Claim Missing Document
Check
Articles

Found 35 Documents
Search

KECELAKAAN TENAGA KERJA PADA PROYEK KONSTRUKSI DI KABUPATEN TABANAN Srijayanthi, Ni Luh Putu; Sudipta, I Gusti Ketut; Putera, IGA. Adnyana
Jurnal Ilmiah Elektronik Infrastruktur Teknik Sipil Vol 1 No 1 (2012): Vol.1, No.1, Desember 2012
Publisher : Jurnal Ilmiah Elektronik Infrastruktur Teknik Sipil

Show Abstract | Download Original | Original Source | Check in Google Scholar | Full PDF (305.091 KB)

Abstract

Abstrak : Kabupaten Tabanan merupakan salah satu bagian wilayah Provinsi Bali dimana dewasa ini pembangunan khususnya pembangunan konstruksi gedung perkembangannya cukup pesat. Secara umum industri konstruksi adalah industri yang menduduki tempat tertinggi ditinjau dari tingkat terjadinya kecelakaan kerja (Dipohusodo, 1996). Penelitian ini dilakukan dengan tujuan untuk mengetahui tingkat kecelakaan tenaga kerja, hubungan kelompok faktor sistem manajemen, perbuatan berbahaya, dan kondisi berbahaya dengan kecelakaan tenaga kerja, mengetahui kelompok faktor yang memberikan  pengaruh terbesar terhadap kecelakaan tenaga kerja pada proyek konstruksi di Kabupaten Tabanan. Data yang diperlukan meliputi data primer dan data sekunder. Metode yang digunakan dalam analisis adalah analisis regresi ganda, analisis korelasi ganda, dan sumbangan relatif. Dari hasil analisis diperoleh bahwa tingkat kecelakaan tenaga kerja di Kabupaten Tabanan adalah sedang,  sedangkan hubungan kelompok faktor yang mempengaruhi kecelakaan tenaga kerja terhadap kecelakaan tenaga kerja pada proyek konstruksi adalah kuat dan 39,473%  kecelakaan tenaga kerja pada proyek konstruksi ditentukan oleh 3 kelompok faktor yang mempengaruhi kecelakaan tenaga kerja tersebut dengan penyebab kecelakaan kelompok faktor yang paling dominan dalah kelompok faktor kondisi berbahaya, diikuti oleh sistem menejemen, dan perbuatan berbahaya.
INVESTMENT RISK IDENTIFICATION FOR THREE STARS HOTEL IN BALI I Gusti Agung Adnyana Putera; Wayan Sri Kristinayanti; I Nyoman Norken
Jurnal Teknobisnis Vol 7, No 1 (2012): Jurnal TEKNOBISNIS
Publisher : Lembaga Penelitian dan Pengabdian kepada Masyarakat- Institut Teknologi Sepuluh Nopember

Show Abstract | Download Original | Original Source | Check in Google Scholar | Full PDF (3451.002 KB) | DOI: 10.12962/j24609463.v7i1.2424

Abstract

The three stars hotel occupation in Bali is unpredictable compared to other luxury hotels. However the average length of stay at the hotel of this level is higher than the other five-star hotel. Both types provide opportunities and risk to investor, thus, that investor need to conduct broad examination before do some investment, especially to identify risk factors for investment. This paper presents comprehensive risk factors of investing in three star hotels in Bali. Data obtained from structured interview to the tourist of the various levels of tourism management in Bali. The data ware processed using a descriptive qualitative into three major groups namely the major risk, unacceptable risk, and undesirable risk. The results of this study indicate that there ware 40 types of investment risk on a three-star hotel in Bali. Amongst the 40 types of these risk, only 25% was acceptable risk and negligible risk, while the rest categorized major risk. Between the major risk, 50% was unacceptable risk and the remaining 25% was an undesirable risk. Unacceptable risk were classified into risk occurs more often in pre-design activities which mainly related to marketing activity, even as the dominant risk was the environmental problem, especially with the traditional village-awing awing (local village regulations). Risks a classified as undesirable risk were more common in the activities during the operation of hotels, which are generally triggered from the human risk.
ANALISIS PERCEPATAN PELAKSANAAN PROYEK UNIT LAYANAN KANKER TERPADU RSUD BALI MANDARA DENGAN METODE FAST TRACK G.A.P Candra Dharmayanti; I Gusti Agung Adnyana Putera; Made Yoga Prasetya
Jurnal Ilmiah Teknik Sipil Jurnal Ilmiah Teknik Sipil, Vol. 25, No. 1, Januari 2021
Publisher : Department of Civil Engineering, Udayana University

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.24843/JITS.2021.v25.i01.p10

Abstract

Unit Layanan Kanker Terpadu RSUD Bali Mandara construction project has a building area of 4.272,74 m2. Projects with a contract value of Rp52.364.056.071 began work on May 6, 2019, and planned to finish on December 1, 2019. At the time of the study, the project progress report up to the 12th week showed a 3,76% delay in project implementation. This affects the project completion time and the contractor may be subject to penalty for the delay. This study’s purpose to design a schedule to get the acceleration of construction time using the fast track method and compare the results obtained by the conditions of project implementation experiencing delays. Secondary data used include time schedules, budget plans (RAB), weekly reports of supervisory consultants, analysis of contractor unit prices, and project drawings. The value of the implementation budget plan (RAP) is Rp45.917.529.226,76 calculated based on the RAB of the contractor without taxes and profits. The results of the analysis using the fast track method show that the project can be accelerated so that it can be finished according to the planned schedule by accelerating by 59 days (22,7%) from the duration of project implementation in a late condition (without acceleration). In terms of cost, project implementation in a late condition incurs more costs than the project implementation using the fast track method. The magnitude of the additional costs of implementing the project with a late condition of Rp2.656.202.803,55 or 5,468% more than the application of the fast track method. The application of the fast track method results in changes in the number of workers and material procurement needs at a time caused by the time shifts in activities implemented out in parallel.
MODEL ESTIMASI TERINTEGRASI BIAYA LANGSUNG PELAKSANAAN KONSTRUKSI DENGAN JADWAL PELAKSANAAN I Gusti Agung Adnyana Putera
Jurnal Ilmiah Teknik Sipil Vol. 13, No. 2 Juli 2009
Publisher : Department of Civil Engineering, Udayana University

Show Abstract | Download Original | Original Source | Check in Google Scholar | Full PDF (98.13 KB)

Abstract

Estimation of duration and cost of a project are two classical problemsthat always arise in the real world construction project. In the current practice, thecost is analyzed separately from a planning by estimators. In fact, time and cost ofthe construction project depend on what kind of product to be constructed, how torealize it, when and where it has to be constructed. They have an intimateinterrelationship and can not be separated while analyzing them. When a planningof activities is changed, the project cost would change as well. The existing costmodel does not integrate this relation. The project cost is estimated based on theassumed rates of construction resources and gross quantity of works without takinginto account how the activities will be performed. This paper proposes a cost modelthat can integrate the planning and the construction direct cost based on the dailynecessary resources of the related planning. It presents also some examples of itsapplication. This model is very useful to simulate the real project direct cost froman estimated planning before executing the project. The accuracy of the resultdepends completely on the accuracy of estimated planning and the basicinformation corresponding to time and cost estimation of an elementary activity.
MODEL PENGGUNAAN LAHAN UNTUK BANGUNAN DI WILAYAH TRANSISI PROVINSI BALI I Gusti Ketut Sudipta; IGA. Adnyana Putera; I Gusti Putu Suparsa
Jurnal Ilmiah Teknik Sipil Vol. 13, No. 1 Januari 2009
Publisher : Department of Civil Engineering, Udayana University

Show Abstract | Download Original | Original Source | Check in Google Scholar | Full PDF (108.246 KB)

Abstract

The growth of land use for building in Bali Province may pose problemsin the foreseeable future. The primary objective of this research is to assess therelation of the land use area for the building against time in the period to come, howlong the land could support the growth of the land use for building and to identifythe regulating method of the land use for building in transitional territory of BaliProvince in order to be able to sustain long term growth.The research data consisted of the area of the settlement, tourism and cultivationzones that were obtained from The Revised Map of The Bali Province SpatialPlanning 2003. The rest of the research data consisted of buildings number and landuser in form of data series that were obtained through documents registrationtechnique.Results of the analysis showed that the forecast annual growth of land use forbuilding in transitional territory of Bali Province was 2.32%; the settlement zonecould only support the growth of the land use for the building up until 2013; thetourism zone could support the growth for much longer time; the cultivation zonewill be fully used in 2072; efforts so that the land could support the growth of theland use for building longer in transitional territory of Bali Province were to reducepopulation growth or to reduce land use area designated per 1 building user.
MEMAHAMI DAN MENGHUBUNGKAN METRIK EVM DENGAN SKEDUL PROYEK KONSTRUKSI I Gusti Agung Adnyana Putera
Jurnal Ilmiah Teknik Sipil Jurnal Ilmiah Teknik Sipil, Vol. 22, No. 2, Juli 2018
Publisher : Department of Civil Engineering, Udayana University

Show Abstract | Download Original | Original Source | Check in Google Scholar | Full PDF (306.38 KB) | DOI: 10.24843/JITS.2018.v22.i02.p01

Abstract

Earned Value Management (EVM) merupakan model yang dikenal sebagai alat bantu manajer untuk mengidentifkasi dan mengendalikan masalah-masalah dalam pelaksanaan konstruksi sebelum terjadi. Model ini menggunakan tiga data dasar untuk menghitung indikator-indikator (metrik) EVM yaitu Nilai Rencana, Nilai Hasil, dan Biaya Aktual. Model ini cukup sederhana dalam konsep tetapi tidak mudah diterapkan pada praktik pengendalian proyek konstruksi. Metrik EVM umumnya disajikan dalam dimensi uang dan indeks tanpa dimensi. Hal ini sering menyulitkan praktisi pemula untuk menerapkan model ini karena mereka lebih sering hanya menggunakan dimensi waktu dalam mengendalikan skedul mereka. Studi ini menyajikan berbagai istilah dan indikator-indikator EVM seperti PV, BCWS, EV, BCWP, ACWP, SPI, CPI, EAC, BAC dan TCPI. Penelitian ini juga memaparkan cara menentukan tiga data dasar EVM dengan menyajikan contoh skedul sederhana sehingga istilah-istilah dan makna indikator-indikator EVM lebih mudah dipahami. Selain itu, studi ini juga menyajikan hubungan metrik EVM dengan skedul. Metode yang digunakan dalam studi ini adalah metode empiris dan analisis kritis metrik EVM berkaitan dengan kebutuhan praktis kontraktor kecil dan praktisi pemula. Sebagai simpulan dari kajian ini adalah metrik EVM dapat ditentukan secara mudah dengan menggunakan formula metrik EVM, apabila tiga data dasar EVM dipahami secara benar. Kesulitan utama yang dihadapi oleh praktisi pemula adalah adanya banyak istilah yang digunakan untuk menyatakan tiga data dasar EVM. Selain itu, beberapa formulasi hubungan antara metrik EVM dengan skedul telah disajikan dalam studi ini, namun perlu dikaji lebih dalam dan lebih luas mengenai hubungan antara metrik EVM dengan skedul.
Cover and TOC, Vol. 22, No. 2, Juli 2018 I Gusti Agung Adnyana Putera
Jurnal Ilmiah Teknik Sipil Jurnal Ilmiah Teknik Sipil, Vol. 22, No. 2, Juli 2018
Publisher : Department of Civil Engineering, Udayana University

Show Abstract | Download Original | Original Source | Check in Google Scholar | Full PDF (272.216 KB)

Abstract

MODEL PENGGUNAAN LAHAN UNTUK BANGUNAN DI WILAYAH PERKOTAAN PROVINSI BALI I Gusti Ketut Sudipta; IGA. Adnyana Putera; I Gusti Putu Suparsa
Jurnal Ilmiah Teknik Sipil Vol. 12, No. 2 Juli 2008
Publisher : Department of Civil Engineering, Udayana University

Show Abstract | Download Original | Original Source | Check in Google Scholar | Full PDF (117.941 KB)

Abstract

The growth of the land use for building in Bali Province may pose problems in the foreseeable future. The primary objective of the research has been to assess the relation of the land use area for the building against time in the period to come, how long the land could support the growth of the land use for building and to identify the regulating method of the land use for building in urban territory of Bali Province in order to be able to sustain long term growth. The research data consisted of the area of the settlement, tourism and cultivation zones that were obtained from The Revised Map of The Bali Province Spatial Planning 2003. The rest of the research data consisted of buildings number and land user in form of data series that were obtained through documents registration technique. Results of the analysis showed that: the forecasted annual growth of land use for building in urban territory of Bali Province was 2.32%; the settlement zone could only support the growth of the land use for the building up until 2013; the tourism zone could support the growth for much longer time; the cultivation zone will be fully used in 2072; efforts so that the land could support the growth of the land use for building longer in urban territory of Bali Province were to reduce population growth or to reduce land use area designated for 1 building user.
PROSES MODEL PENJADWALAN PROYEK DENGAN ALGORITME GENETIKA I Gusti Agung Adnyana Putera
Jurnal Ilmiah Teknik Sipil Vol. 14, No. 1 Januari 2010
Publisher : Department of Civil Engineering, Udayana University

Show Abstract | Download Original | Original Source | Check in Google Scholar | Full PDF (91.756 KB)

Abstract

In the real construction world, resources for construction activitiesare usually limited. The critical path method (CPM) that has beenintensively used in construction industry for planning and controlling ofconstruction, is not feasible for this problem because of the unlimitedresources assumption. To deal with the limited resources, constructionplanner must include resources allocation in order to find out an applicableproject planning. The activity’s duration and their sequences may need to beadjusted by considering the available resources at the considered time. Thispaper presents a process model for project planning using the geneticalgorithm searching technique to solve the multicriteria problem inconstruction planning in order to find out an optimal construction projectplanning. The genetic algorithm can solve the combinatorial problems ofproject planning and give an integrated planning solution, such as, projectplanning, resources levelling, smoothing by considering multi-criteria andmulti-constraints for project planning.
ANALISIS SIKAP DAN PERILAKU KONSUMEN DALAM MEMILIH RUMAH SEDERHANA SEHAT (RSH) PADA PT. BALI KARISMA PRATAMA KABUPATEN BADUNG, BALI I Wayan Muka; IGA. Adnyana Putera; Gede Astawa Diputra
Jurnal Ilmiah Teknik Sipil Vol. 10, No. 2 Juli 2006
Publisher : Department of Civil Engineering, Udayana University

Show Abstract | Download Original | Original Source | Check in Google Scholar | Full PDF (149.67 KB)

Abstract

Persaingan antar pengembang untuk dapat menarik minat konsumen dalam memilih rumah semakin meningkat. Keputusan konsumen dalam memilih rumah dipengaruhi oleh sikap serta norma subyektif dalam lingkungan masyarakat. Norma terbentuk dari dorongan serta keyakinan yang berasal dari lingkungan sosial masyarakat, baik itu dari keluarga, teman, dan tetangga. Perilaku merupakan tindakan yang nyata dari konsumen setelah dapat menentukan sikapnya terhadap suatu produk. Sikap dan perilaku konsumen perlu diperhatikan untuk dapat menentukan langkah-langkah yang mesti diambil pengambang agar produk yang ditawarkan dapat diterima konsumen. Tujuan penelitian ini adalah untuk mengetahui: (1) Sikap dan perilaku konsumen dalam memilih rumah sederhana sehat (RSH) pada PT. Bali Karisma Pratama; (2) Mengidentifikasikan faktor-faktor yang menjadi pertimbangan konsumen dalam memilih rumah sederhana sehat (RSH) pada PT. Bali Karisma Pratama. Teknik analisis data yang digunakan adalah analisis deskriptif dengan metode Fishbein untuk mengukur sikap dan perilaku konsumen dan analisis statistik dengan analisis faktor untuk mengidentifikasi faktor-faktor pertimbangan utama konsumen dalam memilih rumah. Hasil analisis menunjukkan bahwa: (1) sikap dan perilaku konsumen dalam memilih rumah sederhana sehat (RSH) pada PT. Bali Karisma Pratama adalah baik, berarti penilaian konsumen terhadap 12(dua belas) variabel yang ada belum mendapat nilai ideal; (2) faktor yang terbentuk adalah 4(empat) faktor yaitu fisik perumahan, fasilitas umum perumahan, lingkungan perumahan, dan fasilitas sosial perumahan; (3) faktor-faktor yang menjadi pertimbangan utama bagi konsumen dalam memilih rumah adalah faktor fasilitas umum perumahan yaitu fasilitas air bersih/PDAM, fasilitas listrik/PLN dan fasilitas telepon. Hal ini menunjukkan bahwa fasilitas umum adalah sangat penting bagi konsumen karena fasilitas ini merupakan kebutuhan utama dibandingkan dengan fasilitas lainnya. Sehingga pada pengadaan pembangunan rumah sederhana sehat (RSH) ketiga variabel faktor fasilitas umum tersebut harus menjadi perhatian yang paling utama oleh pengembang.