Studi Produktivitas Pekerjaan Kolom dalam Konstruksi Pembangunan Graha Pemuda Kompleks Katedral Jakarta Menggunakan Mekanisme Time Study Pradana, Bintang Akbar Adi; Widiasanti, Irika; Saefudin, Arief
Jurnal Pendidikan Tambusai Vol. 7 No. 3 (2023): Desember 2023
Publisher : LPPM Universitas Pahlawan Tuanku Tambusai, Riau, Indonesia

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.31004/jptam.v7i3.10914

Abstract

Efisiensi kerja memiliki peran penting dalam menilai keberhasilan proyek konstruksi. Tingkat efisiensi yang tinggi sangat berpengaruh pada proyek tersebut. Mempertahankan tingkat efisiensi lapangan yang stabil dengan meningkatkan sumber daya pendukungnya menjadi krusial. Oleh karena itu, penting untuk memahami faktor-faktor yang memengaruhi efisiensi. Penelitian ini bertujuan menganalisis produktivitas dalam pekerjaan kolom pada proyek pembangunan Graha Pemuda Kompleks Katedral Jakarta dan mengidentifikasi faktor-faktor yang memengaruhi produktivitas tenaga kerja. Metode studi waktu digunakan dengan fokus pada aspek teknis. Metode ini melibatkan perancangan stasiun kerja yang disepakati oleh desainer dan perusahaan. Studi waktu melibatkan variasi dalam menentukan jangka waktu yang diperlukan dengan mengacu pada waktu standar untuk tindakan yang melibatkan pekerja manusia, mesin, atau kombinasi keduanya. Penelitian ini akan memberikan wawasan tentang cara meningkatkan efisiensi dan produktivitas dalam proyek konstruksi tersebut.
Faktor Permasalahan Dalam Pengawasan Pengecekan Pada Proyek Pembangunan Graha Pemuda Kompleks Katedral Jakarta Ratfiano Nugroho; Meindito, Raihan Kazam; Ulfiah Utari; Irika Widiasanti; Zikril Hakim
Jurnal Deformasi Vol. 9 No. 1 (2024): JURNAL DEFORMASI
Publisher : Universitas PGRI Palembang

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.31851/deformasi.v9i1.15619

Abstract

Pada proyek-proyek konstruksi di lapangan, saat proses konstruksi maupun pasca konstruksi sering kali dapat kita jumpai beragam permasalahan, salah satunya adalah kerusakan hasil pengecoran beton. Permasalahan pengecoran pada sebuah proyek konstruksi gedung bertingkat adalah salah satu tantangan yang harus dihadapi karena mengakibatkan hasil pengecoran yang tidak baik berupa keretakan, kekurangan kuat tekan, dan kekurangan kuat tarik. Dengan adanya permasalahan tersebut maka dilakukan penelitian ini dengan tujuan untuk mengevaluasi serta memberikan solusi agar tidak terulang permasalahan pengecoran yang serupa. Metode yang digunakan dalam penulisan karya ilmiah ini adalah metode penelitian kuantitatif yang dilakukan dengan cara literatur jurnal-jurnal dan penelitian terdahulu. Untuk mengatasi permasalahan yang terjadi dalam pengecoran diperlukan perencanaan dengan baik terkait penjadwalan dan kebutuhan yang berkaitan dengan pengecoran. Persiapan yang baik dan tepat dalam melakukan pekerjaan pengecoran akan meminimalisir terjadinya hal-hal yang tidak diinginkan terhadap kualitas gedung
Analisis Terhadap Pekerjaan Struktur Pile Cap : Menjamin Keselamatan Dan Kestabilan Bangunan Baihakim, Ivan Maulana; Widiasanti, Irika; Fadhlurrahman, Muhammad; Marananta , Yosua; Hermafito, Aflah
Jurnal Deformasi Vol. 9 No. 1 (2024): JURNAL DEFORMASI
Publisher : Universitas PGRI Palembang

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.31851/deformasi.v9i1.15709

Abstract

Penelitian ini bertujuan untuk melakukan analisis terhadap pekerjaan struktur pile cap dengan fokus pada upaya menjaga keselamatan dan kestabilan bangunan. Metode penelitian yang digunakan adalah kombinasi (mix method) antara pendekatan kualitatif dan kuantitatif. Data kualitatif diperoleh melalui studi literatur dan wawancara, sedangkan data kuantitatif dikumpulkan melalui pengisian kuesioner. Studi ini dilakukan pada proyek konstruksi pembangunan jembatan beton di Pulau Jawa, Indonesia. Populasi penelitian meliputi pegawai dari perusahaan kontraktor, konsultan, akademisi, dan pemerintahan yang berpengalaman dalam proyek jembatan di seluruh Indonesia. Teknik sampel purposive sampling digunakan untuk pemilihan sampel. Hasil penelitian akan memberikan wawasan yang mendalam tentang faktor-faktor yang memengaruhi kinerja struktur pile cap serta identifikasi strategi perawatan yang efektif dalam menjaga keandalan pile cap dalam jangka panjang. Diharapkan penelitian ini dapat memberikan kontribusi signifikan dalam meningkatkan keselamatan dan kestabilan bangunan, khususnya dalam konteks pekerjaan struktur pile cap
Ancaman Melawan Putus Sekolah Dengan Dilema Kualitas Pendidikan Indonesia Widiasanti, Irika; Abdul, Annisa Virgiani; Nirwana, Ari; Arlita, Aurelia Della
JISIP: Jurnal Ilmu Sosial dan Pendidikan Vol 7, No 3 (2023): JISIP (Jurnal Ilmu Sosial dan Pendidikan) (Juli)
Publisher : Lembaga Penelitian dan Pendidikan (LPP) Mandala

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.58258/jisip.v7i3.5228

Abstract

Penelitian ini menggunakan metode penelitian kualitatif berupa studi pustaka untuk mengidentifikasi faktor-faktor utama yang mengancam tingginya angka putus sekolah di Indonesia dan menganalisis dampak yang timbul. Hasil penelitian menunjukkan bahwa faktor-faktor seperti kondisi ekonomi, pernikahan dini, kurangnya motivasi, dan perundungan memainkan peran krusial dalam tingginya angka putus sekolah. Dampaknya mencakup kemiskinan, kesenjangan sosial, dan kekurangan sumber daya manusia berkualitas.
Pengaruh Clash Detection Pada Proses Perencanaan Biaya Pada Laboratorium PUT Izzudin, Alwan; Widiasanti, Irika
Jurnal Talenta Sipil Vol 7, No 1 (2024): Februari
Publisher : Universitas Batanghari Jambi

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.33087/talentasipil.v7i1.466

Abstract

One effort to avoid repetitive work due to errors in construction project planning can be detected from the start by implementing BIM (Building Information Modeling) which can carry out collision analysis (Clash detection) in each discipline of structural work, architecture, MEP and other disciplines. Before the existence of BIM, clashes that occurred in the building construction process were one of the factors causing work costs to increase. So implementing Building Information Modeling is one effort to avoid these problems. In this research, clash detection analysis will be carried out in the PUT Lab building in the structural, architectural and MEP work disciplines. The stages carried out in this research were first carrying out 3D Modeling using Autodesk Revit software on the PUT Lab building, then carrying out clash detection analysis using Autodesk Naviswork software and calculating the cost budget plan for each job affected by clash detection. After carrying out clash detection, clashes can be found that occur in the structural, architectural and MEP work disciplines which after calculating the budget plan can save work costs of up to 80 million rupiah.
Pemanfaatan BIM dalam Integrasi Arsitektur dan MEP Pada Proyek Konstruksi Gedung Lab PUT PNJ Seftiani, Nadia; Widiasanti, Irika; Wangi, Intan Puspa
Jurnal Talenta Sipil Vol 7, No 1 (2024): Februari
Publisher : Universitas Batanghari Jambi

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.33087/talentasipil.v7i1.432

Abstract

Recent building construction projects increasingly prioritize the integration of architectural (design) and MEP (mechanical, electrical, and plumbing) aspects as key elements to achieve effective and sustainable projects. This study aims to explore the close relationship between architecture and MEP in building construction projects and how integrating the two can provide optimal results. This article discusses the important role of Building Information Modeling (BIM) technology in supporting the integration of architecture and MEP. BIM enables architecture and MEP professionals to work collaboratively in an integrated virtual environment, facilitating monitoring, coordination, and early identification of design conflicts. The results showed that effective use of BIM can create more efficient projects in terms of planning, execution, and maintenance. In addition, the study explores planning strategies that support the integration of architecture and MEP, including the selection of environmentally friendly materials, optimal spatial design, and energy efficiency. Comprehensive, sustainable planning can reduce environmental impact, reduce energy consumption, and reduce long-term operating costs. Project control in the context of architectural integration and MEP is also the focus of this study, with emphasis on construction quality monitoring, cost control and risk management. The success of a project often depends on careful control of these aspects. Therefore, this research provides insight into the integration of architecture and MEP in building construction projects and shows how this comprehensive approach can improve efficiency, sustainability, and sustainability as well as overall project outcomes.
Pengimplementasian Sistem Building Information Modelling Pada Tahapan Penjadwalan Gedung PUT PNJ Afriani, Budi; Widiasanti, Irika; Wangi, Intan Puspa
Jurnal Talenta Sipil Vol 7, No 1 (2024): Februari
Publisher : Universitas Batanghari Jambi

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.33087/talentasipil.v7i1.435

Abstract

In the process of achieving goals, projects have characteristics called triple constraints, including specific target time, cost, and performance requirements. The delay in the completion process in a project is what will disrupt the triple constraint which has an impact on waste. One of the reasons is that the project still uses conventional methods. This research was conducted to provide information related to conventionally designed scheduling and with the implementation of Building Infortmation Modeling (BIM), namely using several supporting software including, Naviswork, Microsoft Project and Revit at the scheduling stage of multi-storey buildings, namely at the PNJ PUT Laboratory Building. The results showed that the elaboration of scheduling planning using BIM is more efficient, easy to understand, and provides a visualization of the construction sequence and avoids waste. Then, some of the percentage of waste obtained if using conventional methods is, around 10% on materials, 40% of projects are over budget, 30% of projects are reworked, and almost 90% of projects are delayed. Thus, the implementation of BIM in project scheduling is very important to overcome things that can harm a project.
Analisis Keterlambatan Proyek PT. PP Persero Tbk Pada Pembangunan Gedung MRT Dengan Menggunakan Lean Six Sigma Framework Wijaya, Mochamad Aldi; Widiasanti, Irika
Jurnal Talenta Sipil Vol 7, No 1 (2024): Februari
Publisher : Universitas Batanghari Jambi

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.33087/talentasipil.v7i1.436

Abstract

In general, each construction project has a planned completion time with a set scheduling so that the project can run well. Indonesia is trying to develop infrastructure and public facilities such as the MRT Building Construction Project. This research was conducted at the MRT HUB Building Construction Project Simpang Temu Dukuh Atas Jalan Kendal No. 25, Menteng, Central Jakarta, Special Capital Region of Jakarta 10310 at PT. PP (Persero), Tbk This research aims to obtain factors that cause project delays. This research uses the concept of lean six sigma with the DMAIC phase (Define, Measure, Analyze, Improve, and Control). After being identified, the construction experienced delays in work completion caused by several factors such as overpurchase, delay, and inventories. Lean six sigma helps in finding solutions to minimize delays including not buying goods excessively so as not to cause delays so that workers can work properly without having to wait for the area to be worked on.
Kaitan Big Data Pada Platform Zoom dan Google Classroom Sebagai Media Penunjang Pembelajaran Widiasanti, Irika; Firsta Zanuara, Aisyah Anggie; Maulidina, Dinda Fitri; Rani Atmaja, Frima Armedia; Putri, Sabrina Rida
Sukma: Jurnal Pendidikan Vol. 7 No. 1 (2023)
Publisher : Yayasan Sukma Bangsa

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.32533/07101.2023

Abstract

Pembelajaran jarak jauh atau online semakin menjadi tren di era digital ini. Platform seperti Zoom dan Google Classroom (GCR) sangat membantu dalam mendukung pembelajaran online. Namun, bagaimana big data pada platform tersebut dapat dimanfaatkan sebagai media penunjang pembelajaran masih menjadi topik penelitian yang menarik. Artikel ini membahas tentang bagaimana big data pada platform Zoom dan GCR dapat digunakan untuk meningkatkan kualitas pembelajaran online. Dengan analisis data pengguna, personalisasi pembelajaran, dan peningkatan efektivitas pembelajaran, pengajar dapat memperoleh informasi yang sangat bermanfaat dalam menyusun strategi pembelajaran yang efektif. Namun, etika dan kebijakan privasi data pengguna harus tetap diperhatikan dalam penggunaan big data pada platform tersebut. Dalam rangka meningkatkan pembelajaran online, penggunaan big data pada platform Zoom dan GCR dapat menjadi solusi yang efektif.
OPTIMASI METODE KONSTRUKSI: MENGINTEGRASIKAN PEMBONGKARAN PONDASI DAN SALURAN BETON BERTULANG EKSISTING DENGAN METODE PEKERJAAN PONDASI BOREPILE UNTUK PEMBANGUNAN BERKELANJUTAN Widiasanti, Irika; Danavia, Thoriq Fadhil Muhammad; Pamungkas, Andaru Triza; Prayoga, Alwan; Fadhilah, Bima Rizky
Scientica: Jurnal Ilmiah Sains dan Teknologi Vol. 2 No. 5 (2024): Scientica: Jurnal Ilmiah Sains dan Teknologi
Publisher : Komunitas Menulis dan Meneliti (Kolibi)

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.572349/scientica.v2i5.1319

Abstract

Pembangunan gedung seringkali dihadapi dengan tantangan dalam penyesuaian elevasi tanah dan penggunaan ruang yang optimal. Pendekatan yang menyeluruh untuk mengatasi tantangan tersebut dengan memanfaatkan tanah eksisting dan mengintegrasikan metode pembongkaran infrastruktur eksisting dengan teknik konstruksi modern, khususnya teknik pondasi borepile. Tujuan penelitian ini untuk menyajikan analisis praktis tentang efektivitas integrasi antara pembongkaran pondasi dan saluran beton bertulang eksisting dengan penerapan teknik pondasi borepile dalam konteks pembangunan gedung yang berkelanjutan. Metode penelitian dilakukan melalui analisis terhadap pembongkaran pondasi dan saluran beton bertulang eksisting untuk persiapan tanah yang dipadatkan kembali. Selanjutnya, teknik pondasi borepile diterapkan untuk mendukung konstruksi lanjutan pada gedung yang dibangun. Hasil penelitian menunjukkan bahwa integrasi antara pembongkaran infrastruktur eksisting dengan teknik pondasi borepile secara efektif memungkinkan penggunaan tanah eksisting untuk pembangunan berkelanjutan. Proses ini menghasilkan efisiensi dalam manajemen sumber daya dan waktu konstruksi, serta meminimalkan dampak lingkungan. Dengan menerapkan pendekatan integratif ini, pembangunan gedung dapat dilakukan secara efisien dan berkelanjutan, yang merupakan langkah progresif dalam mencapai tujuan pembangunan berkelanjutan.
Co-Authors Abdul, Annisa Virgiani Achwan Wirayudha Wirayudha Adelia, Lusieta adhi purnomo Adhi Purnomo Adhi Purnomo Adjie, Raditya Nuswantoro Adrianto Oktavianus Adrianto Oktavianus Adriyan Rama Musti Afriani, Budi Agia Rezqiana Agung Fridestu Agustin, Nadiya Putri Ahmad Raby Aisyah Anggie Firsta Zanuara Aisyah Anggie Firsta Zanuara Aisyah Nur Fairus Aisyah Nur Fairus Alif Ibnu Qoyyim Alifia Najma Sholikha Alwan Izzudin Rabitsani Amanda Fitri Astari Ambar Waluny Amos Neolaka Andaris, Hanif Ahmad Anisah Anisah Anisah Anjali Indriyanti Putri Annisa Ayu Yuslina Arief Saefudin Arlita, Aurelia Della Asri Juwita Sari Astrid Wardani Oktafiani Astrid Wardani Oktafiani Asyifa Eka Rahayanti Aulia Putri Aulia, Hidayatul Bagus Septianto BAGUS TRI PRASETYA Baihakim, Ivan Maulana Bintang Akbar Adi Pradana Bintang Prasetyo Budi Afriani Budi Afriani Danavia, Thoriq Fadhil Muhammad Danilo V. Rogayan Jr. Darussyamsu, Rahmawati Dea Astriani Deiharianja, Hosiana Gracia Dela Widiastuti Devitasari, Keisha Andani Dhiya Thahur Dhiya Thahur Dinda Annisa Firdaus Dinda Fitri Maulidina Dinda Fitri Maulidina Dwi Seftiani Syafitri Eka Murtinugraha Elmi Yuntafa Erna Septiandini Esa Aryo Kuncoro Esa Kuncoro Fadhilah, Bima Rizky Fadhlurrahman, Muhammad Faisol Shahab Faisol Shahab Fanny Yustia Zahra Fari Razan Hammadi Fathoni, Ariq Yusron Fatin, Adzra Padika Fazla Mawla Yumadia Febriyanti, Ine Firsta Zanuara, Aisyah Anggie Fitria Hamidah Frima Armedia Rani Atmaja Frima Armedia Rani Atmaja Gina Bachtiar Giry Marhento Gita Aqila Nirvia Gita Lestari, Mayang Gita Rianing Tiyas Hendrica Etmi Primarini Henita Rahmayanti Herdy Dwiyana Hermafito, Aflah Huda Darussyafa Husna, Ajizah Kamila Ida Farida Ilmi Zajuli Ichsan Intan Puspa Wangi, Intan Puspa Isaak Aldo Riski Bagas Isil Koc Izzudin, Alwan Jamarudin, Zaki Rachman Jessica Triuli Adelia Kamal, Aulia Az-Zahra Kania Zahrah Khairunnisa, Rafifah Koc, Isil Lenggogeni Lenggogeni Lenggogeni Lenggogeni Lenggogeni, Lenggogeni Lestari, Nadhiya Putri Linda Widianingsih Luthfia Rosidin Madhuma Acharee Nazhelya Najva Marananta , Yosua Maria Felicita Viola Maulana, Arris Maulidina, Dinda Fitri Meindito, Raihan Kazam Meyra Daniarista Mochamad Aldi Wijaya Mufaziz, Dzaky Muhammad Alfarizi Muhammad Alfarizi Muhammad Fadhlurrahman Muhammad Haristo Rahman Muhammad Ilham Ardiansyah Nabilla Fairani Yusdah Nadia Fanny Renita Nadia Seftiani Nadiatul Huliyah Nafi'atussalwa, Nafi'atussalwa Nirwana, Ari Nisa Wulandari Noval Anki Ramadhan Noval Anki Ramadhan Novyanti, Yuwita Nugraha, R. Eka Murti Nur, Dewi Az-Zahra Nuraty, Garnish Nioko Nurfadhilah Nurfadhilah Nurfadhilah, Nurfadhilah Nyssa Talitha Adhetri Olivia Aziza Balqis Olivia Aziza Balqis Pamungkas, Andaru Triza Pardosi, Yoselin Pradana, Bintang Akbar Adi Prayoga, Alwan Primarini, Hendrica Etmi Puja Istiqoma Puti Farida Tamin Puti Farida Tamin Putri, Sabrina Rida R. Eka Murti Nugraha R. Eka Murtinugraha R. Eka Murtinugraha R. Eka Murtinugraha Rafika Fitriah Rahmadani, Shalasha Rahmawati Darussyamsu Rani Atmaja, Frima Armedia Ratfiano Nugroho Rendi Noval Erlangga Rezi Berliana Yasinta Richard Yordan Suryapratama Ridwan Baihaqi, Moch Rika Sa’diyah Rizal Z. Tamin Rogayan Jr., Danilo V. Rosmawita Saleh Sabrina Rida Putri Sabrina Rida Putri Saefudin, Arief Saffiyarana, Qonita Santoso Sri Handoyo Sa’diyah, Rika Seftiani, Nadia Sembiring, Rinawati Septiana Elfrida Sihotangi Serina Anggraini Sittati Musalamah Sopyan Galih Sukmo Surendra, Faiz Swaraswati Kemala Dewi Sya'bani, Nur Achmad Syafiq Human Maulana Syahnadhea Zahra Syaidah, Siti Tasliah, Siti Titin . Titin Titin Tri Putra Rizky, Ilham Tuti Iriani Ulfiah Utari Veithzal Rivai Zainal Wibowo, Farah Qonita Dzakiyyah Wijaya, Mochamad Aldi Yasinta, Rezi Berliana Yose Architio Septiawan Zahrani, Maulidina Zia Rizki Amalia Zikril Hakim