ANALYSIS OF FACTORS CAUSED FOR DELAYING CONSTRUCTION ROAD REHABILITATION AND MAINTENANCE IN KEJAYAN PURWOSARI’S (LINK 197) PROJECT DUE TO COVID-19 PANDEMIC Ramadhani, Ardhi; Muhammadun, Haris; Oetomo, Wateno
INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY, ENGINEERING, AND INFORMATION SYSTEM Vol. 1 No. 3 (2022): AUGUST
Publisher : Transpublika Publisher

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.55047/ijateis.v1i3.427

Abstract

Implementation of Construction Projects that run within a limited time must be removed from the factors that cause project delays to run optimally and appropriately. This study aims to analyze the factors causing delays in road rehabilitation and maintenance in Kejayan Purwosari (Link 197) construction projects due to the Covid-19 pandemic. The study population consist of 80 people and the number of research samples is the total population. The data collection technique is done by distributing questionnaires. Techniques for analyzing research data using Partial Least Square (PLS). The results of the study prove that the factors of Manpower, Materials and Equipment have no significant effect on Project Delay. Meanwhile, the factors of Construction Method, Relationship and Time and Control have a significant effect on Project Delay.
STUDY OF THE CAUSES OF ROAD DAMAGE TO CAPTAIN HARUN TOHIR STREET, GRESIK EAST JAVA Ramadhani, Ardhi; Muhammadun, Haris; Oetomo, Wateno
INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY, ENGINEERING, AND INFORMATION SYSTEM Vol. 1 No. 3 (2022): AUGUST
Publisher : Transpublika Publisher

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.55047/ijateis.v1i3.457

Abstract

This study aims to make a study and technical planning of the road following the traffic of heavy vehicle loads through the Harun Tohir road. Road maintenance is an activity to maintain, repair, add or replace existing physical buildings so that their functions can be maintained or enhanced for a longer period. This maintenance guideline is intended to regulate the procedures for carrying out rigid pavement maintenance activities, and maintain stable serviceability conditions, to provide safety and comfort to road users. This guideline for the maintenance of rigid pavements includes descriptions of the types of damage that commonly occur in rigid pavements, their possible causes, follow-up consequences, recommendations for handling, and methods.
STUDY OF DRAINAGE, PANORAMIC HOUSING, CEMENGKALANG VILLAGE, SIDOARJO DISTRICT Ismanto, Ikko Bagus; Nugroho, Laksono Djoko; Oetomo, Wateno
INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY, ENGINEERING, AND INFORMATION SYSTEM Vol. 1 No. 3 (2022): AUGUST
Publisher : Transpublika Publisher

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.55047/ijateis.v1i3.458

Abstract

Panorama Residence housing which has an area of 8000 m2 is located in a plain area with a slope of about 0-1%. The survey results on the Panorama Residence Housing, Cemengkalang Village, Sidoarjo District, have an elevation of -0.20 m, slightly above the flood level – 0.30 m. This area has a high probability of flooding due to overflow from the Pucang River, which runs off (run-off water) from other areas if it rains with high intensity. Moreover, the Panorama Residence area is a dense residential area with roads and parking lots, so rainwater has a smaller chance of infiltrating and running off. After analysis, The flood discharge at the 25-year return period on the Pucang River was 72,561 m3/sec. At the same time, the cross-sectional capacity of the Pucang River was 64,402 m3/sec, so the cross-section of the Pucang River at the Panorama Residence Housing location experienced overflow. The run-off volume is 102.6 m3, while the total capacity is 565.68 m3, so the extended storage capacity is quite adequate. In rainy conditions, t = 30 minutes, the run-off volume that occurs = 30.96 m3, and the total channel length = 493.12 m, the total drainage channel capacity = 184.92 m3 is greater than the run-off volume, 30.96 m3.
COMPARATIVE ANALYSIS OF ACCELERATION ALTERNATIVES FOR THE DRAINAGE CHANNEL PROJECT ON XYZ STREET USINGTHE TIME-COST TRADE-OFF (TCTO) METHOD Prasetiyo W., Arif; Oetomo, Wateno; Wulandari, Esti
INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY, ENGINEERING, AND INFORMATION SYSTEM Vol. 2 No. 3 (2023): AUGUST
Publisher : Transpublika Publisher

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.55047/ijateis.v2i3.882

Abstract

In response to the increasing occurrence of rain, the city government is actively striving to mitigate urban flooding by enhancing the drainage system. Collaboration with contracted construction firms is central to this endeavor, although it is not without its challenges, including community opposition driven by concerns over potential disruptions and limited financial resources among contractors. This study adopts the Critical Path Method (CPM) and Microsoft Project software, supplemented with the Time Cost Trade Off (TCTO) method to expedite project completion, emphasizing a comprehensive evaluation that encompasses both time and financial aspects. Notably, the analysis identifies the most feasible acceleration opportunity within the excavation of ordinary soil for construction, with original plans indicating a cost of Rp. 60,818,919 over a 40-day period. Three alternatives are considered: (1) overtime labor, incurring Rp. 65,520,000, with a 34-day duration; (2) increased workforce, incurring Rp. 68,000,000, with a 34-day duration; and (3) introducing a new addendum for the replacement of manual excavation with heavy machinery, incurring Rp. 37,440,000, with a 16-day duration. In conclusion, this study provides a comprehensive strategy for accelerating the urban drainage project, considering the critical path, time-cost trade-offs, and cost-benefit factors, highlighting the significance of selecting the most cost-effective alternative while addressing community concerns and resource limitations in flood risk mitigation efforts.
PERFORMANCE ANALYSIS OF SUPERVISORY CONSULTANTS ON PROJECTS IN THE HOUSING AND SETTLEMENT AREAS OF EAST JAVA PROVINCE Rahadian, Deni; Koespiadi, Koespiadi; Oetomo, Wateno
INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY, ENGINEERING, AND INFORMATION SYSTEM Vol. 2 No. 3 (2023): AUGUST
Publisher : Transpublika Publisher

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.55047/ijateis.v2i3.1015

Abstract

The Supervisory Consultant is the party assigned by the project owner to realize the planned planning results according to the development of good settlement infrastructure facilities and utilities. The government, especially in the PRKP Division of East Java Province, collaborates with service providers, one of which is a supervisory consultant, in this case encouraging supervisory consultants to increase understanding of customer satisfaction. This research has several objectives, namely identifying variables of project management performance of PRKP activities in East Java Province; measuring the level of customer satisfaction from the project management performance of PRKP activities in East Java Province. The research stages taken in this study, namely Research background, Formulation of problems and research objectives, Literature study, Preliminary survey, Data collection, Data testing, Data analysis. The analysis method used is the customer satisfaction index method. The data is processed using the MS.Excel and SPSS programs. The results of the analysis with the customer satisfaction index show a CSI value of 63.55% which means satisfied. which is low and needs to be improved.
ANALYSIS OF PROJECT DELAY USING THE CRITICAL PATH METHOD (CPM): A CASE STUDY ON THE CONSTRUCTION PROJECT OF THE OPD OFFICE BUILDING IN PASURUAN Purnomo, Didik; Oetomo, Wateno; Marleno, Risma
JOURNAL OF HUMANITIES, SOCIAL SCIENCES AND BUSINESS Vol. 3 No. 2 (2024): FEBRUARY
Publisher : Transpublika Publisher

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.55047/jhssb.v3i2.1006

Abstract

In construction project control, the main factors of concern are quality, time and cost control. So it is necessary to use one method in the implementation of control. This study aims to analyze the time and cost of the Raci OPD Office Building Construction project. The benefit of this research is to anticipate potential delays that occur in the project. The problem limitation is focused on work that has not been completed in the remaining time of the contract period. To analyze time and cost, this research uses Critical Path Method (CPM) and Time-Cost Trade-Off (TCTO) which begins with determining the work network and critical path. TCTO analysis is carried out by shortening the duration of work by adding 3 hours of overtime and calculating the Crash Slope of each job on the critical path. Rescheduling is done by accelerating the work that has the lowest cost. The results showed that the most effective rescheduling was carried out on the Lt.3 Installation and Plastering work with the acquisition of an acceleration duration of 8 days. And the total cost required for this acceleration is Rp. 29,441,424, - or Rp. 1,226,726, - per day for 24 days.
TIME PERFORMANCE ANALYSIS ON THE CONSTRUCTION PROJECT OF SUBALI BRIDGE IN SUTOJAYAN DISTRICT (D.G.008), BLITAR REGENCY, USING THE EARNED VALUE METHODOLOGY APPROACH Setyawan, Dhimas Triadi; Oetomo, Wateno; Marleno, Risma
JOURNAL OF HUMANITIES, SOCIAL SCIENCES AND BUSINESS Vol. 3 No. 2 (2024): FEBRUARY
Publisher : Transpublika Publisher

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.55047/jhssb.v3i2.1041

Abstract

One of the project types is the Construction Project. The main activity components of this type of project consist of feasibility assessment, engineering design, procurement and construction. In construction projects very often delays occur where the realization in the field does not match the schedule of the implementation plan, due to several factors that occur, even though a careful plan has been prepared but in practice in the field there are still many problems in implementation. The purpose of this study was to determine the performance of time in the implementation that took place from week -1 to week 17 on the Subali Bridge Construction project, Sutojayan Kec. (D.G.008), Blitar Regency using Earned Value. From the results of the analysis it can be seen that the costs incurred are lower than the planned costs, this can be seen in the CPI value of 1.28 while the implementation time is slower than the planned schedule indicated by the SPI value of 0.71.
EARNED VALUE ANALYSIS FOR COST AND TIME EFFICIENCY ON THE BONDOWOSO POLIJE CAMPUS ADMINISTRATION BUILDING PROJECT Irniawan, Dodik; Oetomo, Wateno; Marleno, Risma
JOURNAL OF HUMANITIES, SOCIAL SCIENCES AND BUSINESS Vol. 3 No. 2 (2024): FEBRUARY
Publisher : Transpublika Publisher

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.55047/jhssb.v3i2.1042

Abstract

The problem in the implementation of the Bondowoso Polije Campus Administration Building Project is the limited cost and time available. With a 5 (five) storey building design with a reinforced concrete structure, each floor of which has an area of 240 m2 with a total floor area of almost 1440 m2, this building is a fairly complex building, in terms of the function of the building itself. The contract value of physical work amounted to Rp. 5,599,873,601.60 and was carried out within 120 days or 18 weeks. This research method uses Earned Value Method. From the analysis, results and discussion of the Bondowoso Polije Campus Administration Building project, the main conclusion is that there are variations in cost and time during the project period, with the lowest value of Cost Variation reaching (-)Rp 228,191,016.04 in week 7. Although the Cost Productivity Index (CPI) showed positive and negative variations, with a low of 0.672 in week 7, the Time Productivity Index (SPI) was always < 1, reaching a final value of 0.663. The estimated cost (EAC) to complete the project is IDR 5,993,156,919.70, while the estimated total work time (EAS) of the project is 20.543 weeks. Overall, the project is expected to experience a delay of 2.543 weeks and a cost loss of Rp 393,323,318.10.
Analisis Biaya dan Waktu Menggunakan Crashing Method pada Proyek Peningkatan Jalan Banyakan – Tiron Kediri Mahendra, Muhammad Yusuf; Oetomo, Wateno
Portal: Jurnal Teknik Sipil Vol 15, No 2 (2023): October Edition
Publisher : Politeknik Negeri Lhokseumawe

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.30811/portal.v15i2.4671

Abstract

In the world of construction, time, quality, and cost are three important components in a construction project planning. Therefore, in a construction project, project control is needed. The wide scope of project work is a driving factor that project work can experience a time delay problem. Project delays can be anticipated by accelerating (crashing) which in its implementation must still pay attention to cost factors. Crashing is a deliberate, systematic and analytical process by testing all activities in a project centered on activities that are on the critical path. Accelerating the time of each activity definitely causes the project completion time to be faster. But the acceleration of the time of these activities will also affect the project in terms of cost. This research was conducted on the Banyakan - Tiron Kediri Road Improvement Project, where the achievement of field progress in week 11, the project experienced a delay of 16.90% with a progress value of 14.72% of the planned progress of 31.62%. This research was conducted with alternatives to increase working hours (overtime) and increase the number of workers. The acceleration results of the two alternatives are compared and the most optimal acceleration alternative is sought. The results of the analysis of the acceleration with the crashing method with alternative additional working hours obtained the total duration of the project to 112 days, from the total duration of the normal condition project for 135 days. Then there was a change in the total cost of the project which previously amounted to Rp. 7,446,453,000.00 to Rp. 7,407,272,294.12. Meanwhile, in the alternative of increasing the number of workers, the total duration of the project is 94 days, from the total duration of the normal condition project for 135 days. Then there was a change in the total cost of the project which previously amounted to Rp. 7,446,453,000.00 to Rp. 7,333,584,952.22. Of the two alternatives, the most efficient alternative to accelerate work completion is to increase the number of workers.
Analisis Kelaikan Fungsi Bangunan Gedung Rumah Sakit Ibu dan Anak Nirmala Kediri Irfan, Ahmad; Oetomo, Wateno
Portal: Jurnal Teknik Sipil Vol 16, No 1 (2024): Special Edition January 2024: Improving skills and ease in various civil engine
Publisher : Politeknik Negeri Lhokseumawe

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.30811/portal.v16i1.4676

Abstract

Indonesia is a developing country which is currently actively carrying out development, both physical development such as buildings, bridges, roads, ports and other physical development as well as non-physical development such as mental rehabilitation. The suitability of a building is a requirement that must be met to obtain a functionally fit certification. Fulfillment of eligibility has several requirements such as safety, health, comfort and convenience. The Nirmala Mother and Child Hospital building is located on Jalan Attorney General Suprapto, Kediri City, East Java. Based on the results of interviews with project supervisors and direct observations in the field, building planning does not refer to the Minister of Health Regulation. This study aims to evaluate the comparison of the existing spatial layout of the Nirmala Mother and Child Hospital with Minister of Health Regulation No. 40 of 2022. Results of the evaluation of the building's functional suitability evaluation based on Minister of Health Regulation No. 40 of 2022 on the spatial layout of the Nirmala Kediri Mother and Child Hospital has met the spatial planning requirements according to the Minister of Health, but with the caveat that there must be an additional waiting room in each examination and treatment room.