DAS Ampal Analisa Fungsi dan Pengaruh Bangunan Pengendali Banjir DAS Ampal Kota Balikpapan Kadar Yanti, Rossana Margaret; Edijatno, Edijatno; Lasminto, Umboro
Specta Journal Vol 2 No 3 (2018): SPECTA Journal of Technology
Publisher : Specta Journal

Show Abstract | Download Original | Original Source | Check in Google Scholar | Full PDF (548.979 KB) | DOI: 10.0610/specta.v2i3.10

Abstract

Ampal Catchment Area has 25.273 km2 area and 4.699 km main river length, which planned to have 13 flood control construction. Until 2017, this catchment area has only three flood control construction. The watershed has only three built-in batters that are used to reduce the amount of flood discharge flowing on the Ampal river. Based on these conditions, it is necessary to analyze the magnitude of the difference of flood peak discharge on the existing condition (three bendali) compared with the condition of the plan (thirteen bendali). Therefore, analyzed the function and influence of flood control construction in Ampal Catchment Area by counting the flood peak discharge in each condition. From the analysis result, obtained the amount of peak discharge flowing in Ampal river existing condition is equal to 170,40 m3/s while at the condition of plan is equal to 83,80 m3/s. From the results of analysis, it is stated that the magnitude of the decrease of debit (?Q) after all the builds is 86.60 m3/s.
DAS Ampal Analisa Fungsi dan Pengaruh Bangunan Pengendali Banjir DAS Ampal Kota Balikpapan Kadar Yanti, Rossana Margaret; Edijatno, Edijatno; Lasminto, Umboro
SPECTA Journal of Technology Vol 2 No 3 (2018): SPECTA Journal of Technology
Publisher : LPPM ITK

Show Abstract | Download Original | Original Source | Check in Google Scholar | Full PDF (548.979 KB) | DOI: 10.35718/specta.v2i3.10

Abstract

Ampal Catchment Area has 25.273 km2 area and 4.699 km main river length, which planned to have 13 flood control construction. Until 2017, this catchment area has only three flood control construction. The watershed has only three built-in batters that are used to reduce the amount of flood discharge flowing on the Ampal river. Based on these conditions, it is necessary to analyze the magnitude of the difference of flood peak discharge on the existing condition (three bendali) compared with the condition of the plan (thirteen bendali). Therefore, analyzed the function and influence of flood control construction in Ampal Catchment Area by counting the flood peak discharge in each condition. From the analysis result, obtained the amount of peak discharge flowing in Ampal river existing condition is equal to 170,40 m3/s while at the condition of plan is equal to 83,80 m3/s. From the results of analysis, it is stated that the magnitude of the decrease of debit (?Q) after all the builds is 86.60 m3/s.
DAS Ampal Analisa Fungsi dan Pengaruh Bangunan Pengendali Banjir DAS Ampal Kota Balikpapan Rossana Margaret Kadar Yanti; Edijatno Edijatno; Umboro Lasminto
SPECTA Journal of Technology Vol. 2 No. 3 (2018): SPECTA Journal of Technology
Publisher : LPPM ITK

Show Abstract | Download Original | Original Source | Check in Google Scholar | Full PDF (548.979 KB) | DOI: 10.35718/specta.v2i3.10

Abstract

Ampal Catchment Area has 25.273 km2 area and 4.699 km main river length, which planned to have 13 flood control construction. Until 2017, this catchment area has only three flood control construction. The watershed has only three built-in batters that are used to reduce the amount of flood discharge flowing on the Ampal river. Based on these conditions, it is necessary to analyze the magnitude of the difference of flood peak discharge on the existing condition (three bendali) compared with the condition of the plan (thirteen bendali). Therefore, analyzed the function and influence of flood control construction in Ampal Catchment Area by counting the flood peak discharge in each condition. From the analysis result, obtained the amount of peak discharge flowing in Ampal river existing condition is equal to 170,40 m3/s while at the condition of plan is equal to 83,80 m3/s. From the results of analysis, it is stated that the magnitude of the decrease of debit (ΔQ) after all the builds is 86.60 m3/s.
Co-Authors Abdus Salam Afkarina Izzati Ahmad Dwi Cahyadi Aisyah Amelia Amrizal Amrizal Anak Agung Ngurah Satria Damarnegara Angela Jasmine Tanya Tjahyana Aninda Rahmaningtyas Anna A Misdanik Anwar, Nadjadji Ardelia Arlimasita Ashilah, Hafizhah Bagas Yoga Pratama Bahmid Tohari Bambang Sarwonno Bambang Sarwono Bangun Muljo Soekotjo Bangun Muljo Sukojo, Bangun Muljo Berlian Al Kindhi Brama Lesmono Budi Rahardjo Cahya Buana Catur Arif Prastyanto, Catur Arif Chandra Eko Prasetyo Chandra Murprabowo Mudjib Data Iranata Devy Amalia Dianeka, Belia Tatika Arno Dwi Retnowati Edijatno Edijatno Edijatno Edijatno Edijatno Edijatno Faradilla Ayu Rizki Shiami Farida Rahmawati Gemma Galgani Tunjung Dewandaru Habibur Rohman Hafidh Farisi Hendrata Wibisana Hera Widyastuti I Gede Tunas Irma Noor Fadhilla Istiar Jagad Dhita Kustyaningrum Jagad Dhita Kustyaningrum Lisna Isminingtyas Made Gita Pitaloka Maulana, Mahendra Andiek Mega Septia Sarda Dewi Mohamad Bagus Ansori Mohamad Bagus Ansori Muh. Fikri Ardwian Nastasia F Margini Nastasia Festy Marginia Novi Andriany Teguh Pukan, Mariano Ado Galot Rachmatika Nurita Rafika Nuramalia Riki Chandra Wijaya Riki Chandra Wijaya Risma Lupita Sari Rizaldi Firdaus Ardiyanto Rizky Saputra Rossana Margaret Kadar Yanti Safira Nur Afifah Sari, Putu Tantri Kumala Sarwono Sarwono Satria Damar Negara Satria Damar Negara Satria Damarnegara Satria Damarnegara Sharfina Cintantya Purwandani Sintya Maghfira Ismawati Sreenatha G. Anavatti Sukotjo, Bangun Muljo Tjahyana, Angela Jasmine Tanya Wahju Herijanto Wardoyo, Wasis Yang Ratri Savitri Yang Ratri Savitri Zakiyatun Nafisah Zharin F. Syahdinar