahfudz M Zaid Sahlan Shaufi M. Abd Hamid M. Ibrahim Ashari M. Ibrahim Ashari M. Nurjansyah Dwi Laksono Mahindra Tegar Mimien Mustikawati Mochamad Yajit Albustomi Mohammad Rizal Wijayanto Muljanto, Widodo Pudji Nafi Isbadrianingtyas, Nafi Ni Putu Agustini Ni Putu Agustini Ni Putu Agustini Ni Putu Agustini Palevi, Bima Romadhon Parada Dian Parada Dian Palevi, Bima Romadhon Parama Diptya Widayaka Putu Rachmadi Setiawan Radimas Putra Muhammad Davi Labib Reza Diharja Reza Diharja risky.a.f, Risky Sasidharan Sreedharan Sasidharan Sreedharan Sirojul Hadi Soeparno Djiwo Solanki, Parmal Singh Soleh, Choirul Sreedharan, Sasidharan Taufik Hidayat Taufik Hidayat Taufik Hidayat Teguh Herbasuki Widodo Pudji Muljanto WIDODO PUDJI MULJANTO Willy Armando Wabes Zulfikar Zauzi Zulfikar Zauzi