Analisis Pertukaran Waktu dan Biaya Menggunakan Metode Time Cost Trade Off (TCTO) pada Proyek Pembangunan Perumahan di PT. X Izzah, Nailul
Rekayasa Vol 10, No 1: April 2017
Publisher : Universitas Trunojoyo Madura

Show Abstract | Download Original | Original Source | Check in Google Scholar | Full PDF (450.909 KB) | DOI: 10.21107/rys.v10i1.3604

Abstract

Pada pembangunan proyek perumahan, perencanaan dibutuhkan untuk memperhitungkan berbagai variabel pekerjaan yang menyangkut sumber daya yang terbatas seperti waktu dan biaya. Tujuan dari penelitian ini  adalah mendeskripsikan aktivitas jaringan kerja yang optimal dengan metode Critical Path Method (CPM), perencananaan kelayakan yang optimal dengan metode Program Evaluation and Review Technique (PERT), dan mendeskripsikan waktu dan biaya proyek yang efisien dengan metode Time Cost Trade Off (TCTO) pada proses pembangunan perumahan. Jalur kritis dari penerapan metode critical path method (CPM) dimulai dari pekerjaan persiapan (A) sampai pekerjaan pagar (AB), tetapi ada satu yang tidak termasuk pada jalur kritis yaitu pekerjaan plafond (H). Pekerjaan tersebut memiliki nilai slack 25, artinya kegiatan tersebut memiliki kelonggaran waktu pengerjaan selama 25 hari. Dari penerapan metode program evaluation and review technique (PERT), proyek perumahan dapat diselesaikan lebih cepat dari kurun waktu normal selama 555 hari dengan waktu yang diharapkan 547 hari dengan peluang 64,8%. Sedangkan dari penerapan metode time cost trade off (TCTO), efisiensi waktu pengerjaan proyek dengan penambahan pekerja adalah 5,76% dengan selisih percepatan 32 hari kerja dan efisiensi biayanya adalah 0,156% dengan biaya optimal sebesar Rp. 6.753.245.793Kata kunci: Critical Path Method (CPM), Program Evaluation and Review Technique (PERT), Time Cost Trade Off (TCTO).  Time Exchange Analysis and Cost Using Time Cost Trade Off (TCTO) Method in Housing Development Projects in PT. XABSTRACTIn the construction of housing projects, planning is needed to account for the various work variables involving limited resources such as time and cost order to achieve the stated objectives and achieve the desired results. The purpose of this research is to describe optimal network activity from the application of Critical Path Method (CPM) method, to describe optimal feasibility planning from applying of Program Evaluation and Review Technique (PERT) method, and to describe time and cost of efficient project from application of Time method Cost Trade Off (TCTO) on the housing development process. The critical path from the application of the method of critical path method (CPM) starts from the preparatory work (A) to the fence work (AB), but there is one that is not included in the critical path ie the ceiling work (H). The work has a slack value of 25, meaning that the activity has a working time clearance for 25 days. From the implementation of the evaluation and review technique (PERT) program method, the housing project can be completed faster than the normal time period of 555 days with the expected time 547 days with a chance of 64.8%. While from the time cost trade off (TCTO) method, the time efficiency of project work with the addition of worker is 5.76% with the acceleration difference of 32 working days and the cost efficiency is 0.156% with the optimum cost of Rp.6.753.245.793.
Co-Authors Aditya, Bagus Galih ahmad arifin Ainiyah, Maslakhatul Ainul Yaqin Alisa, Alisa Amalia, Dian Risky Amaliyah Mushthoza, Dina Anggraini, Wulan Ariliana Ariyanda, Ariyanda Arning Wilujeng Ekawati Arsad, Sulastri Ayu Saputri, Dinda Azizah, Riski Nur bin Abdul Wahab, Muhammad Nubli Chamid, Noer Deddy Junaedi Erwanto, Nanang Fidani, Riki Firdaus, Rayyan Hafidz Yusuf, Muhammad Halim, Nur Hanim, Muhammad Ismail Hendi, Ade Hidayah, Afifah Nor Hidayati, Irva Nur Huwaida, Nisrina Iksan Iksan Jaenullah, Jaenullah Khalim, Muhammad Nur Kusumawardani, Rahma Indah Lailatul Munawaroh, Lailatul Luthfi Afani, Indah Luthfiyah, Nurul Marissa, Erni Mohamad Riyadi Mubarokah, Siti Muhamad Agus Mushodiq, Muhamad Agus Muhammad Rivai Muhammad Syaifullah, Muhammad Munawar, Endang Narto Narto, Narto Nia Indah Purnamasari, Nia Indah Nisa, Kurniaan Lailatun Novianti, Nuraini Ike Nur, Kholida Paramita, Nurhapsari Pradnya Permatasari, Irsa Ardhita Pradani, Rizki Febri Eka Pramita, Riska Dwi Pratiwi, Bety Dwi Putri, Wakhidati Nurrohmah Putri, Wakhidatul Nurrohmah Rahman, Ryan Arif Rasdi Rasdi, Rasdi Rifqi Khairul Anam Rohmah, Nafi'atu Roidah, Salma Roji, Fatkhur Rosyidi, Maulana Rozi, Muhammad Fahrur Rozikin, Ahmad Khoirur Rufaidah, Anik Rusmawati Rusmawati, Rusmawati Sofiyanurriyanti Suminto Suminto Suparno Suparno Sutarto, Auditya Purwandini Suwinda, Suwinda Syuhadak, Syuhadak Ubay Harun Ulfatun Hasanah Umi Habibah Ummi Kulsum Vivi Endar Herawati Widyaningrum, Erika Diah Ari Yusuf, Moh Hafidz Yusuf, Muhammad Hafidz Zaenal Arifin Zain, Zidan Almas